Construction (Design and Management) Regulations 2015 Flashcards

1
Q

What are the key aims of CDM 2015?

A

Intended to ensure that H&S issues are properly considered during a project’s development so that the risk of harm to those who have to build, use and maintain structures is reduced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who are the duty holders in CDM 2015?

A
  • Client (commercial and domestic)
  • Principal designers
  • Principal contractors
  • Designers
  • Contractors
  • Workers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the client’s responsibilities under CDM 2015?

A
  • Making suitable arrangements for managing a project
    • Appointing the principal designer and principal contractor.
    • Allowing sufficient time and resources for each project.
    • Making sure that any principal designer and principal contractor appointed carry out their duties.
    • Making sure suitable welfare facilities are provided for the duration of the work.
  • Maintain and review the management arrangements for the duration of the project.
  • Provide pre-construction information to all.
  • Ensure the principal contractor prepares a construction phase plan.
  • Ensure the principal designer prepares a health and safety file.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the principal designer’s responsibilities under CDM 2015?

A
  • Plan, manage, monitor and coordinate health and safety in the construction phase.
  • Advise the client in bringing together pre-construction information.
  • Work with any other designers on the project to eliminate foreseeable health and safety risks.
  • Ensure that everyone involved in the pre-construction phase communicates.
  • Liaise with the principal contractor, keeping them informed of any risk.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the principal contractor’s responsibilities under CDM 2015?

A
  • Plan, manage, monitor, and coordinate the entire construction phase.
  • Take account of the health and safety risks.
  • Liaise with the client and principal designer.
  • Prepare a written construction phase plan.
  • Arrangements in place for managing health and safety throughout.
  • Consult and engage with workers about their health, safety and welfare.
  • Ensure suitable welfare facilities are provided.
  • Check that anyone the contractor appoints has the expertise.
  • Ensure all workers have site specific inductions.
  • Prevent unauthorised access to the site.
  • Liaise with the principal designer to share any information.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What should the Pre-construction Information Pack include?

A
  • Description of works
  • Description of site
  • Members of design team
  • Site location
  • Welfare facilities
  • Existing documentation
  • Photographic schedule
  • Access strategy
  • Emergency procedures
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What should the Construction Phase Plan include?

A
  • A description of the project
  • Health and safety aims for the project
  • Arrangements to ensure cooperation between project team members
  • Site rules
  • Arrangements for involving workers
  • Site induction
  • Welfare facilities
  • Fire and emergency procedures
  • The control of any of the specific site risks listed in Schedule 3 of CDM 2015 where they are relevant to the work involved.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When is an F10 notification required?

A
  • Last longer than 30 working days (do not have to be consecutive) and have more than 20 workers working simultaneously at any point in the project OR
  • Exceed 500 person days (a person day being one shift of say 8 hours).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When does CDM apply?

A

When there is more than one contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly