CONSTRUCTION Flashcards

1
Q

To compress 2.8 m3 of free air per minute from atmospheric (0.101 N/mm2) to (0.7 N/mm2 indicated on the gauge (i.e. 8.01 bar absolute) requires a compressor with a theoretical power value
Theoretical power = 103 Γ— 0.101 Γ— v1 log

A. 9.7 kW or 11.3 hp
B. 7.9 kW or 11.3 hp
C. 9.7 kW or 13.1 hp
D. 7.9 kW or 13.1 hp

A

9.7 KW /13.1 HP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The density of air decreases with increasing altitude and thus for a compressor operated above sea level, k should be reduced. For example, to compress 2.8 m3 of air per minute from 0.05 N/mm2 (atmospheric pressure) to 0.801 N/mm2 (absolute pressure) requires a compressor with a power value of
A. 7.46 kW B. 6.47 kW C. 7.64 kW D. 6.74 kW

A

6.47 KW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Calculate the pressure loss for a 200 m length of 50 mm diameter pipe, resulting from delivering 10 m3/min (free air) compressed to 7 bar, i.e. 8 bar absolute. Use 𝑓 = 82 Γ— 103 for steel pipes.

A. 0.64 bars
B. 0.44 bars
C. 0.46 bars
D. 0.66 bars

A

0.46 bars

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A drill hole of diameter d (mm), with the bottom charge extending 1.3B from the base, contains explosive of unit weight P kg/m3, thus
𝑃 Γ—πœ‹π‘‘2 Γ—1.3𝐡=𝑄′′ 1064𝑏
𝑄′′ =𝑓×0.8×𝑆(1.4π‘Ž 𝐡2 +1.4π‘Ž 𝐡3)+(π‘Ž +𝑏 )𝐡4 𝑏𝑀𝐡2344
When f = 1, S/B = 1, w = 1, P = 1000, a2 = 0.07, a3 = 0.4, and terms with B4 are ignored. When d = 50 mm, then B is

A. 1.0 m B. 1.5 m C. 2.0 m D. 2.5 m

A

1.5 m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Wells are founded in a circular pattern around an excavation 30 m long and 25 m wide. The height of the water table above an impermeable stratum is 9 m. The depth of the excavation is 5 m and the water table lies 1 m below ground level. The coefficient of permeability of the soil k = 0.002 m/s. Determine the required number of wells.
A. 25 wells B. 15 wells C. 35 wells D. 45 wells

A

15 wells or 20 wells

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Determine the hourly production of 0.57 m3 capacity backhoe, excavating a foundation 3 m deep in common earth.
A. 33 m3/h B. 44 m3/h C. 55 m3/h D. 66 m3/h

A

44 m^3/hr

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Trucks are loaded by a 1 m3 capacity tracked loader machine at the rate of 30 m3/h bulked material. The truck transports the material to a tip 3 km away. Select the size and number of trucks required.
Select truck size, say, loader bucket capacity x 5 = 5 m3 capacity truck.
Minutes Load time = 60/30 x 5 ………………………………….. 10 Cycle time to tip and back (average speed, 20 kph) .. 18
Dumping, turning and accelerating ……………………. 3 β€”-
31

A. Four 4 m3 capacity
B. Three 5 m3 capacity
C. Five 2 m3 capacity
D. Two 3 m3 capacity

A

Three 5 m^3 capacity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Trucks arrive at an excavator from distribution points on a large earthmoving project. The arrival time intervals of the trucks are observed and yield the following results.
Arrival time interval (min) Frequency (%)
2 10
3 15
4 30
5 25
6 20
The time taken to load the trucks, which are either 6 or 12 m3 capacity, are fairly constant at 3 and 5 min, respectively, and
both types are equally represented in the fleet.
If the excavator loads each of the trucks immediately it arrives, in the order that it arrives, calculate the total time that the excavator and trucks will be waiting in any one period of two hours selected at random.
A. Waiting time of excavator = 12 min; of trucks = 12 min
B. Waiting time of excavator = 16 min; of trucks = 16 min
C. Waiting time of excavator = 12 min; of trucks = 16 min
D. Waiting time of excavator = 16 min; of trucks = 12 min

A

Waiting time of excavator: 12 mins.
Waiting time of trucks: 16 mins.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Quarry rocks of 350 mm size are delivered to a crushing plant at a rate of 50 t/h. The sizes required are
38 mm to 19 mm
19 mm to fines
Select appropriate crushers and screens.
Hint: Maximum allowable size of material = 0.8 x feed opening

A. 438 mm
B. 348 mm
C. 384 mm
D. 483 mm

A

Size = 438 mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A large number of test results produce a standard deviation (s) a 1.5 N/mm2, and average strength 10 N/mm2. If 5% of results are permitted to fail, what should be the minimum design strength of the mix?
Hint: π‘₯ = 𝑐̅ βˆ’ 𝑍𝑠
A. 6.70 B. 7.06 C. 7.60 D. 6.07

A

7.06

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Calculatethemaximumpressureproducedwhen placing 75 mm slump concrete at a rate of 2m/h, shuttering 2.5 m high and 250 mm wide. Assume the temperature of the concrete in the formwork is initially 15Β°C and vibration is continuous.

A

46 kpa
55 kpa
56 kpa (arching)
62.5 kpa (height)
80 kpa (Stiffness)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Although paving machines are capable of travelling at 20 m/min or more, the logistical problems of supplying large quantities of concrete commonly result in no more than about 1000 m of pavement being laid during a typical day of production. Thus for a 9 m wide road 200 mm deep and a 50% efficiency factor, what is the production output in m3/h?

A. 115.2
B. 215.1
C. 112.5
D. 251.1

A

112.5 m^3/h

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

β€”β€”β€” occupy about β€”β€”β€” of the volume of concrete and are obtained either from naturally occurring deposits of sands and gravels, including sea-dredged material, or are produced by crushing quarried rock.

A

75%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

While the quality and grading of the aggregate are important, the strength of concrete depends mainly on the

A

WATER CEMENT RATIO

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

the degree of stiffness of the mix and can be directly altered by changing the water/cement ratio.

A

Workability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

a conical mould is filled in three equal layers and rodded 25 times per layer.

A

Slump Test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

concrete is dropped from vessel to
vessel and finally into cylinder.

A

Compaction factor test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

is used for very stiff concrete mixes and consists of vibrating a standard slump test specimen placed in a specified vessel.

A

Vabe Test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

is designed for a very high workability mixes, i.e. those almost of flowing consistency.

A

DIN Test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Strength continues to improve provided sufficient water is supplied to the set concrete to ensure that drying out during the heat of hydration stage is prevented, otherwise the chemical reactions which allow strength to be developed, will cease. The process is known as

A

Curing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

occurs as concrete hardens, being greater in wet mixes. Curing helps to limit its effect and therefore concrete in the actual structure should be thoroughly and continuously moistened for some considerable period after placing.

A

Shrinkage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The time between mixing and placing should not exceed β€”β€”minutes.

A

45 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Good practice would normally require the transport distance from batching plant to paving unit to lie within β€” km.

A

3 km

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Matchlist

A

DIFFERENCE BETWEEN TOTAL AND FREE FLOAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Activity E

A

10 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Project Logic MNOP

A

17 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Critical activity in AOA Network

A

Zero float

28
Q

Air entered in Portland Cement

A

72.18 cu. m

29
Q

Warn road users

A

Warning signs

30
Q

Guide signs

A

Rectangle

31
Q

A-B-C-D-E-F-G-H-I-J-K-L

A

36

32
Q

Normal and Accelerated concrete
CRITICAL PATH?

A

A-C-E-F

33
Q

COST FOR MINIMUM DURATION

A

23400

34
Q

NO. OF DAYS DEDUCTED FROM THE NORMAL CONDITION SO THAT IT WILL BE ECONOMICAL

A

4

35
Q

Device mounted on a fixed support (permanent signs) or potable support (temporary signs)

A

Road Work Signs

36
Q

Process of proportioning Cement, water, aggregate and additives

A

Batching

37
Q

To level a floor or layer of concrete with a straight edge using a back and forth motion while moving across the surface

A

Screeding

38
Q

Inform and advice road users f directions, distances, routed, the location of services for road users and points of interest.
A. Cross road signs
B. Guide Signs
C. Advance direction signs
D. Traffic instruction signs

A

Guide signs

39
Q

Are written instructions detailing how the facility is to be constructed
A. Specifications
B. Estimates
C. Bid documents
D. Plans

A

Specifications

40
Q

What is bulk composition of conc.
A. Portland Cement
B. Water
C. Aggregates.
D. AOTA

A

AOTA

41
Q

JAW CRUSHER

A

2.9 cu. m

42
Q

Determine the rated size of air compressor

A

49.1 cu. m/min

43
Q

Design lateral force for the slab

A

1.46 KN/m

44
Q

Maximum Lateral Pressure

A

28.7 KN/m. sq.

45
Q

Estimate the quantity of mortar required

A

981

46
Q

Total Volume of Brick

A

0.53 cu. m

47
Q

Minimum pressure

A

600 lb/ft.sq
28.7 KPA

48
Q

Hourly production of 3/4 cu. yd capacity backhoe
In-place production rate

A

48 cu. m/hr

49
Q

Crawler crane

A

4150 kg

50
Q

TRUCK MOUNTED

A

7.33 tons

51
Q

Crawler crane

A

4150 kg

52
Q

Crane

A

5 tons

53
Q

Shovel

A

6

54
Q

Slip and rimpull

A

Not slip and 57 KN

55
Q

Jaw crusher

A

2.9 cu. m

56
Q

No. Of haulens

A

11 trucks and 212 BCM/hr

57
Q

No. of pusher

A

112 BCM/hr

58
Q

No. Of scraper

A

2 & 3

59
Q

Ct= 0.5 - 0.3

A

178 LM/hr

60
Q

24.1 km of gravel road require reshaping and leveling, how many grader hours?

A

23.1h

61
Q

Trial blasting

A

6.8

62
Q

Volume of plastic concrete

A

0.51 cu.m

63
Q

Actual weight with excess 5% moisture on sand and 2% in gravel

A

Water 63 kg
Sand 447 kg
Gravel 560 kg

64
Q

Safe load bulb pile

A

164t

65
Q

Total number of brick

A

981

66
Q

Max safe unsupported height heavyweight concrete block

A

1.9 m