Conflict Avoidance and Management Flashcards

1
Q

What are causes of dispute?

A

Differing terms between parties

Poor construction of contract/agreement

Lack of open communication between parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How should a contract be written to avoid dispute?

A

Be applicable to type of work and location

Includes warnings for parties to communicate problems early on

Good contract management

Viable Compensation Event Procedure (CEP)

No ambiguity

Simple English, avoiding legal terms and jargon

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are examples of Alternative Dispute Resolution (ADR)?

A

Mediation
Arbitration
Conciliation
Adjudication
Independent Expert Determination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the benefits of ADR over litigation?

A

Quicker
Less formal
Cheaper
Private

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is mediation?

A

Mediator helps parties reach an agreement themselves.

May gives suggestions but wont advise.

Parties then sign document agreeing to the settlement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is arbitration?

A

More formal than mediation.

Tribunal process

Independent arbitrator who hears both sides of the dispute before making a decision.

Decision is binding and can be enforced through the courts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is conciliation?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is adjudication?

A

Subject to contract provisions to the contrary, the adjudicator’s decision is binding unless either party commences court/arbitration proceedings.

Adjudicator is either names in the contract or the parties agree to a nominating body (usually RICS adjudication service).

Party who wants to enforce adjudication must issue a notice to the nominated person/body and they must appoint an adjudicator within 7 days.

No opportunity to voice opinion, only the review of documentation.

Decision is made within 28 days.

Both parties must meet their own costs unless they have agreed for the adjudicator to have the power to award costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is PACT?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Independent Expert Determination?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the RICS Dispute Resolution Service?

A

Helps find the right ADR solver, provides and explains options.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are methods for avoiding dispute?

A

Risk management (early warning)

Partnering (alliancing)

Effective client briefing

Conflict Avoidance Pledge

Dispute Resolution Board

Dispute Resolution Advisor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How is an early warning system implemented in regards to risk management?

A

Identify risk areas so all parties can deal with potential problems before they happen.

Implemented throughout a project to assess how risks previously identified are currently performing.

Early warning meeting should discuss how to mitigate and avoid impacts on the project.

Contract should include obligations for parties to identify and communicate problems early.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is partnering (alliancing)?

A

A collaborative management approach that encourages openness and trust between parties to a contract.

The parties become dependent on one another for success, and this requires a change in culture, attitude, and procedures throughout the supply chain.

Most used on large, long-term or high-risk contracts.

Contract should specify that parties are required to work together to find solutions and actions for the benefit of all involved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Conflict Avoidance Pledge?

A

Demonstrates commitment to conflict avoidance and the use of amicable resolution procedures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a Dispute Resolution Board?

A

Board of 1-3 people assisting contracting parties throughout the life of a project to help avoid, manage, and resolve disputes in real-time, by identifying issues early on.

17
Q

What is a Dispute Resolution Advisor?

A
18
Q
A