What are project risks?
Project risks are unfavourable events that jeopardize the achievement of one or more stakeholders project objectives on time
What are product risks?
Any risk that adversely impacts the quality of the products. Includes failures, incomplete or erroneous data and inadequate competence of testers
What are the four things you can do to deal with risks in a project?
- Ignore the risk
- Mitigate the risk
- Create a contingency plan
- Transfer the risk to another party
What are the common risk types that can occur in project?
- Supplier Issues
- Organizational Issues
- Product changes
- Test environment issues
- Fault test items
- Technical problems
What are the four sections of the IEEE incident report template?
- Incident report identifier
- Incident Summary
- Incident description
- Impact
What does a Change Control Board (CCB) do?
Analyses the incidents reported during testing and decides how to handle them. Responsible for conflict resolution and release management