Conditions, Breach, and Repudiation Flashcards

1
Q

Definition of Condition

A

An event or non-event that must occur before performance is due

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Result of failure of condition

A

Contract is voidable - thus if we start changing terms then these are counteroffers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Conditions v Promises

A

Promises are broader and do not void a contract (courts see conditions are drastic); if a court is unsure if it’s a promise or condition, typically say it is a promise (and you could sue for damages, but not void contract) – NOTE: this should incorporate Interpretation (above) and the rules – this is codified in §227 “interpretation preferred that will reduce risk of forfeiture” (aka voiding)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Event that Terminates a Duty (formerly called condition subsequent)

A

§230 says events can cancel duties UNLESS either (a) not in good faith OR (b) impracticable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Condition of Personal Satisfaction

A

if only aesthetic, watch out – probably cannot void this; typically courts try to find an objective standard (like an architect etc) and will use this if the architect or other expert is acting in good faith. But if its entirely subjective than this condition will hold. Ex of I don’t like this self-portrait and I am not paying -> you can do this §228

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Types of conditions

A

Express Conditions: Either in writing or through actions
Implied Conditions: Sometimes called implied-in-fact Ex) the concert I am renting will exist on rental date (some courts can construe actions as implied-in-fact conditions)
Constructive Conditions: Court decides to read in a condition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Common condition - order of performance

A

Typically the person whose task takes the longest should start first – ex) if you are building my house a common constructed condition is that payment due at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Pay-if paid vs pay-when paid

A

example of promise (pay-when paid) vs condition (pay-if paid)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Severability

A

Whatever provision of a contract cannot be enforced can be CUT OUT of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Severability clause

A

most contracts have a clause saying it is severable (explicitly)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Agreed Equivalents (Restatement §183)

A

“agreed equivalents” of pairs of performances is allowed as long as it (a) does not violate public policy and (there is no serious misconduct)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Partially performance as agreed equivalents

A

if task is partially performed, court can sever performance off and enforce the other half of as a pair of duties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Installment Contract

A

UCC Severability - UCC - §2-612 –(1) even if agreement explicitly states “each delivery is separate contract” UCC will treat as an installment contract (2) may reject non-conforming goods BUT if seller gives assurance of cure they must accept installment (3) HOWEVER, if the value of the contract is decreased because non-conformity (Ex. does not send the motherboards) can reject UNLESS the aggrieved party accepts the goods without seasonable notification, or the issue is with prior accepted installments or future installments (aka not the installment at issue here)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Types of breaches

A

(1) Total and material breach – Remedy: (a) withhold payment (b) terminate contract (c) sue for damages
(2) Material breach – Remedy: (a) suspend performance (b) wait for cure (C) sue for damages
(3) Immaterial breach – Remedy: sue for damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do I know if breach is material?

A

5 factors - see §241 – (1) deprivation of reasonably expected benefit (2) extent to which compensation is possible (3) risk of forfeiture (4) likelihood of curing (5) whether it was in good faith. THUS, if the breach deprives other party of reasonable benefits, compensation is possible, it goes to the heart of the contract, the other party is unlikely to cure, and it was in bad faith -> DEF a material breach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Materiality of breach if substantial performance

A

If you have done a substantial part of performance, the courts will NOT view it as a material breach: Helpful case = Jacobs & Youngs v Kent – No Reading pipe case, house was already built – not a material breach

17
Q

Materiality of breach if contract explicitly states the unfulfilled term

A

Court may still “waive the non-occurrence of a condition” in this case

18
Q

Breach under the UCC

A

“Perfect Tender Rule” – UCC use perfect tender, any goods not as outlined in contract are nonconforming goods

19
Q

Breach Under UCC - What can buyer do if good nonconforming

A

May reject all, may partially reject and accept a “commercial unit”, or may accept

20
Q

Breach Under UCC - Accepting/Rejecting non-conforming goods

A

You (the buyer) accept when you either (a) do NOT tell they are non-conforming in reasonable about of time OR (b) fail to reject OR (c) does any act inconsistent with seller’s ownership

21
Q

Breach Under UCC - Curing

A

First issue: is the contract due? If there is time left on contract, seller must notify BUT has remaining time to cure; If there is not time left on contract, with or without money allowance may notify buy and you get a reasonable time to cure

22
Q

Breach under UCC - Revoking acceptance

A

Revocation (§2-608) - May revoke acceptance (HIGH BAR) IF either (a) you assumed it would be cured OR (b) buyer did not discover issue because INDUCED assumption of (1) seller said it would be okay OR (2) it would have been difficult to discover

23
Q

Repudiation (Same in Restatement as UCC)

A

Cancellation of performance after a contract is formed (risky)

24
Q

Options after repudiation

A

§2-610 – Options – (1) Buyer Waits (2) Buyer Seeks Remedy OR (3) Buyer suspends own performance (risky!)

25
Q

Retraction of repudiation under UCC

A

§2-611 – Retraction of Repudiation – Can retract UNLESS (1) material reliance of other party OR (2) Notice of acceptance

26
Q

Demanding adequate assurance (same in UCC/Restatement)

A

When you have “reasonable grounds” that other party is insecure or insolvent

27
Q

Adequate assurance rules UCC

A

If you reasonably suspect insecurity, you MUST DEMAND IN WRITING. Until adequate assurance, you can suspend performance

(1) If both merchants – adequacy of assurance determined by commercial standard
(2) If after a “justified demand” no adequate answer AT MOST 30 days, contract is void

28
Q

Excusal of Condition (by the courts)

A

(1) Disproportionate forfeiture (e.g. Reading Pipe case)
(2) Other party tells you they will perform
(3) Bad faith – Life insurance company denying coverage in bad faith
(4) Waiver – cannot waive material conditions without consideration but can waive immaterial conditions; think fire insurance company that should have known building was unoccupied