CompTia Project Glossary - Part 02 Flashcards

1
Q

A standard of measurement that specifically defines how something will be measured.

A

metric

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A major deliverable or key event in the project used to measure project progress.

A

milestone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

This project process group is where activities are performed to monitor the progress of the project and determine whether there are variances from the project plan. Corrective actions are taken during this process to get the project back on course.

A

monitoring and controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A project that is initiated by multiple business units.

A

multiple business unit project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Negotiating is a leadership technique and a conflict - resolution technique. Negotiating is the act of two or more parties explaining their needs and coming to a mutual agreement on a resolution.

A

negotiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Evaluation of the cash inflows using the discounted cash flow technique, which is applied to each period the inflows are expected. The total present value of the cash flows is deducted from the initial investment; this assumes that cash inflows are reinvested at the cost of capital. It is similar to discounted cash flows.

A

net present value (NPV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A depiction of project activities and the interrelationships between these activities.

A

network diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Operations typically involve ongoing functions that support the production of goods or services. They don ? t have a beginning or an end.

A

operations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A high - level estimate of the time and cost of a project based on the actual cost and duration of a similar project.

A

order of magnitude

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The process of addressing factors that may impact how to manage a project team, defining roles and responsibilities for project team members, identifying how the project team will be organized, and documenting a staffing management plan.

A

organization planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A quantitatively based estimating technique that is typically calculated by multiplying rate times quantity.

A

parametric estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A Quality Control technique used to rank importance of a problem based on its frequency of occurrence over time. This diagram is based on the Pareto principle, more commonly referred to as the 80/20 rule , which says that the majority of defects are caused by a small set of problems

A

pareto diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The length of time it takes a company to recover the initial cost of producing the product or service of the project.

A

payback period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Collecting information regarding project progress and project accomplishments and reporting it to the stakeholders, project team members, management team, and other interested parties. It also makes predictions regarding future project performance.

A

performance reporting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

cost of work that ? s been budgeted for an activity during a certain time period.

A

planned value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The process group where the project plans are developed that will be used throughout the project to direct, monitor, and control work results. The primary result of this process is the project plan.

A

planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Performed when a project is canceled or ends prematurely. It describes the reasons for cancellation or failure and documents the deliverables that were completed.

A

post-mortem analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Conducted at the end of the project to document lessons learned.

A

post-project review

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A network diagramming method that places activities on nodes, which connect to dependent activities using arrows. Also known as activity on node .

A

precedence diagramming method (PDM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A task on the network diagram that occurs before another task.

A

predecessor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

An investigation at project request time to determine the costs and benefits of the project, as well as examine alternatives to the proposed solution in order to determine the feasibility of carrying out the project

A

preliminary investigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A type of change request that usually occur during the Monitoring and Controlling process group. Preventive actions are implemented to help reduce the probability of a negative risk event.

A

preventative action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

A Quality Control tool and technique that keeps errors from reaching the customer. Prevention is less expensive than having to fix problems after they ? ve occurred.

A

prevention

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

The cost of activities performed to avoid quality problems, including quality planning, training, and any product or process testing.

A

prevention costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

The likelihood a risk event will occur. Probability is expressed as a number between 0.0 and 1.0.

A

probability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

The process of identifying what goods or services will be purchased from outside the organization. It uses make - or - buy analysis to determine whether goods or services should be purchased outside the organization or produced internally.

A

procurement planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Explains the major characteristics of the product and describes the relationship between the business need and the product. This is also referred to as high - level requirements .

A

product description

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Occurs in the Close Procurements process and determines whether the work of the contract is acceptable and satisfactory.

A

product verification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

A grouping of related projects that are managed together to capitalize on benefits that couldn ? t be achieved if the projects were managed separately.

A

program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Calculates the expected value, or weighted average, of critical path tasks to determine project duration by using three estimates: most likely, pessimistic, and optimistic. The PERT calculation is (optimistic + pessimistic + (4 ? most likely)) / 6.

A

program evaluation and review technique (PERT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Reports from project team members listing the tasks each team member is working on, the current progress of each task, and the work remaining.

A

progress reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Temporary in nature, with a definite start and end date; creates a unique product, service, or result. It is completed when the goals and objectives of the project have been met and signed off on by the stakeholders.

A

project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

An organizational structure focused on projects. Project managers generally have ultimate authority over the project, and sometimes supporting departments such as human resources and accounting might report to the project manager. Project managers are responsible for making project decisions and acquiring and assigning resources.

A

project-based organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

The person who fully understands, believes in, and espouses the benefits of the project to the organization. This is the cheerleader for the project.

A

project champion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

An official, written acknowledgment and recognition that a project exists. It ? s signed by the project sponsor and gives the project manager authority to assign organizational resources to the work of the project.

A

project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

The formal acceptance of a project and the activities required to formally end the project work.

A

project closure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Documents the key characteristics of the product or service that will be created by the project.

A

project description

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Carrying out the project plan. Activities are clarified, the work is authorized to begin, resources are committed and assigned to activities, and the product or service of the project is created. The largest portion of the project budget will be spent during this process.

A

project execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Documentation in the project charter that includes the reason the project is being undertaken and the business need the project will address.

A

project justification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

The grouping of project phases in a sequential order from the beginning of the project to the close.

A

project life cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Applying skills, knowledge, and project management tools and techniques to fulfill the project requirements.

A

project management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

The world ? s leading professional project management association.

A

Project Management Institute (PMI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

The nine project management groupings, or Knowledge Areas, that bring together common or related processes. They are Integration, Scope, Time, Cost, Quality, Human Resource, Communications, Risk, and Procurement

A

project management knowledge areas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Established by organizations to create and maintain procedures and standards for project management methodologies to be used throughout the organization.

A

project management office (PMO)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

The person responsible for applying the skills, knowledge, and project management tools and techniques to the project activities to successfully complete the project objectives.

A

project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Measures that the project manager uses to determine whether the project is on track, such as any deviation from the baseline schedule or the baseline budget.

A

project performance indicators

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

A document, or assortment of documents, that constitutes what the project is, what the project will deliver, and how all the processes will be managed. Used as the guideline throughout the project Executing and Controlling phases to track and measure project performance and to make future project decisions. Also used as a communication and information tool for stakeholders, team members, and management.

A

project plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

A formal presentation by the project manager or project team members to the sponsor, the client, and the other executive stakeholders.

A

project review

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Determines the start and finish dates for project activities and assigns resources to the activities.

A

project schedule

50
Q

Used to determine which proposed projects are approved to move forward.

A

project selection

51
Q

A project that undertakes to prove that a specific activity can be done or an idea can be accomplished.

A

proof of concept

52
Q

Determining the impact of identified risks on the project and the probability they?ll occur. Aligns risks in a priority order according to their effect on the project objectives.

A

qualitative risk analysis

53
Q

Monitoring work results to see whether they fulfill the quality standards et out in the quality management plan; determines whether the end product conforms to the requirements and product description defined during the planning processes.

A

quality control

54
Q

Describes how the project management team will enact the quality policy and documents the resources needed to carry out the quality plan. It describes the responsibilities of the project team in implementing quality and outlines all the processes and procedures the project team and organization will use to satisfy quality requirements.

A

quality management plan

55
Q

Identifying the quality standards applicable for the project and how they ? ll be fulfilled.

A

quality planning

56
Q

A complex analysis technique that uses a mathematical approach to numerically analyze the probability and impact of risk events.

A

quantitative risk analysis

57
Q

A duration estimate obtained by applying a productivity rate of the resource performing the task.

A

quantitatively based durations

58
Q

A type of responsibility assignment matrix that describes the resources needed for the task and their role for that task using the following descriptors: responsible, accountable, consult, or inform.

A

RACI chart

59
Q

Setting a new project baseline because of substantial changes to the schedule or the budget.

A

rebaselining

60
Q

This process is where the project manager gathers and documents the collection of baseline data for the project. Baseline data includes cost, schedule, scope, and quality data. Performance report information is delivered to the stakeholders at project status meetings and steering committee meetings

A

Report Performance

61
Q

A document that is sent out to potential vendors requesting them to provide a proposal on a product or service.

A

request for proposal (RFP)

62
Q

The specifications and characteristics of the goal or deliverable.

A

requirement

63
Q

A process that defines and documents all the resources needed and the quantity of resources needed to perform project activities, including human, material, and equipment resources.

A

resource planning

64
Q

A listing of all the job titles within a company or department with a brief description of the job. It may also identify the number of people currently employed in each job title.

A

resource pool description

65
Q

A document containing a description of the resources needed from all three resource types for work package items from the WBS.

A

resource requirements

66
Q

A resource chart that defines the WBS identifier, the resource type needed for the WBS element, and the quantity of resources needed for the task. A WBS is displayed in chart form.

A

responsibility assignment matrix (RAM)

67
Q

An update to the approved start or end date of the schedule baseline, typically a result of approved scope changes.

A

revision

68
Q

An action that is taken as a result of quality activities to correct a defect.

A

rework

69
Q

A potential future event that can have either negative or positive consequences.

A

risk

70
Q

The process used to identify and focus on those risks that are the most critical to the success of your project.

A

risk analysis

71
Q

Identifying the potential project risks and documenting their characteristics.

A

risk identification

72
Q

A numbered list of risks that are produced during the risk identification process and that are documented within a risk register.

A

risk list

73
Q

Details how risk management processes will be implemented, monitored, and controlled throughout the life of the project. It does not define responses to individual risks.

A

risk management plan

74
Q

The process that involves implementing the risk response plan, tracking and monitoring identified risks, and identifying and responding to new risks as they occur.

A

risk monitoring and control

75
Q

Identifying, analyzing, and determining how risk events will be managed for a project.

A

risk planning

76
Q

A process that describes how to reduce threats and take advantage of opportunities, documents the plan for negative and positive risk events, and assigns owners to each risk.

A

risk response planning

77
Q

An event that warns a risk is imminent and a response plan should be implemented.

A

risk trigger

78
Q

A Quality Control tool and technique that shows variation in the process over time or shows trends such as improvements or the lack of improvements in the process.

A

run chart

79
Q

The final, approved project schedule that is used during project execution to monitor project progress.

A

schedule baseline

80
Q

The process of documenting and managing changes to the project schedule.

A

schedule control

81
Q

Calculating and preparing the schedule of project activities, which becomes the schedule baseline. It determines activity start and finish dates, finalizes activity sequences and durations, and determines activity duration estimates

A

schedule development

82
Q

Measures the progress to date against the progress that was planned. The SPI indicator acts as an efficiency rating. If the result is greater than one, performance is better than expected, and you ? re ahead of schedule. If it ? s less than one, performance is less than expected, and you ? re behind schedule. The formula is SPI = EV / PV.

A

schedule performance index (SPI)

83
Q

Any change that is made to the project schedule as part of the ongoing work involved with managing the project.

A

schedule update

84
Q

The difference between a task ? s progress as compared to its estimated progress represented in terms of cost. The formula is SV = EV ? PV.

A

schedule variance (SV)

85
Q

The description of the work involved to complete the project. It defines both what is included in the project and what is excluded from the project.

A

scope

86
Q

The process of documenting and managing changes to project scope. Any modification to the agreed - upon WBS is considered a scope change. Changes in product scope will require changes to project scope, and scope changes always require schedule changes.

A

scope control

87
Q

The minor changes or small additions that are made to the project outside of a formal scope change process that cause project scope to grow and change.

A

scope creep

88
Q

Per the PMBOK Guide , the process of breaking down the major deliverables from the scope statement to create the WBS. For purposes of the CompTIA objectives and exam, scope definition is used in a much broader sense to cover several scope planning elements, including the scope statement and the scope management plan.

A

scope definition

89
Q

Defines the process for preparing the scope statement and the WBS. This also documents the process that manages project scope and changes to project scope.

A

scope management plan

90
Q

The process of defining the scope management plan, the scope statement, and the WBS and WBS dictionary.

A

scope planning

91
Q

Documents the product description, key deliverables, success and acceptance criteria, key performance indicators, exclusions, assumptions, and constraints. The scope statement is used as a baseline for future project decisions.

A

scope statement

92
Q

A process that concerns formally accepting the deliverables of the project and obtaining sign - off that they?re complete.

A

scope verification

93
Q

One of the benefit measurement methods used for project selection. It contains a predefined list of criteria against which each project is ranked. Each criterion has a scoring range and a weighting factor. A scoring model can also be used as a tool to select from among competing vendors.

A

scoring model

94
Q

Putting the project activities in the order in which they will take place.

A

sequencing

95
Q

The amount of time allowed to delay the early start of a task without delaying the finish date of the project. This is also known as float time .

A

slack time

96
Q

A requirement that a product or service must be obtained from a single vendor in government work; also includes justification.

A

sole source

97
Q

Obtaining bids and proposals from vendors in response to RFPs and similar procurement documents prepared during the solicitation planning process.

A

solicitation

98
Q

An executive in the organization with authority to allocate funds, assign resources, and enforce decisions regarding the project.

A

sponsor

99
Q

Obtaining human resources and assigning them to the project. Human resources may come from inside or outside the organization.

A

staff acquisition

100
Q

Documents when and how human resources will be added to and released from the project team and what they will be working on while they are part of the team.

A

staffing management plan

101
Q

A person or an organization that has something to gain or lose as a result of the project. Most stakeholders have a vested interest in the outcomes of the project.

A

stakeholder

102
Q

A task relationship where the finish of the successor task is dependent on the start of its predecessor.

A

start - to - finish

103
Q

A project task relationship where the start of the successor task depends on the start of the predecessor task.

A

start - to - start

104
Q

A type of project ending where resources are cut off from the project.

A

starvation

105
Q

Contains the details of a procurement item in clear, concise terms and includes the project objectives, a description of the work of the project, and concise specifications of the product or services required.

A

statement of work (SOW)

106
Q

The date when the project manager measures how much has been spent on a specific task.

A

status date

107
Q

See acceptance criteria

A

success criteria

108
Q

A task on the network diagram that occurs after another task.

A

successor

109
Q

A way to get diverse groups of people to work together efficiently and effectively. This is the responsibility of the project manager. It can involve activities performed together as a group or individually designed to improve team performance.

A

team building

110
Q

Creating an open, encouraging environment for stakeholders to contribute, as well as developing the project team into an effective, functioning, coordinated group.

A

team development

111
Q

Also known as nonfunctional requirements , the product characteristics needed for the product to perform the functional requirements. Technical requirements typically refer to information technology ? related projects. They are typically the elements and functions that happen behind the scenes of a program to meet the client ?s request.

A

technical requirements

112
Q

A type of contract where the buyer and the seller agree on a unit rate, such as the hourly rate for a programmer. The total cost is unknown and will depend on the amount of time spent to produce the product.

A

time and materials contract

113
Q

The projected performance level that must be achieved in the remaining work of the project in order to satisfy financial or schedule goals. The formula is TCPI = (BAC ? EV) / (BAC ? AC).

A

to - complete performance index (TCPI)

114
Q

An estimating technique that uses actual durations from similar activities on a previous project. This is also referred to as analogous estimating .

A

top - down estimating

115
Q

A mathematical technique that can be used to predict future defects based on historical results.

A

trend analysis

116
Q

According to CompTIA, time, cost, and quality. Other sources site scope rather than quality in their definitions of the triple constraints.

A

triple constraint

117
Q

The comparison of planned project results with actual project results. The formula is VAC = BAC ? EAC.

A

variance analysis

118
Q

A deliverables - oriented hierarchy that defines the total work of the project. Each level has more detailed information than the previous level.

A

work breakdown structure (WBS)

119
Q

A document that describes the deliverables and their components, the code of accounts identifier, estimates, resources, criteria for acceptance, and any other information that helps clarify the deliverables.

A

work breakdown structure (WBS) dictionary

120
Q

The total time it takes for a person to complete a task if they did nothing else from the time they started until the task was complete.

A

work effort

121
Q

The lowest level in a WBS. Team assignments, time estimates, and cost estimates can be made at this level. On very large projects, this level is handed off to subproject managers who develop their own WBS to fulfill the requirements of the work package deliverable.

A

work package