CompTia Project Glossary - Part 02 Flashcards
A standard of measurement that specifically defines how something will be measured.
metric
A major deliverable or key event in the project used to measure project progress.
milestone
This project process group is where activities are performed to monitor the progress of the project and determine whether there are variances from the project plan. Corrective actions are taken during this process to get the project back on course.
monitoring and controlling
A project that is initiated by multiple business units.
multiple business unit project
Negotiating is a leadership technique and a conflict - resolution technique. Negotiating is the act of two or more parties explaining their needs and coming to a mutual agreement on a resolution.
negotiating
Evaluation of the cash inflows using the discounted cash flow technique, which is applied to each period the inflows are expected. The total present value of the cash flows is deducted from the initial investment; this assumes that cash inflows are reinvested at the cost of capital. It is similar to discounted cash flows.
net present value (NPV)
A depiction of project activities and the interrelationships between these activities.
network diagram
Operations typically involve ongoing functions that support the production of goods or services. They don ? t have a beginning or an end.
operations
A high - level estimate of the time and cost of a project based on the actual cost and duration of a similar project.
order of magnitude
The process of addressing factors that may impact how to manage a project team, defining roles and responsibilities for project team members, identifying how the project team will be organized, and documenting a staffing management plan.
organization planning
A quantitatively based estimating technique that is typically calculated by multiplying rate times quantity.
parametric estimating
A Quality Control technique used to rank importance of a problem based on its frequency of occurrence over time. This diagram is based on the Pareto principle, more commonly referred to as the 80/20 rule , which says that the majority of defects are caused by a small set of problems
pareto diagram
The length of time it takes a company to recover the initial cost of producing the product or service of the project.
payback period
Collecting information regarding project progress and project accomplishments and reporting it to the stakeholders, project team members, management team, and other interested parties. It also makes predictions regarding future project performance.
performance reporting
cost of work that ? s been budgeted for an activity during a certain time period.
planned value (PV)
The process group where the project plans are developed that will be used throughout the project to direct, monitor, and control work results. The primary result of this process is the project plan.
planning
Performed when a project is canceled or ends prematurely. It describes the reasons for cancellation or failure and documents the deliverables that were completed.
post-mortem analysis
Conducted at the end of the project to document lessons learned.
post-project review
A network diagramming method that places activities on nodes, which connect to dependent activities using arrows. Also known as activity on node .
precedence diagramming method (PDM)
A task on the network diagram that occurs before another task.
predecessor
An investigation at project request time to determine the costs and benefits of the project, as well as examine alternatives to the proposed solution in order to determine the feasibility of carrying out the project
preliminary investigation
A type of change request that usually occur during the Monitoring and Controlling process group. Preventive actions are implemented to help reduce the probability of a negative risk event.
preventative action
A Quality Control tool and technique that keeps errors from reaching the customer. Prevention is less expensive than having to fix problems after they ? ve occurred.
prevention
The cost of activities performed to avoid quality problems, including quality planning, training, and any product or process testing.
prevention costs
The likelihood a risk event will occur. Probability is expressed as a number between 0.0 and 1.0.
probability
The process of identifying what goods or services will be purchased from outside the organization. It uses make - or - buy analysis to determine whether goods or services should be purchased outside the organization or produced internally.
procurement planning
Explains the major characteristics of the product and describes the relationship between the business need and the product. This is also referred to as high - level requirements .
product description
Occurs in the Close Procurements process and determines whether the work of the contract is acceptable and satisfactory.
product verification
A grouping of related projects that are managed together to capitalize on benefits that couldn ? t be achieved if the projects were managed separately.
program
Calculates the expected value, or weighted average, of critical path tasks to determine project duration by using three estimates: most likely, pessimistic, and optimistic. The PERT calculation is (optimistic + pessimistic + (4 ? most likely)) / 6.
program evaluation and review technique (PERT)
Reports from project team members listing the tasks each team member is working on, the current progress of each task, and the work remaining.
progress reports
Temporary in nature, with a definite start and end date; creates a unique product, service, or result. It is completed when the goals and objectives of the project have been met and signed off on by the stakeholders.
project
An organizational structure focused on projects. Project managers generally have ultimate authority over the project, and sometimes supporting departments such as human resources and accounting might report to the project manager. Project managers are responsible for making project decisions and acquiring and assigning resources.
project-based organization
The person who fully understands, believes in, and espouses the benefits of the project to the organization. This is the cheerleader for the project.
project champion
An official, written acknowledgment and recognition that a project exists. It ? s signed by the project sponsor and gives the project manager authority to assign organizational resources to the work of the project.
project charter
The formal acceptance of a project and the activities required to formally end the project work.
project closure
Documents the key characteristics of the product or service that will be created by the project.
project description
Carrying out the project plan. Activities are clarified, the work is authorized to begin, resources are committed and assigned to activities, and the product or service of the project is created. The largest portion of the project budget will be spent during this process.
project execution
Documentation in the project charter that includes the reason the project is being undertaken and the business need the project will address.
project justification
The grouping of project phases in a sequential order from the beginning of the project to the close.
project life cycle
Applying skills, knowledge, and project management tools and techniques to fulfill the project requirements.
project management
The world ? s leading professional project management association.
Project Management Institute (PMI)
The nine project management groupings, or Knowledge Areas, that bring together common or related processes. They are Integration, Scope, Time, Cost, Quality, Human Resource, Communications, Risk, and Procurement
project management knowledge areas
Established by organizations to create and maintain procedures and standards for project management methodologies to be used throughout the organization.
project management office (PMO)
The person responsible for applying the skills, knowledge, and project management tools and techniques to the project activities to successfully complete the project objectives.
project manager
Measures that the project manager uses to determine whether the project is on track, such as any deviation from the baseline schedule or the baseline budget.
project performance indicators
A document, or assortment of documents, that constitutes what the project is, what the project will deliver, and how all the processes will be managed. Used as the guideline throughout the project Executing and Controlling phases to track and measure project performance and to make future project decisions. Also used as a communication and information tool for stakeholders, team members, and management.
project plan
A formal presentation by the project manager or project team members to the sponsor, the client, and the other executive stakeholders.
project review