competency questions Flashcards

1
Q

What are some common defects with a pitched timber roof?

A

BS5534 should be adhered to, where it isn’t multiple issues arise;

Keeping water out;

  • Pitch - minimum/maximum
  • Long rafters - runs of 10m + flat tiles are less affective
  • Eaves course - incorrect fascia hights
  • Drainage design - bottle necks & overloading

Keeping tiles on;

  • fix every tile once, perimeter twice
  • avoid small tiles no less than 1/2 tile
  • mechanically fixed, mortar has no tensile strength
  • fixings must be specified

Managing internal condensation - BS52550

  • Blocking eaves vents with insulation
  • Not cutting back ridge underlay

Preventing movement;

  • roof spread due to overloading
  • sagging due to skinny rafters and purlins
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are some types of piles and when are they used?

A

There are many types of piles for different uses, using differing materials, to name a few;

Sheet pile wall - retain earth or water used on waterfront structures such as wharfs and piers

Contiguous piled walls - used in dry and cohesive soils and are often the quickest and more economical method of constructing retaining walls.

Friction piles - used where the load-bearing strata is too deep they are held in place by shear stresses along the sides of the pile

Carrison/end bearing - used where the load-bearing stratum is close to the surface and bears directly against it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the typical construction of a warehouse?

A

The construction varies as many different factors would have been considered but typically;

  • Steel portal frame structure
  • Pad foundations
  • Profiled metal sheet cladding, sometimes composite -sandwich panel
  • Brick/block wall, typically only on small sections i.e. where apertures
  • PVCU profiled skylights
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the changes to the RICS rules of conduct?

A

The Rules of conduct for firms changed in 2020 The rules include;

Ethical behavior - Competence - Service -
Continuing Professional Development - Solvency -
Information to RICS - Cooperation

Some alterations include;

  • Principles for better regulation have been simplified and some omitted
  • Combining the principles of taking responsibility and maintaining public confidence in the profession
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the changes to the 2020 Plan of Work?

A

The green overlay has been adopted into the main plan.

Stage 2 Preparation and brief were changed to Preparation and briefing to demonstrate that the brief is an ever-evolving document.

Stage 3 changed developed design to spatial design. To show it’s not changing the concept but coordinating the spaces.

the 2013 guide was unclear when planning permission should be submitted 2-4 the 2020 plan clearly states at the end of stage 3.

Stage 5 changed to manufacturing and construction from construction as I now recognize. modern methods of construction such as offsite manufacturing and offsite construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What was the hackitt review?

A

A series of 53 recommendations to improve the safety of construction and buildings. Her recommendations formed “Building a safer future review” which identified unsatisfactory processes and practices within the industry. Some of her recommendations include;

  • Ban of the use of combustible cladding - EWS1 process
  • Improve regulatory oversight - Building Safety Act - Gateways
  • Improve the change control process
  • Introduce a new building safety regulator - Building Safety Act - Regulator intervention
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the hackitt golden thread?

A

The ‘golden thread’ seeks to extend fire safety best practice beyond fire professionals to wider society, relaying key information about a building through a chain of stakeholders, from architects to fire engineers through to building safety managers to end-users and is a focal pint of the new Building Safety Act.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the building safety act?

A

The Building Safety Bill 2020 was announced in the Queen’s Speech in December 2019 following the Grenfell Tower fire in 2017. The Bill will reform safety in construction by placing a focus on the The ‘golden thread’. The Bill introduces various new mechanisms to improve safety;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is the new building safety regulator?

A

The Building Safety Regulator - The duties of the new Building Safety Regulator are mainly two-fold: to introduce a better safety system and impose sanctions and regulations to ensure this happens.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What roles did the building safety act introduce?

A

The bill introduces new roles;

Accountable person - Introduced at (usually the owner) at the occupation stage. Required to register the building with the Building Safety Regulator

Building safety manager - Their main role will be to support the accountable person in the day-to-day management of the building to ensure safety standards are adhered to.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the 3 gateways in the building safety act?

A

The Bill introduces three gateways where information is assessed at each gateway by the regulator.

Gateway 1 - Planning Stage - Requiring fire safety information to be submitted to the local planning authority as part of the planning application. The Building Safety Regulator a required consultee for higher risk buildings

Gateway 2 - Replaces the current ‘deposit of full plans’ stage in the Building Regulations - The regulator must be satisfied that the design meets the functional requirements of the building regulations. The contractor cannot commence on site until this is achieved.

Gateway 3 - Completion - At the final certificate/completion stage, to ensure that the information provided in stage 2 is built or any variations are picked up and approved. Once the point at which they are happy a ‘golden thread’ of information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What impact does the building safety act have on Building control

A

All Building control bodies will be required to be registered with the inspector’s register and prove their competence. The new building regulator will act as building control on higher-risk buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the differences between JCT and NEC contracts?

A

JCT and NEC are both contract suites, JCT established in 1931 with it’s current edition being 2016 and NEC established 1993 with its current edition being NEC4. They are generally similar however there are some key differences;

Extensions of time and loss and expense - JCT deals with delay extensions of time and loss and expense as two separate mechanisms, relevant matters and relevant events. NEC deals with extensions of time and loss and expense as a single compensation event.

Provisional Sums - JCT has provisions for provisional sums NEC does not.

Programme - JCT contract does not have a programme as a contractual document. NEC has the programme as a contractual document.

Price - The JCT Contract is a fixed price lump sum contract. NEC Option B offers a fixed price lump sum contract but Options C and D are target cost contracts.

Roles - The JCT suite employs the use of a contract administrator who executes the contract whereas the NEC contract has no Contract Administrator, no Clerk of Works and no Architect. As such, the Project Manager is the focal point of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the main suites of contracts?

A

There are many suites of contracts that are used throughout the industry;
JCT including - Minor works, Intermediate works
Standard building, Sub-Sub contract, Major works, Management, Construction Management, Repair and maintenance

NEC4 including - Supply Contract, Design-Build and operate, Engineering and Construction, Engineering and Construction subcontract, Professional service

FIDC including;
Red Book -  Building and Engineering works
Yellow Book - Plant and Design-Build
Silver Book - EPC/Turnkey Projects 
Green Book - Short Form of Contract 

There are multiple other more specialist contracts that can be used for example I have used NFDC on a dilapidated cottage demolition project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the responsibilities of a contract administrator?

A

The roles and responsibilities of a Contract Administrator are set out in the Contract administration RICS Practice Standards, UK 1st edition, guidance note and include;

  • Keeping records
  • Conducting site inspections
  • Attending and recording meetings
  • Reporting to the client / employer
  • Issuing instructions
  • Interim valuations of the works
  • Issuing certificates
  • Manage the insolvency of a contractor
  • Adjust the contract sum
  • Loss and expense claims
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are key dates for valuations?

A
Contractors application: -7 days
Due Date: 0 day
Vlauation: +7 days
Pay less: +9days
Final Date for Payment: +14 day
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How do you avoid conflicts?

A

Change control - Have a clear and robust change control process

Clear communication - so that there is no room for misinterpretation

Monthly valuation with the contractor - so there are no surprises

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is a Principal Designer?

A

A principal designer can be an organisation or individual who is appointed by the client to take the lead in planning, managing, monitoring and coordinating health and safety during the pre-construction phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What design standards have you used that are not the approved documents?

A

There are a few design standards that I have used when dealing with specific clientele. A few examples are;

When completing a scheme for Healthcare clients I use the Health Technical Memorandum and Health Building notes. HTMs & HBNs are focused towards delivering practical health care spaces which have different requirements to the building regulations such as medical gases and infection control. Whilst working on a dental refit project I produced a derogation schedule of items that the client had specified that deviated from the HTMs & HBNs.

When completing a scheme for education clients I use the Building Bulletins and The Output Specification. Building bulletins and The output specification are focused towards delivering safe and functional education spaces which have different requirements to the building regulations such as improved safeguarding measures produce Condition Improvement Funds bids annually that utilise both of these design standards such as Eggbuckland, Leigham, Ashburton and Lipson safeguarding bids and Widewell and Victoria Road window replacement bids.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What is included within a tender pack?

A

The information would vary depending on the size and scope of the project but typically I include;
Preliminaries - Description of the works
Specifications - Performance Specifications or Prescriptive Specifications
SoW - Pricing schedule or if a larger complex project a BoQ
Communication - Post and pre tender
Drawings
Pre-construction information - any additional information e.g. utilities & asbestos

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What would you include within a major works pack that would not be included within a smaller works package?

A

BIM requirements - Public procurement require BIM level 2 PAS 1192
Bill of Quants rather than a Schedule of Works
Sustainable aspirations
Pre-qualification questionnaire

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How is the client protected by a contract?

A
Insurances
Defect liability period
Damages
Parent company guarantees
Performance bonds
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the procedure to deal with a default?

A

Employer issues warning notice specifying default and related contract clause. If no attempt is made to rectify within 14 days the CA or employer can issue a termination notice within 21 days of the expiry of the warning notice. If multiple warning notices have been issued the contract can be terminated without waiting for the 14 day notice period to expire.

Typical contractor defaults include;

Failure to proceed with the works in a timely manner
Failure to complete works competently
Abandoning the site
Failure to remove or rectify defective works

Typical employer defaults include;

Breach of CDM
Interferes with the issuing of a certificate
Does not pay by the final date on multiple occasions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

How is a delay caused by COVID dealt with?

A

Disruption to the supply chain, lack of labour and the governmental site shut down due to COVID 19 has been treated as a relevant event and the contractor shall be awarded an extension of time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

How is a consultant appointed?

A

A description of the service to be provided
Terms and conditions
PII requirements
QP5 - quality management questionnaire

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

How would you select an appropriate contract?

A

Typically I would use the “Guide to selecting the appropriate JCT main contract 2016” which is produced by the Joint Contract Tribunal. It consists of a flow chart that takes into consideration;

  • procurement route,
  • design responsibility,
  • size of the project,
  • if BoQ are required,
  • subcontractors
  • various other factors that have a bearing on the type of contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What are some examples of warranties and what are they used for?

A

Typically a written guarantee, issued to the purchaser of an article by its manufacturer, promising to repair or replace it if necessary within a specified period of time. Some examples of warranties are;

Collateral warranties - Collateral warranties are agreements which are associated with another ‘primary’ contract. They provide for a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract.

Building warranties - A structural or building warranty is technically ‘structural defects liability insurance’. Warranty providers’ carry out an inspection process as the build progresses and, on completion, a 10-year warranty is provided covering major defects in design, materials or workmanship.

Manufacturer warranties - The manufacturer/installer will cover you for the cost of any material failures outside of your control. Typically e.g. roofing warranty these are only valid if the system is installed by an accredited installer and a regular specified maintenance is undertaken.

28
Q

What are 3rd party agreements and what are they used for?

A

Third party contracts are agreements that involve a person who isn’t a party to a contract but is involved with the transaction. The law around this topic is set out in Contracts (Rights of Third Parties) Act 1999.

A common example of a 3rd party agreement is a Collateral warranties; they are used as a supporting document to a primary contract where an agreement needs to be put in place with a third party outside of the primary contract. JCT does not issue a Consultant Collateral Warranties. However, their suite of collateral warranties include; Contractors/Subcontractors/Employers/Tenants/Purchase.

29
Q

What are some typical sources of ignition?

A
Dangerous substances and explosive atmospheres HSE Approved Code of Practice indicates various sources;
Flames;
Direct fired space and process heating;
Use of cigarettes/matches etc;
Cutting and welding flames;
Hot surfaces.
30
Q

What are Active and passive measures?

A

Active provisions take action to put out a fire i.e. sprinkler system, deluge system, fire extinguisher, fire alarms, smoke detectors, and even firefighters.

Passive Fire Protection will help prevent a fire from spreading or resist the initial ignition i.e Fire dampers, Fire rated walls, Fire doors, Steel protection (Overboarding, thin film intumescent) e.c.t

31
Q

What are some methods used to protect the structure from fire spread?

A
There are many ways in which the structure can be protected;
Thin film intumescent coatings
Off site applied intumescent coatings
Thick film intumescent coatings
Boards
Sprays
Flexible blanket systems
Concrete encasement
32
Q

What is VESDA?

A

Very early smoke detection apparatus. It consistently draws in and monitors the air for any gasses associated with smoke.

33
Q

What are the roles under the RRO?

A

Responsible person;
• Undertaking risk assessments
• Taking fire precautions to ensure the safety of employees and premises.
• Eliminating or reducing risks from dangerous substances.
• Providing information and training to employees.

Competent Person;
• Understand the relevant fire safety legislation and the associated guidance documents
• Have appropriate education, training, knowledge and experience in the principles of fire safety
• Have appropriate training and/or experience in carrying out fire risk assessments

Relevant Person - any person in the immediate vicinity of the premises who is at risk from a fire on the premises.

34
Q

What is the height of collimation?

A

Height of Collimation is the height of the horizontal plane through the telescope. In order to see the staff on the BM the instrument must be higher. To find the Height of Collimation (Instrument Height) add the staff reading to the level of the BenchMark.

35
Q

How do you Check the dimensions on a drawing are accurate?

A

Self measure - E.g. receive drawing from a client, take check dimensions to guarantee the accuracy of the drawing.

Triangulation - The process of determining the location of a point by measuring only angles to it from known points at either end of a fixed baseline

36
Q

What are some common errors when leveling?

A

There are various factors that need to be considered to prevent errors. Some common form of errors include;

Instrument errors - Not holding staff vertically, moving the position of the staff to take the backsight, not pulling out all the sections of the staff. Setting up the tripod unevenly.

Human error - Reading the wrong crosshair, recording levels incorrectly.

Mathematical errors - Mathematical checks e.g. Sum of B.S.minus sum of F.S. = last R.L.
minus First R.L.

37
Q

What are the IMPS standards and when are they used?

A

IMPS were introduced to address current inconsistencies in the way property of all types is measured from one market to the next. The RICS Practice note

IMPS 1 - Sum of all floor areas measured to the outer perimeter wall. Similar to GEA. Used for Town planning, Rating and council tax for houses and bungalows.

IPMS office 2 - Sum of all floor areas measured to the internal dominant face recorded on a component by component (vertical penetrations, structural elements,circulation spaces) basis. Used for Estate agency and valuation, Rating, Property management of industrial buildings.

IPMS office 3 - The measurement of the internal area exclusive to an occupier used for letting properties. The wall shared with adjacent properties is included up to the centerline. Used for Estate agency and valuation, Rating, Property management of shops, supermarkets, offices and business use.

38
Q

Who uses the IMPS standards

A

There are over 80 professional bodies and companies that utilise IMPS including the RICS, British Property Federation, Australian Property Institute, European Council of Real Estate Professions.

39
Q

What are typical tolerances on drawings?

A

Guidance note RICS property measurement 2nd edition Appendix A includes a table of typical tolerances at various scales and when they are typically used. e.g.

1: 20 | +/- 5mm | used for high precision setting out drawings
1: 100 | +/- 25mm | used for low precision General arrangement drawings for space planning

40
Q

Name a recent change to sustainability legislation?

A

January the government set out its plans and timeframe for its new Future Homes Standard;

‘zero carbon ready’ by 2025
A full technical specification for the Future Homes Standard will be consulted on in 2023
legislation introduced in 2024
Implementation in 2025

41
Q

How would you inspect reinforced concrete?

A

Non-destructive testing methods to the standard set out in BS EN 12390 would be preferred. Some examples on nondestructive testing includes;

Schmitt hammer - Rebound test to check the integrity

Reinforcement detector - Check it’s location and depth

Pull test - Test tensile strength

Ultrasonic pulse velocity method - high velocity good, low velocity bad.

Resonant Frequency Test - Measures vibration from mechanical impact.

1/2 cell mapping - Measures Mv and maps to identify weaknesses

42
Q

What are some local issues that pose a threat to buildings?

A

Mundic - block created using mine waste that deteriorates from the cavity outward

Marine environment - marine grade metals

Mines - Cornwall have tin mines, Dartmoor has ceramic mines

43
Q

What are the recent updates to the approved documents?

A

Part B - The latest changes came into force in November 2020; Sprinklers - A reduction in trigger height from 30m - 11m, New signage recommendations within flats above 11m.

Part M - The latest changes to Approved document M came into force in January 2021; At least 1Nr changing toilet in the following buildings; Assembly, recreation, entertainment (more than 250 people) and Shopping centres more than 30,000m2

Part L - New backstop u-values. Introduction of the primary energy factor - PEF was developed to provide a more accurate measure of overall energy. It records the energy from the following activities; Planting/Cultivation, Extraction, Processing, Transportation, Transmission.

44
Q

What is the Building Act 1984?

A

The Building Act 1984 is the primary, enabling legislation under which secondary legislation such as the building regulations are made. It’s basic aims are;
Securing the health, safety, welfare and convenience of persons in or about buildings and of others who may be affected by buildings or matters connected with buildings.

Furthering the conservation of fuel and power.
Preventing waste, undue consumption, misuse or contamination of water.

The Building Act also sets the legal status of the “approved documents”, which provide general guidance on how specific aspects of building design and construction can comply with the building regulations.

45
Q

What are the consequences of not complying with building control?

A

Failure to comply with the requirements of the Building Regulations can result in formal enforcement action being instigated under the provisions of section 35 and 36 of the Building Act 1984.

Section 35 - breach of building regulations - If there is a breach a person is liable on summary conviction of a magistrates court to a fine not exceeding level five (currently £5,000.00) and a further fine not exceeding £50.00 for each day the default continues after conviction.

Section 36 - removal or alteration of offending work - Without prejudice by notice, require that the owner of the property; pulls down or removes the work or if the owner so elects, to effect such alterations to make it comply with the regulation.

Section 37 - obtaining a report where a section 36 notice is given

46
Q

What is HASWA 1974

A

HASWA is a piece of primary Health and Safety legislation in the UK andwas introduced in 1974, was updated in the 90s with the six pack regulations including PPE regulations and manual handling operations regulations. It places the following duties on employers;

Ensure the health, safety and welfare of employees at work

Other persons are not exposed to health and safety risks

The premises are safe and without risk

47
Q

What is The Party Wall etc. Act 1996

A

The Party Wall etc. Act 1996 is an enabling Act, insofar as it grants the owner of a property the legal right to undertake certain works that might otherwise constitute trespass or nuisance.

48
Q

What are the notices under the party wall act 1996?

A

The three types of Notice are known, respectively as:

Section 1: Line of Junction Notice
Section 3 (for S2 works): Party Structure Notice
Section 6: Notice of Adjacent Excavation (3m or 6m)

49
Q

What are some tender procedures?

A

There are many types of tender procedures, some of which are identified in the Public Procurement Regulations 2015;
Single stage tendering (open)
Two stage tendering (restricted)
Negotiated tendering (competitive dialog)
Competitive with negotiation
Innovative partnerships

50
Q

What are some advantages and disadvantages of a single-stage tender?

A

Single-stage tendering is used when all the information necessary to calculate a realistic price is available when tendering commences.

Pros;
The client benefits from a competitive tendering process which can lead to more competitive pricing.
The client can also benefit from a fixed price through this tendering process.

Cons;
Contractors may not have been consulted on the buildability at the outset meaning ever-changing building costs throughout the project.
Typically slower to appoint a contractor

51
Q

What are some advantages and disadvantages of a two-stage tender?

A

Two stage tendering is a method of procurement where the employer seeks to appoint a contractor at an initial stage of the project based on an outline scope of work.

Pros;
The project doesn’t have to be fully designed and costed before they can start procurement for the project
Shorter timescales required to get a contractor appointed.

Cons;
Have to appoint a contractor before obtaining an accurate price.

52
Q

What are alternatives 1 and alternatives 2?

A

Under Tendering Practice Note 2017 Alternative 1 correction of the tender price is not permitted and under Alternative 2 correction of the tender price is permitted.

53
Q

What are some typical questions within a pre-qualification questionnaire?

A

Company details (including legal status).
Details of insurance cover.
Financial information (such as recent accounts).
Relevant experience.
Information about technical and professional ability.
Information about capability and capacity.
Health and safety policy.
Quality assurance policy.

54
Q

What is the code of practice for tendering?

A

Tendering Practice Note 2017 is a general guidance document, providing an informative and practical tool. It provides guidance on;

Preliminary Enquiry - including a project information schedule and pre-qualification questionnaire.

Invitation to Tender and Tender - covering the documents involved, the criteria and compliance.

Assessment and Award - covering assessment, examination of priced documents and related matters, and notification to tenderers.

55
Q

What are some differences between financial and managerial accounts?

A

Management accounts are financial reports produced for the business owners and managers, generally monthly or quarterly, normally a Profit & Loss report and a Balance Sheet.

Financial accounts typically focus on creating accurate financial statements that can be shared outside the company.There are 5 main differences that come to mind;

Target audience - FA External, MA internal

Outlook - FA focuses on past events and transactions. MA focuses on improvements that can be made in the future.

Scope - FA is a broad summary of the whole business. MA is narrow as it focuses in detail on specific areas of the businesses.

Accuracy - FA accounting is a true and accurate representation. MA can often contain estimates and predictions.

Rules - FA must adhere to GAAP in used nationally and IFRS if used internationally. MA has no rules as only used internally.

56
Q

What is the difference between a balance sheet and a profit and loss statement?

A

A balance sheet is a snapshot of a companies financial position at a specific point in time and identifies a business’s current assets and liabilities.

A Profit and loss statement shows a companies financial position over a specified period of time typically the previous financial year and identifies a companies income and expenditure over that period.

Both are required to be submitted to form a financial report in accordance with GAAP or IFRS and the Companies Act 2006;

57
Q

What is required to set up an RICS regulated firm?

A

There is an application form available on the RICS website. Before completing the form there are some conditions that need to be met;

At least 25% of principals must be charted with the RICS

Your firm must offer professional services in surveying disciplines

Agree to comply with RICS Rules of Conduct for Firms

The Rules of conduct for firms changed in 2020 The rules include;

Ethical behavior - Competence - Service - Continuing Professional Development - Solvency - Information to RICS - Cooperation

58
Q

What are some differences between arbitration and adjudication?

A

Arbitration and adjudication are both forms of alternative dispute resolution that see a dispute put before a competent person in order to make a judgment. However, there are some important differences to note;

Finality - The decision of an Arbitrator is final and cannot be overturned in the courts (unless an appeal is expressly agreed beforehand). Whereas an adjudication decision can be enforced by using civil procedure rule 9 it can be appealed.

Speed - Adjudication tends to be quicker than arbitration as documents are shared faster and a decision is met over weeks rather than months.

Statutory - Statutory adjudication can be entered at any point during a dispute through means of the Housing Grants and Regeneration Act 1996. Whereas arbitration must be entered by agreement.

Awarding costs - Arbitrators have the power to award penalty costs whereas adjudicators can only recover their own fees.

59
Q

What are some methods of conflict avoidance?

A

There are numerous best practice that can be utilized in order to minimize the likelihood of

Constant risk monitoring 
Change control 
Undertake monthly valuations with the contractor
Clear communication
Agreed costs on variations
60
Q

How can you terminate a contract?

A

There are numerous reasons as to why and how a contract can be terminated;

Default by the contractor - Employer issues warning notice specifying default and related contract clause. If no attempt is made to rectify within 14 days the CA or employer can issue a termination notice within 21 days of the expiry of the warning notice.

Insolvency of the contractor - Insolvency is defined in JCT IC 16 in section 8.1 “a company becomes insolvent when it enders administration or it makes a winding up order.”

Frustration - Occurs when circumstances that are the fault of either party make it impossible to proceed with the contract e.g. Building destroyed or unforeseen government restrictions imposed on the building.

Convenience - Some contracts allow for termination by convenience. E.g. client fails to secure funding for the works. However, this can leave the terminating party open to significant claims.

Recession - Both parties agree to return themselves to a position before the contract existed. E.g. if there is a fundamental error with the contract. Near impossible as damages may be awarded if there is a start on site.

61
Q

What is bailey Partnerships complaints handling procedure?

A

As required by RICS Rules of Conduct for Firms Bailey Partnership has a complaints handling procedure and it is as follow;

  • Where a written complaint is received it is to be passed onto the relevant person. In my case, this is one of the Partners.
  • If a complaint is made orally, request the complaint in writing.
  • Once the complaint is received we have 7 days to provide a written summary typically containing our understanding of the circumstances leading to the complaint and an invitation to provide a response.
  • Within 21 days of the complaint they will be informed of the investigation into the complaint and to let them know what actions have been or will be taken.
  • If they are not happy with the response they are invited to contact our Relevant persons or The Regulatory Board; namely, Arbitrators drawn from the RIBA, RICS or CIArb.
62
Q

What are some common concrete defects?

A

Alkali-silica reaction - Alkali-Silica Reaction (ASR) commonly known as ‘concrete cancer’ is the most common form of alkali-aggregate reaction. ASR occurs when moisture reacts with some types of aggregates which produces a hygroscopic gel that expands. The expansion caused craze cracking.

Concrete Carbonation - Carbonation is the reaction of carbon dioxide in the environment with the calcium hydroxide in the cement paste. This reaction produces calcium carbonate and lowers the pH to around 9.

Inadequate reinforcement cover - water ingress of the surface will allow shallow reinforcement to exfoliate causing spalling.

Cracking caused by movement - thermal expansion e.g. missing expansion joints, ground heave, subsidence e.t.c.

63
Q

What is surveying safely

A

A guidance note produced by the RICS covering the following topics;

  • Visiting sites
  • Undertaking risk assessments
  • Lone working
  • Personal responsibilities
  • Corporate responsibilities
  • Occupational health and hygiene
  • Fire safety
64
Q

What are some principles of GDPR

A
Lawfulness, fairness and transparency,
Purpose limitations,
Data minimisation,
Accuracy,
Storage limitations,
Integrity and confidentiality,
Accountability.
65
Q

What is included within a fee proposal

A
  • A description of the project
  • A schedule of the works to be carried out
  • Any limitations
  • Details of personnel
  • The fee chargeable
  • Hourly rate if the scope is expanded
66
Q

What is the town and country planning act

A

A piece of primary legislation that;

States the policies and general proposals for the development and other use of land in its area;

Takes account of the policies at national and regional level insofar as they affect the physical and environmental planning of its area;

and Provides the framework for local plans.

67
Q

The Landlord and Tenant Act 1985

A

The Landlord and Tenant Act 1954 governs the rights and obligations of landlords and tenants of premises which are occupied for business purposes.

The act covers;
Security of tenure for the tenant
Grounds for regaining possession
Terminating leases
New lease granted under the Act
Lease terms
Rent
Tenancies excluded from the Act