codes Flashcards

1
Q

UL 1741

A

product safety requirements for inverters and other equipment used in both interconnected and stand alone systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

table 310

A

open air/race way, conduit codes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

706.21(E)

A

a disconnect means is required to isolate the fuse from all sources for servicing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

table 690.7

A

determining the max number of modules depending on max source Voltage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

706

A

energy storage systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

NEC 250.52(A)(3)(1)

A

dealing with rebar and concrete encasements ?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

90.4

A

The AHJ has
the responsibility for making interpretations of the rules, for deciding on the approval of
equipment and materials, and for granting the special permissions covered by the NEC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

705.12 (B)

A

load side connections must comply with the following six requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

706.30 (A)

A

Concealed lithium-ion battery compartments that do not require maintenance can operate at voltages
above 100V in dwellings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Article 300

A

Wiring Methods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

250.97

A

For circuits over 250 volts where oversized concentric or eccentric knockouts are encounter the raceway needs to be bonded by one of the means listed in 250.92(B) except for (B)(1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

706

A

energy storage systems (ESS), listed to UL 9540 is NOT subject to field inspection except for field termination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

706.23 (B)

A

Interactive systems must also have a second
independent charge controller to prevent battery overcharge when the grid or loads are not
available to divert excess power

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

NEC 334.30

A

USE-2 wire be secured 12” from the junction box

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Article 230

A

services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

110.27

A

all live parts shall be guarded

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Article 240

A

overcurrent devices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

710

A

stand-alone systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

NEC 310.15(B)(16)

A

At 75⁰C THW, XHHW, THWN should be used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

NEC 338.10(B)(4). Article 334.30

A

Installation methods for exterior USE-2 conductors; USE-2 wire must be strapped and secured between modules at
intervals no more than 4.5”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

110.26

A

Working spaces must be allowed for installers and maintenance personnel to safely work on electrical equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Article 691

A

Large-Scale PV Power

Production Facility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

90.1 (purpose)

A

“is the practical safeguarding of persons and property from hazards
arising from the use of electricity and is not intended as a design specification
or an instruction manual for untrained persons”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

250.110

A

Any conductive battery racks, cases or trays must also have proper equipment grounding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Article 712

A

DC Microgrids

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

110.3 (B)

A

A key element of a safe and code-compliant electrical installation is adherence to product
installation and use instructions included with listed and labeled products

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

NEC Table 310.15(B)(16)

A

75 or 90 degree column is good for #8 wire good for 50 Amp breaker

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

690.41 (B)

A

most PV systems, residential, and commercial must have ground fault

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

[NEC 706.23(B)]

A

Whenever a diversionary charge controller is used, a second independent charge controller is
required to prevent battery overcharge in the event the diversion loads are unavailable or the
diversion charge controller fails

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

250.12

A

aluminum either has an anodized coating to reduce corrosion or a thick layer of oxidation as in the case of non-anodized aluminum. In either case, simple bolting of modules to structures, or lugs to modules or structures, will not necessarily provide the necessary bonding and grounding. The NEC generally requires that the installer remove non-conductive coatings prior to making electrical connections

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

706.23

A

A charge controller is required in most
PV systems that use battery storage, to prevent damage to the batteries or hazardous conditions
resulting from overcharging

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

IEEE 1547

A

establishes the technical requirements for interconnecting all types of distributed generation
equipment, including PV, fuel cells, wind generators, reciprocating engines, microturbines, and
larger combustion turbines with the electrical power system. It also establishes requirements
for testing, performance, maintenance and safety of the interconnection, as well as response to
abnormal events, anti-islanding protection and power quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

690.34

A

Junction boxes do not have to be readily accessible, but must
permit ready access by temporarily removing modules connected by flexible wiring methods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Article 690.45(A) refers to Table 250.122

A

Where no overcurrent protection is provided for the PV dc circuit,
an assumed overcurrent device rated at the PV circuit Isc is used to size
the equipment grounding conductor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Article 705

A

Interconnected Electric

Power Production Sources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

IEEE 1547

A

testing procedures required to ensure that grid-direct inverters conform with safety requirements related to voltage, frequency, synchronization, disturbances, faults, and reconnect time. “islanding”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

690.8 (A) (3)

A

conductor should be sized according to the max continuous current output of the inverter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Article 250.52 (A) (4)

A

1/0 ground wire = ground ring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Article 690.14 (C)(1)

A

Requirements and location for Disconnecting Means

40
Q

90.7, 110.3

A

Equipment is generally

approved when it is listed, labeled, or evaluated for safety by an approved testing laboratory

41
Q

[NEC 690.4(B), 705.6].

A

Certain PV
products are also identified for specific applications and conditions of use, such as inverters
intended for utility interconnection

42
Q

710.15 (C)

A

special warning sign is required on

the panel to prohibit the connection of multiwire branch circuits

43
Q

690.72

A

self regulating PV charge controller

44
Q

480.10(C), 110.26

A

Sufficient working spaces and clearances must be

provided for any battery installations

45
Q

690.2

A

installer should be able to clearly identify the different circuits ( DC or AC )

46
Q

UL 2579

A

fuses for photovoltaic systems

47
Q

690.42

A

The dc system grounding connection must be made at a single point on the PV output circuit

48
Q

690.72

A

Active means of charge control is required by the NEC
unless the maximum array charge current for 1 hour is less than
3% of the rated battery capacity measured in amp/hours.

49
Q

Article 706

A

Energy Storage Systems

50
Q

NEC 240.4(D) (7)

A

copper #10 wire limited to 30 Amp overcurrent device

51
Q

480.9, 480.10

A

To prevent battery installations from being classified as hazardous locations, ventilation of explosive
battery gasses is required. However, the NEC does not provide specific ventilation requirements.
Vented battery cells must incorporate a flame arrestor to help prevent cell explosions from external
ignition sources, and cells for sealed batteries must have pressure relief vents

52
Q

690.49

A

Where the removal of the utility-interactive inverter or other
equipment disconnects the bonding connection between the
grounding electrode conductor and the photovoltaic source and/or
the photovoltaic output circuit grounded conductor, a BONDING JUMPER shall be
installed to maintain the system grounding while the inverter or
other equipment is removed.

53
Q

710.15 (A)

A

the inverter should be large enough to power the total connected load, but is only
required to be as large as the single largest load

54
Q

110.26

A

requirements for working spaces

around live electrical equipment

55
Q

Article 710

A

Stand-Alone Systems

56
Q

Article 480

A

Storage Batteries

57
Q

Article 250.53 (F)

A

30” of burial depth for ground ring

58
Q

UL 1741

A

standard for inverters, converters, charge controllers and combiner
boxes

59
Q

PV racking systems are UL standard 2703, meaning?

A

module clamps, when mechanically attached, have a means to bond the frames of the mods to the rails for equipment grounding purpose

60
Q

Article 690.14 (D) (1-4)

A

) Utility-interactive inverters mounted in not-readily –

accessible-locations.

61
Q

705

A

AC microgrids

62
Q

NEC 690.17

A

The DC and AC disconnects should be on either side of the inverter AKA ‘readily accessible requirement’

63
Q

Article 310

A

Conductors for

General Wiring

64
Q

250, 690.43

A

The installation of an equipment grounding conductor (EGC) is required for all metal framed PV module systems and any PV array that has exposed conductors in contact with metal support structures, regardless of system voltage ; The EGC can be a conductor, busbar, metallic raceway, or structural component.

65
Q

UL 2703

A

standard for racking systems

66
Q

Article 250

A

Grounding and Bonding

67
Q

300.9

A

conductors in conduit installed outdoors/ rooftops must be water tight; labeled W

68
Q

Article 240

A

Overcurrent Protection

69
Q

UL 4703

A

standard for PV wire

70
Q

690.4 (C), 705.6

A

any PV system equipment, including any electrical power production
sources operating in parallel with a primary source of electricity be installed only by qualified
persons

71
Q

690.53

A

The maximum rated output current of the charge controller must be posted on a
sign at the dc disconnect

72
Q

690.72

A

max charge rates from PV array multiplied by 1 hour = 3% of battery nominal Ah capacity or greater a charge controller is required

73
Q

712

A

DC microgrids

74
Q

300.5

A

conductors in conduit installed underground must be water tight; labeled W

75
Q

NEC 338.10(B) (4).

A

USE-2 wires should be lifted off of roof ad strapped at 3’ (wire management)

76
Q

OSHA requirements for battery installations

A

-Unsealed batteries must be installed in ventilated enclosures to prevent fumes, gases, or
electrolyte spray entering other areas, and to prevent the accumulation of an explosive mixture.
• Battery racks, trays and floors must be of sufficient strength and resistant to electrolyte.
• Face shields, aprons, and rubber gloves must be provided for workers handling acids or
batteries, and facilities for quick drenching of the eyes and body must be provided within
25 feet of battery handling areas.
• Facilities must be provided for flushing and neutralizing spilled electrolyte and for fire
protection.
• Battery charging installations are to be located in designated areas and protected from
damage by trucks.
• Vent caps must be in place during battery charging and maintained in a functioning condition.

77
Q

480.8

A

Metal racks must be painted or otherwise treated to resist degradation from electrolyte and
provide insulation between conducting members and the battery cells

78
Q

690.45

A

EGC (equip. grounding conductor) size for DC side

79
Q

706.30 (B)

A

If batteries are connected in series to produce more than 240 V (nominal), then the batteries
must be connected in a manner that allows the series strings of batteries to be separated into
strings of 240 V or less for maintenance by qualified persons

80
Q

690.8

A

code-approved method to determine conductor/wiring

81
Q

480.10

A

proper ventilation for vented and sealed battery systems

82
Q

690.7

A
The charge
controller rated continuous current (sometimes specified as input current, sometimes as
output current)
must be at least
125% of the PV
array short-circuit
output current, and
the charge controller
maximum input
voltage must be
higher than the
maximum system
voltage
83
Q

Article 110

A

Requirements for

Electrical Installations

84
Q

UL 1703

A

standard for PV mods

85
Q

Article 705.10

A

Permanent plaque or directory

86
Q

706.30 (A) exception

A

First, if routine maintenance is required, which would not be the case for lithium-ion or valve-regulated lead-acid (VRLA) batteries, then the terminals must be guarded to prevent contact during that maintenance. Second, a ground-fault detector-indicator is also required for any ESS operating over 100 volts.

87
Q

690.31

A

Spacing between cable management devices for PV wire

88
Q

Commissioning protocol standards

A

NFPA 70 (National Fire Protection Association) National Electrical Code and in
particular those Articles relevant to the solar industry: 690, 691, 705, 706, 710, and, in
some projects, 712.
• NFPA 70E Standard for Electrical Safety in the Workplace.
• IEC 62446-1 Grid connected photovoltaic systems – Minimum requirements for system
documentation, commissioning tests and inspection. This standard provides a framework for
system commissioning that is widely accepted in the solar industry.

89
Q

IEC 62446-1

A

Grid connected photovoltaic systems – Minimum requirements for system documentation, commissioning tests and inspection

90
Q

ANSI/ NETA ATS 2017

A

Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems

91
Q

110.26

A

requirements for working spaces around live electrical equipment

92
Q

Table 250.122

A

Where no overcurrent protection is provided for the PV dc circuit, an assumed overcurrent device rated at the PV circuit Isc is used to size the equipment grounding conductor

93
Q

690.31 (G)

A

metallic conduit, raceways, and enclosures for PV source and output circuits (DC) that run inside a building/structure

94
Q

ANSI Z87.1

A

standard for safety glasses

95
Q

250.119 and 200.6 (A)

A

color coding requirements