codes Flashcards
UL 1741
product safety requirements for inverters and other equipment used in both interconnected and stand alone systems
table 310
open air/race way, conduit codes
706.21(E)
a disconnect means is required to isolate the fuse from all sources for servicing
table 690.7
determining the max number of modules depending on max source Voltage
706
energy storage systems
NEC 250.52(A)(3)(1)
dealing with rebar and concrete encasements ?
90.4
The AHJ has
the responsibility for making interpretations of the rules, for deciding on the approval of
equipment and materials, and for granting the special permissions covered by the NEC
705.12 (B)
load side connections must comply with the following six requirements
706.30 (A)
Concealed lithium-ion battery compartments that do not require maintenance can operate at voltages
above 100V in dwellings
Article 300
Wiring Methods
250.97
For circuits over 250 volts where oversized concentric or eccentric knockouts are encounter the raceway needs to be bonded by one of the means listed in 250.92(B) except for (B)(1)
706
energy storage systems (ESS), listed to UL 9540 is NOT subject to field inspection except for field termination
706.23 (B)
Interactive systems must also have a second
independent charge controller to prevent battery overcharge when the grid or loads are not
available to divert excess power
NEC 334.30
USE-2 wire be secured 12” from the junction box
Article 230
services
110.27
all live parts shall be guarded
Article 240
overcurrent devices
710
stand-alone systems
NEC 310.15(B)(16)
At 75⁰C THW, XHHW, THWN should be used
NEC 338.10(B)(4). Article 334.30
Installation methods for exterior USE-2 conductors; USE-2 wire must be strapped and secured between modules at
intervals no more than 4.5”
110.26
Working spaces must be allowed for installers and maintenance personnel to safely work on electrical equipment
Article 691
Large-Scale PV Power
Production Facility
90.1 (purpose)
“is the practical safeguarding of persons and property from hazards
arising from the use of electricity and is not intended as a design specification
or an instruction manual for untrained persons”
250.110
Any conductive battery racks, cases or trays must also have proper equipment grounding
Article 712
DC Microgrids
110.3 (B)
A key element of a safe and code-compliant electrical installation is adherence to product
installation and use instructions included with listed and labeled products
NEC Table 310.15(B)(16)
75 or 90 degree column is good for #8 wire good for 50 Amp breaker
690.41 (B)
most PV systems, residential, and commercial must have ground fault
[NEC 706.23(B)]
Whenever a diversionary charge controller is used, a second independent charge controller is
required to prevent battery overcharge in the event the diversion loads are unavailable or the
diversion charge controller fails
250.12
aluminum either has an anodized coating to reduce corrosion or a thick layer of oxidation as in the case of non-anodized aluminum. In either case, simple bolting of modules to structures, or lugs to modules or structures, will not necessarily provide the necessary bonding and grounding. The NEC generally requires that the installer remove non-conductive coatings prior to making electrical connections
706.23
A charge controller is required in most
PV systems that use battery storage, to prevent damage to the batteries or hazardous conditions
resulting from overcharging
IEEE 1547
establishes the technical requirements for interconnecting all types of distributed generation
equipment, including PV, fuel cells, wind generators, reciprocating engines, microturbines, and
larger combustion turbines with the electrical power system. It also establishes requirements
for testing, performance, maintenance and safety of the interconnection, as well as response to
abnormal events, anti-islanding protection and power quality
690.34
Junction boxes do not have to be readily accessible, but must
permit ready access by temporarily removing modules connected by flexible wiring methods
Article 690.45(A) refers to Table 250.122
Where no overcurrent protection is provided for the PV dc circuit,
an assumed overcurrent device rated at the PV circuit Isc is used to size
the equipment grounding conductor
Article 705
Interconnected Electric
Power Production Sources
IEEE 1547
testing procedures required to ensure that grid-direct inverters conform with safety requirements related to voltage, frequency, synchronization, disturbances, faults, and reconnect time. “islanding”
690.8 (A) (3)
conductor should be sized according to the max continuous current output of the inverter
Article 250.52 (A) (4)
1/0 ground wire = ground ring