The thing to when a schedules actual time exceeds the planned time is to find who did it?
False
The PERT Technique is a probabilisitic model
True
A milestone consumes Time but not Resources
Fasle
If the schedule is going better than planned do not need to do anything
False
The reason why any two activities must be done in a particular order is termed a constraint.
True
One of the effects of Constraints is that they generally increase project cost
True
You should only include physical costraints in the initial schedule.
True
A layout is a customized view of activity info
True
There is only one level of activity detail for a construction project
False
You must pick what calender you want for the project and all activities must use this calender
False
When you subcontract all the work then the schedule need not to be resource loaded
False
The best way to contact me is through email
False
The greatest disadvantage of the Gantt Chart was the relationship between activities
False
The two companies that first developed the network logic diagrams were dow and the airforce
False
only Pert schedules have a critical path
False
The way for a p6 schedule to recalculate the schedule data is to go to “tools”, “schedule”
False
The menus for p6 are divided into two main parts ____ and ____
enterprise data, project data
My new projects are stored in ________
Enterprise Project Strucutre (EPS)
There are three main types of relationships, _____, _____ and _____
finish to start, start to start, finish to finish
The schedule is the reflection of the _____
Plan
Network modes have two main techniques ____ and _____
Precedence Diagramming Method(PDM) and Evaluation and REview Technique (PERT)
_____ are the basic building block of the network
Activities
What is Lag?
Lag specifies an offset or delay between an activity and its successor.
In p6 there are four switched to control the outcome of adding resources. List them
Fixed Duration
Fixed duration & time per unit
fixed units
fixed units/ time