The thing to when a schedules actual time exceeds the planned time is to find who did it?
False
The PERT Technique is a probabilisitic model
True
A milestone consumes Time but not Resources
Fasle
If the schedule is going better than planned do not need to do anything
False
The reason why any two activities must be done in a particular order is termed a constraint.
True
One of the effects of Constraints is that they generally increase project cost
True
You should only include physical costraints in the initial schedule.
True
A layout is a customized view of activity info
True
There is only one level of activity detail for a construction project
False
You must pick what calender you want for the project and all activities must use this calender
False
When you subcontract all the work then the schedule need not to be resource loaded
False
The best way to contact me is through email
False
The greatest disadvantage of the Gantt Chart was the relationship between activities
False
The two companies that first developed the network logic diagrams were dow and the airforce
False
only Pert schedules have a critical path
False