Cm 4101 Nelson Flashcards

1
Q

The thing to when a schedules actual time exceeds the planned time is to find who did it?

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The PERT Technique is a probabilisitic model

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A milestone consumes Time but not Resources

A

Fasle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If the schedule is going better than planned do not need to do anything

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The reason why any two activities must be done in a particular order is termed a constraint.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

One of the effects of Constraints is that they generally increase project cost

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

You should only include physical costraints in the initial schedule.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A layout is a customized view of activity info

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

There is only one level of activity detail for a construction project

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

You must pick what calender you want for the project and all activities must use this calender

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When you subcontract all the work then the schedule need not to be resource loaded

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The best way to contact me is through email

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The greatest disadvantage of the Gantt Chart was the relationship between activities

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The two companies that first developed the network logic diagrams were dow and the airforce

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

only Pert schedules have a critical path

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The way for a p6 schedule to recalculate the schedule data is to go to “tools”, “schedule”

A

False

17
Q

The menus for p6 are divided into two main parts ____ and ____

A

enterprise data, project data

18
Q

My new projects are stored in ________

A

Enterprise Project Strucutre (EPS)

19
Q

There are three main types of relationships, _____, _____ and _____

A

finish to start, start to start, finish to finish

20
Q

The schedule is the reflection of the _____

A

Plan

21
Q

Network modes have two main techniques ____ and _____

A

Precedence Diagramming Method(PDM) and Evaluation and REview Technique (PERT)

22
Q

_____ are the basic building block of the network

A

Activities

23
Q

What is Lag?

A

Lag specifies an offset or delay between an activity and its successor.

24
Q

In p6 there are four switched to control the outcome of adding resources. List them

A

Fixed Duration
Fixed duration & time per unit
fixed units
fixed units/ time

25
Q

It is common that a quick summary for construction is made in Excel. The data is calculated to show the amount of people in a _____ and the ____ in a line Chart

A

Column Chart, Percent Complete

26
Q

A ____ is the determination of what must be done, how it must be performed, and the sequence order in which it will be performed in order to achieve the objective.

A

Schedule

27
Q

Give two reasons why you should formally schedule the const project.

A

get job done in timely order, manage change

28
Q

The scheduling system is made up of 4 parts

A

plan. do, monitor, control

29
Q

Five major resources a PM/Super must plan for , manage, and control

A
Labor
Materials
equipment
time 
money
30
Q

Name 4 effects constraints have on a scedule

A

reduces schduling flexibilty
lengthen project duration
generally increase project cost
confuse basic scheduling logic