Closing Process Group Flashcards

1
Q

4.7 - Close Project or Phase

Inputs

A
  1. Project Charter
  2. Project Management Plan
    • All Components
  3. Project Documents
    • Assumption Log
    • Basis of Estimates
    • Change Log
    • Issue Log
    • Lessons Learned Register
    • Milestone List
    • Project Communications
    • Quality Control Measurements
    • Quality Reports
    • Requirements Documentation
    • Risk Register
    • Risk Report
  4. Accepted Deliverables
  5. Business Documents
    • Business Case
    • Benefits Management Plan
  6. Agreements
  7. Procurement Documentation
  8. Organizational Process Assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

4.7 - Close Project or Phase

Tools & Techniques

A
  1. Expert Judgement
  2. Data Analysis
    • Document Analysis
    • Regression Analysis
    • Trend Analysis
    • Variance Analysis
  3. Meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

4.7 - Close Project or Phase

Outputs

A
  1. Project Documents Updates
    • Lessons Learned Register
  2. Final Product, Service, Or Result Transition
  3. Final Report