[Clark] Flashcards
Activity
A distinct Scheduled portion of work performed during the course of a project [Clark p.697]
Activity Code
An Alphanumeric value assigned to each activity that enables classifying, sorting, and filtering. [Clark p.697]
Accuracy
Values that are close to the true target value [Clark p.697]
Activity Label
A phrase that names and describes an activity [Clark p.697]
Adaptive Lifecycles
The process within their iterations can be going on in parallel used in application areas where there is a rapid change [Clark p.697]
Actual Cost (AC)
The realized cost incurred for the work performed on an activity during a specific time period [Clark p.697]
Apportioned Effort
An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts [Clark p.697]
Assumption
A factor in the planning process considered to be true, real, or certain, without proof or demonstration [Clark p.697]
Alternative Analysis
A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project [Clark p.697]
Analogous Estimating
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. [Clark p.697]
Change Requests
A formal proposal to modify a document, deliverable, or baseline [Clark p.699]
Baseline
The approved version of a work product that can be changed using formal change control procedures and is used as the basis for comparison to actual results [Clark p.699]
Avoidance
A risk response strategy whereby the project team acts to eliminate the threat of protect the project from its impact [Clark p.699]
Backward Pass
Is a critical path method technique for calculating the late start and late finish dates by working backward through a schedule model from the project end date [Clark p.699]
Balanced Matrix
Is a two-dimensional management structure (matrix) in which employees are assigned to two organizational groups [Clark p.699]
Work Performance data
The raw observations and measurements identified during activities being performed to carry out the project work [Clark p.699]
Budget at Completion (BAC)
The sum of all the budgets established for the work to be performed [Clark p.699]
Benefits Management Plan
Includes the target benefits of the project, such as net present value calculations and the tine frame for realizing benefits [Clark p.699]
Bidder Conferences
Are the meetings between buyers and prospective sellers prior to submittal [Clark p.699]
Bottom-up Estimating
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS) [Clark p.699]
Brainstorming
Uses the combined creative efforts of the project team, experts, and consultants to develop the quality management plan [Clark p.701]
Change Control Board
A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions [Clark p.701]
Code of Accounts
QA numbering system used to uniquely identify each component of the work breakdown structure [Clark p.701]
Work Performance Report
The physical or electronic representation of work performance information compiled in project documents, intended to generate decisions, actions, or awareness [Clark p.701]
Constraint
A factor that limits the options for managing a project, program, portfolio, or process [Clark p.701]
Change Control
A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected. [Clark p.701]
Change Control System
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled [Clark p.701]
Communications Management Plan
A component of the Project, program, or portfolio management plan that describes how, when, and by whom information will be administered and disseminated [Clark p.701]
Configuration Management System
A collection of procedures used to track project artifacts and monitor and control changes to these artifacts [Clark p.701]
Contingency Plan
A document describing actions that the project team can take if predetermined trigger conditions occur. [Clark p.701]
Contingency Reserve
Time or Money allocated in the schedule or cost baseline for known risks with active response strategies [Clark p.703]
Corrective Action
An intentional activity that realigns the performance of the project work with the project management plan [Clark p.703]
Cost Management Plan
A component of a project or program management plan that describes how costs will be planned, structured, and controlled [Clark p.703]
Cost Variance (CV)
The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost [Clark p.703]
Critical Chain Method
A schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties [Clark p.703]
Control Account
A management control point where scope, budget, actual cost, and schedule are integrated and compared to earned value for performance measurement Control Account (CA) is a management control point at which budgets (resource plans) and actual costs are accumulated and compared to earned value for management control purposes. [Clark p.703]
Cost Baseline
The approved version of work package cost estimates and contingency reserve that can be changed using formal change control procedures and is used as the basis for comparison to actual results [Clark p.703]
Cost Performance Index (CPI)
A measure of cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost [Clark p.703]
Crashing
A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources [Clark p.703]
Critical Path
The sequence of activities that represents the longest path through a project, which determines the shortest possible duration [Clark p.703]
Critical Path Activity
An activity on the critical path in a project schedule. [Clark p.705]
Data Date
A point in time when the status of the project is recorded [Clark p.705]
Decomposition
A technique used for dividing and subdividing the project scope and project deliverables into smaller more manageable parts. [Clark p.705]
Deliverable
Anu unique and verifiable product, result, or capability to perform a service that is produced to complete a process, phase, or project [Clark p.705]
Duration
The total number of work periods required to complete an activity or work breakdown structure component, expressed in hours, days, or weeks [Clark p.705]
Critical Path Method
A method used to estimate the minimum project duration and determine the amount of scheduling flexibility the logical network paths within the schedule model [Clark p.705]
Decision Tree Analysis
A diagramming and calculation technique for evaluating the implications of a chain of multiple options in the presence of uncertainty [Clark p.705]
Defect Repair
An intentional activity to modify a nonconforming product or product component [Clark p.705]
Discrete Effort
An activity that can be planned and measured and that yields a specific output [Clark p.705]
Early Finish Date
In the critical path method, the earliest possible point in time when the uncompleted portions of a schedule activity can finish based on the schedule network logic, the data date, and any schedule constraints [Clark p.705]
Early Start Date
In the Critical Path Method the earliest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the data date, and any schedule constraints [Clark p.707]
Earned Value Management
A Methodology that combines scope, schedule, and resource measurements to asses project performance and progress [Clark p.697]
Enterprise Environmental Factors (EEF)
Conditions, not under the immediate control of the team, that influence, constrain, or direct the project, program, or portfolio. [Clark p.707]
Estimate to Complete (ETC)
The expected cost to finish all the remaining project work [Clark p.707]
Finish-to-Finish
A logical relationship in which a successor activity cannot finish until a predecessor activity has finished. [Clark p.707]
Earned Value Management
The measure of work performed expressed in terms of the budget authorized for that work [Clark p.707]
Effort
The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks [Clark p.707]
Estimate at Completion (EAC)
The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete [Clark p.707]
Fast Tracking
The schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration [Clark p.707]
Finish-to-Start
A logical relationship in which a successor activity cannot start until a predecessor activity has finished [Clark p.707]
Fixed Formula Method
A method of estimating earned value in which a specified percentage of the budget value of a work package is assigned to the start milestone and the remaining percentage is assigned when the work package is complete [Clark p.709]
Free Float
The amount of time that a scheduled activity can be delayed without delaying the early start date of any successor or violating a schedule constraint [Clark p.709]
Gantt Chart
A bar chart of schedule information where activities are listed on the vertical axis, dates are shown on the horizontal axis, and activity durations are shown as horizontal bars placed according to the start and finish dates. [Clark p.709]
Late Finish Date
In the critical path method , the attest possible point in time when the uncompleted portions of a schedule activity can finish based on schedule network logic, the project completion date, and any schedule constraints [Clark p.709]
Lead
The amount of time whereby a successor activity can be advanced with respect to a predecessor activity [Clark p.709]
Forward Pass
A critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start date or a given point in time [Clark p.709]
Functional Organization
Organizational structure in which staff is grouped by areas of specialization and the project manager has limited authority to assign work and apply resources [Clark p.709]
Lag
The amount of time whereby a successor activity will be delayed with respect to a predecessor activity [Clark p.709]
Late Start Date
In the critical path method, the latest possible point in time when the uncompleted portions of a schedule activity can start based on the schedule network logic, the project completion date, and any schedule constraints. [Clark p.709]
Lessons Learned
The knowledge gained during a project which shows how project events wee addressed or should be addressed in the future for the purposes of improving future performance [Clark p.709]
Level of Effort (Activity)
In project management, level of effort (LOE) is a support-type project activity that must be done to support other work activities or the entire project effort. … As a result, an LOE activity should never be on the critical path of the project schedule, as it never of itself adds time to the project. [Clark p.711]
Management Reserve
Time or money that management sets aside in addition to the schedule or cost-baseline and releases for ‘unforeseen’ work that is within the scope of the project [Clark p.711]
Milestone
A significant point or event in a project, program, or portfolio [Clark p.711]
Most Likely Duration
An estimate of the most probable activity duration that takes into account all the known variables that could affect performance [Clark p.711]
Near-Critical Path
A sequence of activities with low float which, if exhausted, becomes a critical path sequence for the project [Clark p.711]
Logical Relationship
A dependency between two activities or between an activity and a milestone [Clark p.711]
Matrix Organization
An organization structure in which the project manager shares authority with the functional manager temporarily to assign work and apply resources [Clark p.711]
Milestone Schedule
a type of schedule that presents milestones with planned dates [Clark p.711]
Near-Critical Activity
an activity with a total float that is deemed to be low based on expert judgment [Clark p.711]
Network Logic
All activities and dependencies in a project schedule network diagram [Clark p.711]
Network Path
A sequence of Activities connected by logical relationships in a project schedule network diagram [Clark p.713]
Opportunity
A risk that would have a positive effect on one or more project outcomes [Clark p.713]
Organizational Breakdown Structure
A hierarchical representation of the project organization, which illustrates the relationship between project activities and the organizational units that will perform those activities [Clark p.713]
Organizational Process Assets
Plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization [Clark p.713]
Organizational Project Management Maturity
The level of an organization’s ability to deliver the desired strategic outcomes in a predictable, controllable, and reliable manner. [Clark p.713]
Node
A point at which dependency lines connect on a schedule network diagram [Clark p.713]
Optimistic Duration
An estimate of the shortest activity duration that takes into account all of the known variables that could affect performance [Clark p.713]
Organizational Enabler
A structural, cultural, technological, or human resource practice that the performing organization can use to achieve strategic objectives. [Clark p.713]
Organizational Project Management (OPM)
A framework in which portfolio, program, and project management are integrated with organizational enablers in order to achieve strategic objectives [Clark p.713]
Parametric Estimating
An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters. [Clark p.713]
Path Convergence
A relationship where a scheduled activity has more than one predecessor [Clark p.715]
Percent Complete
An estimate expressed as a percent of the amount of work that has been completed on an activity or a work breakdown structure component [Clark p.715]
Performing Organization
An enterprise whose personnel are the most directly involved in doing the work of the project or program [Clark p.715]
Phase Gate
A review at the end of a phase in which a decision is made to continue to the next phase, to continue with modification, or to end a project or program [Clark p.715]
Portfolio
Projects, programs, subsidiary portfolios, and operations managed as a group to achieve strategic objectives. [Clark p.715]
Path Divergence
A Relationship where a schedule activity has more than one successor [Clark p.715]