Claims Flashcards

1
Q

What are the parts of a claim

A
  1. Facts - contemporary records , witness statements, other evidence (news papers)
  2. Legal basis - contractual an legal provision
    3.Liability - Employer liability to provide relief
  3. Quantum -Amount of EOT/ or other payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Types of claims.

A

1.contractual claims ( arising out of breach express provisions in contract
2.claims at law ( breach of implied law)
3. Quantum merit
4. Ex gratia claims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the grounds which gives Employment to terminate the contract under RB 99?

A

-Fail to comply with performance security requirements (valid /enforceable/ un-extendable)
-commencement delay
-Fail to pass test and remedy defects
-abandon the works and have no intention to perform.
-subcontract whole works without agreement with the employer.
- optional termination (force major)
-Termination at Employer’s convenience
Immediate termination on
Bankruptcy and bribery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the Employer’s risks ( Excluded in works insurance)

A

Under subclause 20.4
-War / Hostility / Invocation/rots
-Presser valves
-radiation action and chemical nuclear fuels
-Loss of damages due to occupation
-Damages due to extent of the Design
-Force of Nature ( Tsunami)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the Varied works

A

17.1 Seeting out Errors
20.3 Employers Risk
31.2 Facilities to other contractors
49.3 Remading defects
65.3 Specisl risk (damages)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Variations

A

51.1 Variations
5.2 Priority of the documents
7.1 supplementary drawings and Instructions
13.1 Works to be in accordance with Engineer
18.1 Boreholes and expository excavations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you explain the provision of Suspension of Works as per your contract?

A

Under clause 40.1
-Breach of contract
-Due to climatic conditions
-Necessary for the proper execution of the works Saftry of the Works.

  • If the suspension last more than 84 days contractor can give notice within 28 to proceed with the works.
    -If not granted terminate the Contract as DEFAULT of Employer.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the delay analysis methods used in the industry?

A

Impacted VS as Planed Analysis
Time impact analysis
Window analysis
Planed Vs Asbuilt analysis
Retrospect long path analysis
collapse asbuilt analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Time at large

A

NO provision in the contract for duration or No provision for EOT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the Heading of suspension claimes

A

Demobalisin Labor
Demobalising Plant
Ideal manpower
cost of protection of works
Cost of the left materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a TIme bar

A

The strict deadline which either party relay on the contractual notice only.
-TO alert the Employer / Engineer.
-Emanble Employer take appropriate actions to manage and Mitigate additional cost.
-Allow to check the contemporary record and swiftly evaluate the claim .