Christopher Johnson Flashcards
PMP Brain Dump
Maslow’s Hierarchy of Needs
Self Actualization Esteem Belonging Safety Physiological
Types of Power for the Project Manager (HR)
Formal (Given by Charter) Expert (Earned on your Own) Reward (Best) Penalty (worst) Referent (Presence Based)
Conflict Resolution Types (HR)
Collaboration / Problem Solving Compromising / Reconciling Focusing / Directing (Worst) Smoothing / Accommodating Withdrawing / Avoiding
Process Groups Main Outputs
Initiating = Charter
Planning = Project Management Plan
Executing = Work Results
Monitoring & Controlling = Corrective Actions
Closing = Product, Service, or Result Transition
Rough Order of Magnitude (ROM)
-25% to +75%
Definitive (or Control)
-5% to +10%
Sigma Percentages
\+/-1 = 68.26% \+/-2 = 95.46% \+/-3 = 99.73% \+/-6 = 99.9997%
Standard Deviation Formula
σ = (Pessimistic - Optimistic) / 6
PERT Formula
Beta = (Pessimistic + (4 * Most Likely) + Optimistic) / 6
Communication Channels Formula
n * (n-1) / 2
Earned Value Formula
EV = % complete * BAC
What you get:
A monetary value.
Schedule Variance (SV)
SV = EV - PV
What you get:
Time units. The interpretation of SV calculated by this formula is the same as the traditional SV formula, i.e., positive SV = project ahead of schedule; negative SV = project behind schedule.
Cost Variance (CV) Formula
CV = EV – AC
What you get:
A monetary amount. A negative number means you are over budget (that’s bad). A positive number means you are under budget (hurrah!). It’s most useful to report CV alongside the project budget so that you can easily see the magnitude of any variance. As mentioned earlier, contemporary project management sees all project variances, positive or negative, as potentially harmful to the project and the performing organization. Similarly to schedule variance, the cost variance outside the defined threshold limit (e.g., +/-15%) should be investigated, and a root cause identified. For example, positive cost variance could be a result of conservative estimation during project planning. If a project was conservatively estimated, extra funds allocated to it could have been spent elsewhere by the organization.
Cost Performance Index (CPI)
CPI = EV / AC
What you get:
A number. You’re aiming for 1. That means that you are getting $1 of value for every $1 spent. You are using your project budget as planned. If it’s more than 1, you are getting more than $1 for every $1 spent. This could mean that your initial budget was not put together in a robust way and your estimates were too conservative.
Estimate at Completion (EAC)
EAC = BAC / CPI
What you get:
A monetary value.