Christopher Johnson Flashcards

PMP Brain Dump

You may prefer our related Brainscape-certified flashcards:
1
Q

Maslow’s Hierarchy of Needs

A
Self Actualization
Esteem
Belonging
Safety
Physiological
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Types of Power for the Project Manager (HR)

A
Formal (Given by Charter)
Expert (Earned on your Own)
Reward (Best)
Penalty (worst)
Referent (Presence Based)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Conflict Resolution Types (HR)

A
Collaboration / Problem Solving
Compromising / Reconciling
Focusing / Directing (Worst)
Smoothing / Accommodating
Withdrawing / Avoiding
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Process Groups Main Outputs

A

Initiating = Charter
Planning = Project Management Plan
Executing = Work Results
Monitoring & Controlling = Corrective Actions
Closing = Product, Service, or Result Transition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Rough Order of Magnitude (ROM)

A

-25% to +75%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Definitive (or Control)

A

-5% to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Sigma Percentages

A
\+/-1 = 68.26%
\+/-2 = 95.46%
\+/-3 = 99.73%
\+/-6 = 99.9997%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Standard Deviation Formula

A

σ = (Pessimistic - Optimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PERT Formula

A

Beta = (Pessimistic + (4 * Most Likely) + Optimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Communication Channels Formula

A

n * (n-1) / 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Earned Value Formula

A

EV = % complete * BAC

What you get:
A monetary value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Schedule Variance (SV)

A

SV = EV - PV

What you get:
Time units. The interpretation of SV calculated by this formula is the same as the traditional SV formula, i.e., positive SV = project ahead of schedule; negative SV = project behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Cost Variance (CV) Formula

A

CV = EV – AC

What you get:
A monetary amount. A negative number means you are over budget (that’s bad). A positive number means you are under budget (hurrah!). It’s most useful to report CV alongside the project budget so that you can easily see the magnitude of any variance. As mentioned earlier, contemporary project management sees all project variances, positive or negative, as potentially harmful to the project and the performing organization. Similarly to schedule variance, the cost variance outside the defined threshold limit (e.g., +/-15%) should be investigated, and a root cause identified. For example, positive cost variance could be a result of conservative estimation during project planning. If a project was conservatively estimated, extra funds allocated to it could have been spent elsewhere by the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost Performance Index (CPI)

A

CPI = EV / AC

What you get:
A number. You’re aiming for 1. That means that you are getting $1 of value for every $1 spent. You are using your project budget as planned. If it’s more than 1, you are getting more than $1 for every $1 spent. This could mean that your initial budget was not put together in a robust way and your estimates were too conservative.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Estimate at Completion (EAC)

A

EAC = BAC / CPI

What you get:
A monetary value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule Performance Index (SPI)

A

SPI = EV / PV

What you get:
A number. Again, as this one is a ratio too you are aiming for 1 as that means you are working through the project at the rate you had expected. If the number is greater than one, it means you are racing through your tasks faster than you had planned (but it doesn’t comment on the quality of the work done – just something to think about!). If the number is less than 1 it means you are progressing more slowly than planned and the tasks are taking longer.

17
Q

Variance at Completion (VAC) Formula

A

VAC = BAC - EAC

What you get:
A monetary value. This shows you how much over or under budget (the variance) we will be at the end of the project. A value of $0 means you’ll hit budget. Less than zero means you’ll be over budget so ideally you’re looking for a number near $0.

18
Q

Estimate to Complete Formula (ETC)

A

What you get:

A monetary value that tells you how much more the project will cost.

19
Q

To Complete Performance Index (TCPI)

A

TCPI = (BAC - EV) / (EAC - AC)

20
Q

3 Point Estimate

A

(Pessimistic + Optimistic + R ) / 3