Chp3: Types of Contracts Flashcards

1
Q

What are the 4 pure types of contracts, from a financial POV?

A

1) Unit Price Contract
2) Cost-Plus Contract
3) Lump Sum Contract
4) Job Ordering Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

1) What are Unit Price Contracts?

A
  • Fixed pricing is determined before start of construction

- Owner will estimate the number of units, and potential bidders will estimate the unit price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the components of a unit price?

A

Low Bidder will be evaluated based on:

1) Direct expenditure
2) Overhead
3) Profit
4) Missing items

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Under Unit Price contract what is a balanced bid?

A

Anticipated costs for the bid are accurately reflected in the unit prices.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Under Unit Price contract what is an Unbalanced bid?

A

Method used by some contractors where unit prices are altered so they do not reflect the true cost of items

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the conditions for an unbalanced bid to maximize profits?

A
  • Does not alter the total amount
    1) Positive cash flow: Increase price of work units that are performed early, to reduce initial investment costs.
    2) Owner’s Estimation Error: Contractor is more confident with his work unit estimations than the owner’s
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What should be the owner’s response to an unbalancing bid?

A
  • Owner’s error in estimation will be very costly
    1) If the unbalanced bid is irregular, reject bid

2) Renegotiate if the actual quantity varies from the
estimated quantity by more than a stated percentage.

3) Resort to a change order that will delete a grossly unbalanced bid item. This may constitute a breach of contract if the deleted work is a large portion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Adv of Unit Pricing?

A

1) Easy for contractor selection
2) Fair basis for competition
3) Changes can be made easily by the owner
4) Lower risk for contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Disadv of Unit Pricing?

A

1) Total project cost is not known at the beginning
2) Owner staffing must be extensive (STAFF must be alert and account for every item)
3) Quantity errors can be very costly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Applications of Unit Pricing?

A

1) Project has to be fairly defined although quantities are difficult to estimate prior to construction.
2) Total construction cost should be slightly deviated from established total price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

2)What are Cost-Plus Contracts?

A

The contractor is reimbursed for most of the direct
expenditures plus an allowance for overhead and
profit. (2 kinds of Eqns)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Adv of Cost-Plus Contracts?

A

o Project definition: scope of work need not
be clearly defined

Advantages:
▪ Work commences without detailed plans.
▪ No negotiations required for changes.
▪ Owner has the complete flexibility to oversee
design and construction.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Disadv of Cost-Plus Contracts?

A

Difficulty for project cost control. (Most of the time is overbudget)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Are there any modifications to Cost-Plus Contracts?

A
1) With guaranteed maximum:
▪ Advantage: Maximum price is
known without detailed design
drawings.
▪ Disadvantage: Contractor’s fee will
be higher due to the added risk.
2) With guaranteed maximum
and incentive:
▪ Advantage: Contractor is motivated
to cut costs (shared savings).
▪ Disadvantage: Contractor fee will
still be high due to added risk.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Applications for Cost-Plus Contracts?

A

These contracts are used when the actual costs of a
project are difficult to estimate with accuracy.

1) Fast delivery
2) When the true nature cannot be
accurately described before construction
begins (e.g., decoration, renovation).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are Lump Sum Contracts?

A

The contract essentially states that the contractor will produce the project as designed
for a stated specific sum.

17
Q

Can an unbalanced bid occur in Lump Sum Contracts?

A

Yes, only for Positive Cash flow, however less risk to the owner compared to unit price.

However, the owner will be at considerable risk if the contractor defaults.

18
Q

Adv of Lump Sum Contracts?

A

1) Less risk for owner
2) Minimal Owner staffing for project
3) Max construction efficiency

19
Q

Disadv of Lump Sum Contracts?

A

1) Changes from owner must be separately negotiated

2) High risk fro contractor, but high return

20
Q

Applications for Lump Sum Contracts?

A

1) When entire design is completed prior to construction
2) Quantities has to be accurately established
3) For owners with limited budget

21
Q

What is Job Order Contracting? (JOC)

A

A contractor will be “on call” for any task, JOC done through multi-year contracts

22
Q

Adv of JOC?

A

1) Established Cost & Fee prior to work
2) Work on short notice
3) Owner can utilise various JOC for diff works

23
Q

Disadv of JOC?

A

Difficult selection of JOC contractors (Reliable, efficient, safe, competent, deliver timely)

24
Q

Applications of JOC?

A

1) Public agencies: Renovation, repair, and
maintenance.

2) Private: Owners with substantial facilities