Chp3: Types of Contracts Flashcards
What are the 4 pure types of contracts, from a financial POV?
1) Unit Price Contract
2) Cost-Plus Contract
3) Lump Sum Contract
4) Job Ordering Contract
1) What are Unit Price Contracts?
- Fixed pricing is determined before start of construction
- Owner will estimate the number of units, and potential bidders will estimate the unit price
What are the components of a unit price?
Low Bidder will be evaluated based on:
1) Direct expenditure
2) Overhead
3) Profit
4) Missing items
Under Unit Price contract what is a balanced bid?
Anticipated costs for the bid are accurately reflected in the unit prices.
Under Unit Price contract what is an Unbalanced bid?
Method used by some contractors where unit prices are altered so they do not reflect the true cost of items
What are the conditions for an unbalanced bid to maximize profits?
- Does not alter the total amount
1) Positive cash flow: Increase price of work units that are performed early, to reduce initial investment costs.
2) Owner’s Estimation Error: Contractor is more confident with his work unit estimations than the owner’s
What should be the owner’s response to an unbalancing bid?
- Owner’s error in estimation will be very costly
1) If the unbalanced bid is irregular, reject bid
2) Renegotiate if the actual quantity varies from the
estimated quantity by more than a stated percentage.
3) Resort to a change order that will delete a grossly unbalanced bid item. This may constitute a breach of contract if the deleted work is a large portion.
Adv of Unit Pricing?
1) Easy for contractor selection
2) Fair basis for competition
3) Changes can be made easily by the owner
4) Lower risk for contractors
Disadv of Unit Pricing?
1) Total project cost is not known at the beginning
2) Owner staffing must be extensive (STAFF must be alert and account for every item)
3) Quantity errors can be very costly
Applications of Unit Pricing?
1) Project has to be fairly defined although quantities are difficult to estimate prior to construction.
2) Total construction cost should be slightly deviated from established total price.
2)What are Cost-Plus Contracts?
The contractor is reimbursed for most of the direct
expenditures plus an allowance for overhead and
profit. (2 kinds of Eqns)
Adv of Cost-Plus Contracts?
o Project definition: scope of work need not
be clearly defined
Advantages: ▪ Work commences without detailed plans. ▪ No negotiations required for changes. ▪ Owner has the complete flexibility to oversee design and construction.
Disadv of Cost-Plus Contracts?
Difficulty for project cost control. (Most of the time is overbudget)
Are there any modifications to Cost-Plus Contracts?
1) With guaranteed maximum: ▪ Advantage: Maximum price is known without detailed design drawings. ▪ Disadvantage: Contractor’s fee will be higher due to the added risk.
2) With guaranteed maximum and incentive: ▪ Advantage: Contractor is motivated to cut costs (shared savings). ▪ Disadvantage: Contractor fee will still be high due to added risk.
Applications for Cost-Plus Contracts?
These contracts are used when the actual costs of a
project are difficult to estimate with accuracy.
1) Fast delivery
2) When the true nature cannot be
accurately described before construction
begins (e.g., decoration, renovation).