Chp 4 - Integration Management Flashcards

1
Q

Project Manager’s primary role

A

Integration management - to pull all the pieces of a project together into a cohesive whole.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2 types of knowledge

A

Explicit - fact-based, easily communicated

Tacit - emotions, experience, abilities. not easily communicated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Types of Change Requests

A

Corrective Action
Preventative Action
Defect Repair

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Change Request Decisions

A

Approved
Rejected
Deferred

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Integration Management Processes

A
Develop Project Charter
Develop Project Management Plan
Direct and Manage Project Work
Manage Project Knowledge
Monitor and Control Project Work
Perform Integrated Change Control
Close Project or Phase
How well did you know this?
1
Not at all
2
3
4
5
Perfectly