Chp 4 - Integration Management Flashcards
1
Q
Project Manager’s primary role
A
Integration management - to pull all the pieces of a project together into a cohesive whole.
2
Q
2 types of knowledge
A
Explicit - fact-based, easily communicated
Tacit - emotions, experience, abilities. not easily communicated
3
Q
Types of Change Requests
A
Corrective Action
Preventative Action
Defect Repair
4
Q
Change Request Decisions
A
Approved
Rejected
Deferred
5
Q
Integration Management Processes
A
Develop Project Charter Develop Project Management Plan Direct and Manage Project Work Manage Project Knowledge Monitor and Control Project Work Perform Integrated Change Control Close Project or Phase