Chapter 9 Thermal Wells Flashcards

1
Q

BOP Elastomers should have a temperature rating of ____ degrees C and a peak working rating of ____ degrees C for one hour emergency services.

A

121C

177C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Flexible hoses should have a temperature rating of ____ degrees C and a peak working rating of ____ degrees C for one hour emergency services

A

121C

160C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Drilling fluids usually consist of brine solution. Increase in temperature will ____ the effective brine weight.

A

Decrease

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why are ECD’s a consideration in thermal wells?

A

ECD’s increase with measure depth, losses might occur into the pair well as the fracture gradient of the horizontal formation doesn’t change.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The recommend reserve drilling fluid additives and volume while drilling thermal wells are ___%.

A

50%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

True or False: any well drilled into, or in close proximity to a thermally enhanced reservoir can be considered to be a Thermal well.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

True or False: While drilling a thermal well, risks are associated with drilling the vertical section as the caprock integrity might be compromised.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Key steps in producing the drilling program for a thermal well are :

A
  • Determine the outer boundaries of the production affected area.
  • Communicate with nearby status of wells proximal to your operations.
  • Consider the heating of wellbore fluids during trips or extended periods of downtime.
  • Drilling fluid contamination.
  • Create the deviation control program (this is issued for all wells including intended straight holes).
  • Estimate the uncertainty in the evaluation of the pore pressure.
  • Consider the lack flexibility in casing seat selection due to directional constraints and caprock.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When drilling both the caprock & thermal sections of a well the following should be considered:

A
  • Closely monitor returns and drilling fluid temperature while drilling.
  • Check all drill pipe to ensure hard banding is of “flush” to minimize potential casing wear.
  • Drilling operations should be suspended if the temperature of the drilling fluid return at surface could present a hazard to personal.
  • When not circulating, the well should be monitored continuously and consider circulating continuously across the trip tank.
  • The trip tank should be kept half full when in use. If it is not being used, the contents should be pumped out and replaced every tour.