Chapter 8 - Discharge by Performance Flashcards
DISCHARGE BY PERFORMANCE
Overview
1) Time for performance
2) Manner of performance
TIME FOR PERFORMANCE
Overview
1) General rule
2) Time is of the essence
3) Time is not of the essence
4) Time in conditional contracts
TIME FOR PERFORMANCE
General rule
1) S.47:
- within reasonable time.
2) Damansara Realty Bhd v Bungsar Hill Holdings Sdn Bhd:
- when the time is at large, duty is to commence work within reasonable time;
- failure to take necessary steps to commence work may amount to breach, i.e. anticipatory breach.
TIME IS OF THE ESSENCE
Overview
1) The law & scope
2) When is time of the essence - general rule
3) Existence of LAD clause
4) Waiver
5) Acceptance of performance other than time specified
6) Failure to perform
TIME IS OF THE ESSENCE
The law & scope
1) The law:
- S.56
2) Scope - Sim Chio Huat v Wong Ted Fui:
- failure to perform at specified time = party may terminate;
- no termination = contract subsisting, time ceases to be of the essence.
- cannot claim damages for late performance unless there is specific clause allowing it.
- can make time of the essence again, but need to send notice of new date of completion.
TIME IS OF THE ESSENCE
When is time of the essence - general rule
Tan Ah Kian v Haji Hasnan:
- EXPRESSLY stipulated in the contract; or
- REASONABLE NOTICE to make time of the essence; or
- NATURE of the contract making it time of the essence.
TIME IS OF THE ESSENCE
When is time of the essence - existence of LAD clause
1) BTS Sdn Bhd v M-Concept Sdn Bhd (FC):
- when there is LAD clause, it points to time not being of the essence.
2) cf. Chye Fook v Teh Teng Seng Realty Sdn Bhd:
- entitlement to LAD does not take away the right to rescind for failure to complete within stipulated time;
- time is still of the essence if it is provided as such.
TIME IS OF THE ESSENCE
Waiver - overview
1) Effect of waiver
2) Silence
3) Continued negotiations
4) Extension of time
5) Extension of time + continued negotiations
WAIVER
Effect of waiver
Sim Chio Fuat v Wong Ted Fui:
- innocent party is deemed to treat the contract as subsisting;
- ctt exists but time is at large;
- cannot claim for liquidated damages unless there is provision for it;
- must give notice if wants to make time of the essence again.
WAIVER
Silence
Araprop Development Sdn Bhd v Leong Chee Kong & Anor:
- mere silence per se cannot amount to waiver;
- there must be additional factor which can be interpreted or inferred as waiver.
WAIVER
Continued negotiations
Wong Kup Sing v Jeram Rubber Estate Ltd:
- Continued negotiations & allowing time to pass amounts to waiver.
WAIVER
Extension of time
Siah Kwee Mow v Kulim Rubber Plantation:
- Mere extension of time stipulated would not amount to waiver.
- extension of time is a waiver for substituting the original time, not waiver for time of the essence.
WAIVER
Extension of time & continued negotiations
Wong Kup Sing v Jeram Rubber Estate Ltd:
- multiple extensions & continued negotiations amount to waiver.
ACCEPTANCE OF PERFORMANCE OTHER THAN TIME SPECIFIED
Overview
1) the law & scope
2) housing development
ACCEPTANCE OF PERFORMANCE OTHER THAN TIME SPECIFIED
the law & scope
1) The law:
- S.56(3)
2) Scope - Yeo Kim Pong Realty Ltd v Ng Kim Pong:
- a party who grants eot to the defaulting party has accepted the performance at other time than the time agreed;
- if he intends to sue for damages for late performance, he must give notice to the defaulting party.
- if no notice is given, he may not be able to recover such compensation.
ACCEPTANCE OF PERFORMANCE OTHER THAN TIME SPECIFIED
housing development
Sentul Raya Sdn Bhd v Hariram Jayaram:
- S.56(3) does not apply to housing development contract;
- Under HDA, purchaser is able to claim for LAD for late delivery once completion dates have passed.
FAILURE TO PERFORM
Overview
1) Effect of failure to perform
2) Options to rescind
3) Rights to damages
FAILURE TO PERFORM
Effect of failure to perform
Linggi Plantations Ltd v Jagatheesan:
- amounts to breach;
- terminate the contract + sue for breach + restitution S.65; OR
- affirm the contract + sue for breach.
FAILURE TO PERFORM
Options to rescind
Loke Yuen Cheng & Anor v Vintex Sdn Bhd:
1) Option 1:
- rescind under S.56(1);
- rescission ab initio;
- remedies: restitution S.65 + 66 ONLY
- cf. with Muralidhar below.
2) Option:
- action for breach under S.40;
- remedies: damages S.76, restitution S.65 +66
FAILURE TO PERFORM
Rights to damages
Muralidhar Chatterjee v International Film Company Ltd:
- damages are claimable despite termination taken under S.56(1) or S.40.
- S.56(1) is also voidable ctt, so S.65 + 66 apply.
TIME IS NOT OF THE ESSENCE
Overview
1) The law
2) When
2) Right to rescind
3) Notice to make time is of the essence
4) Relief for SP
TIME IS NOT OF THE ESSENCE
The law
S.56(2)
TIME IS NOT OF THE ESSENCE
When
KL Landmark Sdn Bhd v Standard Chartered Bank:
- NO EXPRESSION that time is of the essence;
- NO NOTICE is given to make time of the essence;
- NATURE OF THE CONTRACT does not make time is of the essence.
TIME IS NOT OF THE ESSENCE
Right to rescind
Ganam Rajamany v Somoo Sinniah:
- There is no right to rescind if the time is not of the essence.