Chapter 7 Flashcards

1
Q
The master budget is:
A) a flexible budget
B) a static budget
C) developed at the end of the period
D) based on the actual level of output
A

B) a static budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A flexible budget:
A) is another name for management by exception
B) is developed at the end of the period
C) is based on the budgeted level of output
D) provides favorable operating results

A

B) is developed at the end of the period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
Management by exception is the practice of concentrating on:
A) the master budget
B) areas not operating as anticipated
C) favorable variances
D) unfavorable variances
A

B) areas not operating as anticipated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A variance is:
A) the gap between an actual result and a benchmark amount
B) the required number of inputs for one standard output
C) the difference between an actual result and a budgeted amount
D) the difference between a budgeted amount and a standard amount

A

C) the difference between an actual result and a budgeted amount

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

An unfavorable variance indicates that:
A) actual costs are less than budgeted costs
B) actual revenues exceed budgeted revenues
C) the actual amount decreased operating income relative to the budgeted amount
D) All of these answers are correct.

A

C) the actual amount decreased operating income relative to the budgeted amount

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A favorable variance indicates that:
A) budgeted costs are less than actual costs
B) actual revenues exceed budgeted revenues
C) the actual amount decreased operating income relative to the budgeted amount
D) All of these answers are correct.

A

B) actual revenues exceed budgeted revenues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Bowden Corporation used the following data to evaluate their current operating system. The company
sells items for $20 each and used a budgeted selling price of $20 per unit.
Actual Budgeted
Units sold 46,000 units 45,000 units
Variable costs $225,400 $216,000
Fixed costs $47,500 $50,000
7) What is the static-budget variance of revenues?
A) $20,000 favorable
B) $20,000 unfavorable
C) $2,000 favorable
D) $2,000 unfavorable

A

A) (46,000 units × $20) - (45,000 units × $20) = $20,000 F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Bowden Corporation used the following data to evaluate their current operating system. The company
sells items for $20 each and used a budgeted selling price of $20 per unit.
Actual Budgeted
Units sold 46,000 units 45,000 units
Variable costs $225,400 $216,000
Fixed costs $47,500 $50,000

What is the static-budget variance of variable costs?
A) $1,200 favorable
B) $9,400 unfavorable
C) $20,000 favorable
D) $1,200 unfavorable
A

B) $225,400- $216,000 = $9,400 U

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Bowden Corporation used the following data to evaluate their current operating system. The company
sells items for $20 each and used a budgeted selling price of $20 per unit.
Actual Budgeted
Units sold 46,000 units 45,000 units
Variable costs $225,400 $216,000
Fixed costs $47,500 $50,000

What is the static-budget variance of operating income?
A) $10,600 favorable
B) $10,600 unfavorable
C) $13,100 favorable
D) $13,100 unfavorable
A

C) $13,100 favorable

Actual Static Static-budget
Results Budget Variance
Units sold 46,000 45,000     0
Revenues $920,000 $900,000 $20,000 F
Variable costs 225,400 216,000 9,400 U
Contribution margin$694,600 $684,000 10,600 F
Fixed costs 47,500 50,000 (2,500) F
Operating income $647,100 $634,000 $13,100 F
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Caan Corporation used the following data to evaluate their current operating system. The company sells
items for $20 each and used a budgeted selling price of $20 per unit.
Actual Budgeted
Units sold 200,000 units 203,000 units
Variable costs $1,250,000 $1,500,000
Fixed costs $ 925,000 $ 900,000
10) What is the static-budget variance of revenues?
A) $60,000 favorable
B) $60,000 unfavorable
C) $6,000 favorable
D) $6,000 unfavorable

A

B) (200,000 units × $20) - (203,000 units × $20) = $60,000 U

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Caan Corporation used the following data to evaluate their current operating system. The company sells
items for $20 each and used a budgeted selling price of $20 per unit.
Actual Budgeted
Units sold 200,000 units 203,000 units
Variable costs $1,250,000 $1,500,000
Fixed costs $ 925,000 $ 900,000

What is the static-budget variance of variable costs?
A) $200,000 favorable
B) $50,000 unfavorable
C) $250,000 favorable
D) $250,000 unfavorable
A

C) $1,250,000 - $1,500,000= $250,000 F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Caan Corporation used the following data to evaluate their current operating system. The company sells
items for $20 each and used a budgeted selling price of $20 per unit.
Actual Budgeted
Units sold 200,000 units 203,000 units
Variable costs $1,250,000 $1,500,000
Fixed costs $ 925,000 $ 900,000

What is the static-budget variance of operating income?
A) $165,000 favorable
B) $190,000 unfavorable
C) $60,000 favorable
D) $60,000 unfavorable
A

A) Actual Static Static-budget
Results Budget Variance
Units sold 200,000 203,000
Revenues $4,000,000 $4,060,000 $(60,000) U
Variable costs 1,250,000 1,500,000 (250,000) F
Contribution margin$2,750,000 $2,560,000 190,000 F
Fixed costs 925,000 900,000 25,000 U
Operating income $1,825,000 $1,660,000 $165,000 F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Everclean Filter Corporation used the following data to evaluate their current operating system. The
company sells items for $10 each and had used a budgeted selling price of $11 per unit.
Actual Budgeted
Units sold 306,000 units 300,000 units
Variable costs $965,000 $950,000
Fixed costs $ 53,000 $ 50,000
13) What is the static-budget variance of revenues?
A) $60,000 favorable
B) $30,000 unfavorable
C) $30,000 favorable
D) $6,000 favorable

A

C) (306,000 units × $10) - (300,000 units × $11) = $30,000 F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Everclean Filter Corporation used the following data to evaluate their current operating system. The
company sells items for $10 each and had used a budgeted selling price of $11 per unit.
Actual Budgeted
Units sold 306,000 units 300,000 units
Variable costs $965,000 $950,000
Fixed costs $ 53,000 $ 50,000

What is the static-budget variance of variable costs?
A) $13,000 favorable
B) $13,000 unfavorable
C) $15,000 favorable
D) $15,000 unfavorable
A

D) $965,000 - $950,000= $15,000 U

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Everclean Filter Corporation used the following data to evaluate their current operating system. The
company sells items for $10 each and had used a budgeted selling price of $11 per unit.
Actual Budgeted
Units sold 306,000 units 300,000 units
Variable costs $965,000 $950,000
Fixed costs $ 53,000 $ 50,000

What is the static-budget variance of operating income?
A) $12,000 unfavorable
B) $12,000 favorable
C) $15,000 favorable
D) $15,000 unfavorable
A

$12,000 favorable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Regier Company had planned for operating income of $10 million in the master budget but actually
achieved operating income of only $7 million.
A) The static-budget variance for operating income is $3 million favorable.
B) The static-budget variance for operating income is $3 million unfavorable.
C) The flexible-budget variance for operating income is $3 million favorable.
D) The flexible-budget variance for operating income is $3 million unfavorable.

A

B) The static-budget variance for operating income is $3 million unfavorable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The master budget is one type of flexible budget.

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

A flexible budget is calculated at the end of the budget period.

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Information regarding the causes of variances is provided when the master budget is compared with
actual results.

A

FALSE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A variance is the difference between the actual cost for the current and expected (or budgeted)
performance

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A favorable variance results when actual costs exceed budgeted costs

A

FALSE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Management by exception is the practice of concentrating on areas not operating as anticipated
(such as a cost overrun) and placing less attention on areas operating as anticipated.

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

The essence of variance analysis is to capture a departure from what was expected.

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

A favorable variance should be ignored by management.

A

FALSE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
An unfavorable variance may be due to poor planning rather than due to inefficiency.
TRUE
26
``` The flexible budget contains: A) budgeted amounts for actual output B) budgeted amounts for planned output C) actual costs for actual output D) actual costs for planned output ```
A) budgeted amounts for actual output
27
``` The following items are the same for the flexible budget and the master budget EXCEPT for: A) variable cost per unit B) total fixed costs C) units sold D) sales price per unit ```
C) units sold
28
``` The sales-volume variance is due to: A) using a different selling price from that budgeted B) inaccurate forecasting of units sold C) poor production performance D) Both A and B are correct. ```
B) inaccurate forecasting of units sold
29
An unfavorable sales-volume variance could result from: A) decreased demand for the product B) competitors taking market share C) customer dissatisfaction with the product D) All of these answers are correct.
D) All of these answers are correct.
30
``` If a sales-volume variance was caused by poor-quality products, then the ________ would be in the best position to explain the variance. A) production manager B) sales manager C) purchasing manager D) management accountant ```
A) production manager
31
``` The variance that is best for measuring operating performance is the: A) static-budget variance B) flexible-budget variance C) sales-volume variance D) selling-price variance ```
B) flexible-budget variance
32
An unfavorable flexible-budget variance for variable costs may be the result of: A) using more input quantities than were budgeted B) paying higher prices for inputs than were budgeted C) selling output at a higher selling price than budgeted D) Both A and B are correct.
D) Both A and B are correct.
33
An unfavorable variance: A) may suggest investigation is needed B) is conclusive evidence of poor performance C) demands that standards be recomputed D) indicates continuous improvement is needed
A) may suggest investigation is needed
34
All of the following are needed to prepare a flexible budget EXCEPT determining the: A) budgeted variable cost per output unit B) budgeted fixed costs C) actual selling price per unit D) actual quantity of output units
C) actual selling price per unit
35
The variance that LEAST affects cost control is the: A) flexible-budget variance B) direct-material-price variance C) sales-volume variance D) direct manufacturing labor efficiency variance
C) sales-volume variance
36
A flexible-budget variance is $600 favorable for unit-related costs. This indicates that costs were: A) $600 more than the master budget B) $600 less than for the planned level of activity C) $600 more than standard for the achieved level of activity D) $600 less than standard for the achieved level of activity
D) $600 less than standard for the achieved level of activity
37
JJ Abrams planned to use $164 of material per unit but actually used $160 of material per unit, and planned to make 1,200 units but actually made 1,000 units. 12) The flexible-budget amount is: A) $160,000 B) $164,000 C) $192,000 D) $196,800
B) 1,000 units × $164 = $164,000
38
JJ Abrams planned to use $164 of material per unit but actually used $160 of material per unit, and planned to make 1,200 units but actually made 1,000 units. ``` The flexible-budget variance is: A) $4,000 favorable B) $28,000 unfavorable C) $32,800 unfavorable D) $4,800 favorable ```
A) ($160 - $164) × 1,000 = $4,000 F
39
JJ Abrams planned to use $164 of material per unit but actually used $160 of material per unit, and planned to make 1,200 units but actually made 1,000 units. The sales-volume variance is: A) $4,000 favorable B) $28,000 unfavorable C) $32,800 unfavorable D) $4,800 favorable
C) (1,000 - 1,200) × $164 = $32,800 U
40
Bebee Corporation currently produces cardboard boxes in an automated process. Expected production per month is 40,000 units, direct-material costs are $0.60 per unit, and manufacturing overhead costs are $18,000 per month. Manufacturing overhead is all fixed costs. What is the flexible budget for 20,000 and 40,000 units, respectively? A) $21,000; $33,000 B) $21,000; $42,000 C) $30,000; $42,000 D) None of these answers are correct.
Explanation: C) 20,000 units 40,000 units Materials ($0.60) $ 12,000 $24,000 Machinery 18,000 18,000 $30,000 $42,000
41
Brennen Incorporated planned to use $24 of material per unit but actually used $25 of material per unit, and planned to make 2,000 units but actually made 2,400 units. The flexible-budget amount is: A) $48,000 B) $50,000 C) $57,600 D) $60,000
C) 2,400 units × $24 = $57,600
42
Brennen Incorporated planned to use $24 of material per unit but actually used $25 of material per unit, and planned to make 2,000 units but actually made 2,400 units. The flexible-budget variance is: A) $9,600 favorable B) $2,400 unfavorable C) $10,000 unfavorable D) $12,000 favorable
B) ($25 - $24) × 2,400 = $2,400 U
43
Brennen Incorporated planned to use $24 of material per unit but actually used $25 of material per unit, and planned to make 2,000 units but actually made 2,400 units. The sales-volume variance is: A) $9,600 favorable B) $2,400 unfavorable C) $10,000 unfavorable D) $12,000 favorable
A) (2,400 - 2,000) × $24 = $9,600 F
44
Melville Incorporated planned to use $37.50 of material per unit but actually used $36.75 of material per unit, and planned to make 1,800 units but actually made 1,600 units The flexible-budget amount is: A) $60,000 B) $67,500 C) $59,200 D) $1,200
A) 1,600 units × $37.50 = $60,000
45
Melville Incorporated planned to use $37.50 of material per unit but actually used $36.75 of material per unit, and planned to make 1,800 units but actually made 1,600 units The flexible-budget variance is: A) $7,500 favorable B) $7,500 unfavorable C) $1,200 unfavorable D) $1,200 favorable
D) ($36.75 - $37.50) × 1,600 = $1,200 F
46
Melville Incorporated planned to use $37.50 of material per unit but actually used $36.75 of material per unit, and planned to make 1,800 units but actually made 1,600 units The sales-volume variance is: A) $7,500 favorable B) $7,500 unfavorable C) $1,200 unfavorable D) $1,200 favorable
B) (1,600 - 1,800) × $37.50 = $7,500 U
47
Hemberger Corporation currently produces baseball caps in an automated process. Expected production per month is 20,000 units, direct material costs are $3.00 per unit, and manufacturing overhead costs are $46,000 per month. Manufacturing overhead is entirely fixed costs. What is the flexible budget for 10,000 and 20,000 units, respectively? A) $53,000; $83,000 B) $53,000; $106,000 C) $76,000; $106,000 D) None of these answers are correct.
Explanation: C) 10,000 units 20,000 units Materials ($3.00) $30,000 $60,000 Machinery 46,000 46,000 $76,000 $106,000
48
The actual information pertains to the month of September. As part of the budgeting process, Kriger Fencing Company developed the following static budget for September. Kriger is in the process of preparing the flexible budget and understanding the results. Actual Flexible Static Results Budget Budget Sales volume (in units) 10,000 ________12,500 Sales revenues $500,000 _________ $625,000 Variable costs 256,000 $ ________ 300,000 Contribution margin 244,000 _______$ 325,000 Fixed costs 229,000 $ ________ 225,000 Operating profit $ 15,000 $ _________$ 100,000 ``` The flexible budget will report ________ for the fixed costs. A) $229,000 B) $225,000 C) $180,000 D) $286,250 ```
B) $225,000, given in the static budget
49
The actual information pertains to the month of September. As part of the budgeting process, Kriger Fencing Company developed the following static budget for September. Kriger is in the process of preparing the flexible budget and understanding the results. Actual Flexible Static Results Budget Budget Sales volume (in units) 10,000 ________12,500 Sales revenues $500,000 _________ $625,000 Variable costs 256,000 $ ________ 300,000 Contribution margin 244,000 _______$ 325,000 Fixed costs 229,000 $ ________ 225,000 Operating profit $ 15,000 $ _________$ 100,000 ``` The flexible budget will report ________ for variable costs. A) $256,000 B) $300,000 C) $240,000 D) $320,000 ```
C) 10,000 units × $300,000/12,500 = $240,000
50
The actual information pertains to the month of September. As part of the budgeting process, Kriger Fencing Company developed the following static budget for September. Kriger is in the process of preparing the flexible budget and understanding the results. Actual Flexible Static Results Budget Budget Sales volume (in units) 10,000 ________12,500 Sales revenues $500,000 _________ $625,000 Variable costs 256,000 $ ________ 300,000 Contribution margin 244,000 _______$ 325,000 Fixed costs 229,000 $ ________ 225,000 Operating profit $ 15,000 $ _________$ 100,000 ``` The flexible-budget variance for variable costs is: A) $16,000 unfavorable B) $60,000 unfavorable C) $16,000 favorable D) $60,000 favorable ```
A) $256,000 - (10,000 × $300,000/12,500) = $16,000 U
51
The static-budget variance can be subdivided into the flexible-budget variance and the sales-volume variance.
TRUE
52
The flexible-budget variance may be the result of inaccurate forecasting of units sold.
FALSE
53
Decreasing demand for a product may create a favorable sales-volume variance.
FALSE
54
An unfavorable variance is conclusive evidence of poor performance.
FALSE
55
A company would NOT need to use a flexible budget if it had perfect foresight about actual output units
TRUE
56
The flexible-budget variance for direct-cost inputs is subdivided into two detailed variances, the efficiency variance and the price variance.
TRUE
57
The actual information pertains to the month of September. As part of the budgeting process, Kriger Fencing Company developed the following static budget for September. Kriger is in the process of preparing the flexible budget and understanding the results. Actual Flexible Static Results Budget Budget Sales volume (in units) 10,000________ 12,500 Sales revenues $500,000 $_______ $625,000 Variable costs 256,000 $ ________ 300,000 Contribution margin 244,000 $_______ 325,000 Fixed costs 229,000 $ ________ 225,000 Operating profit $ 15,000 $_________ $ 100,000 ``` The primary reason for low operating profits was: A) the variable-cost variance B) increased fixed costs C) a poor management accounting system D) lower sales volume than planned ```
D) lower sales volume than planned
58
The actual information pertains to the third quarter. As part of the budgeting process, the Duck Decoy Department of Wooden Figurines Incorporated had developed the following static budget for the third quarter. Duck Decoy is in the process of preparing the flexible budget and understanding the results. Actual Flexible Static Results Budget Budget Sales volume (in units) 13,000 ________12,000 Sales revenues $257,500 $_________ $250,000 Variable costs 154,000 $ ________ 175,000 Contribution margin 103,500 $__________ 75,000 Fixed costs 50,500 $ ________ 49,500 Operating profit $ 53,000 $ $______ 25,500
``` The flexible budget will report ________ for variable costs. A) $154,000 B) $189,583 C) $175,000 D) $13,583 ``` B) 13,000 units × $175,000/12,000 = $189,583
59
The actual information pertains to the third quarter. As part of the budgeting process, the Duck Decoy Department of Wooden Figurines Incorporated had developed the following static budget for the third quarter. Duck Decoy is in the process of preparing the flexible budget and understanding the results. Actual Flexible Static Results Budget Budget Sales volume (in units) 13,000 ________12,000 Sales revenues $257,500 $_________ $250,000 Variable costs 154,000 $ ________ 175,000 Contribution margin 103,500 $__________ 75,000 Fixed costs 50,500 $ ________ 49,500 Operating profit $ 53,000 $ $______ 25,500 ``` The flexible budget will report ________ for the fixed costs. A) $50,500 B) $49,500 Favorable C) $49,500 D) $1,000 Unfavorable ```
C) $49.500, given in the static budget
60
The actual information pertains to the third quarter. As part of the budgeting process, the Duck Decoy Department of Wooden Figurines Incorporated had developed the following static budget for the third quarter. Duck Decoy is in the process of preparing the flexible budget and understanding the results. Actual Flexible Static Results Budget Budget Sales volume (in units) 13,000 ________12,000 Sales revenues $257,500 $_________ $250,000 Variable costs 154,000 $ ________ 175,000 Contribution margin 103,500 $__________ 75,000 Fixed costs 50,500 $ ________ 49,500 Operating profit $ 53,000 $ $______ 25,500 ``` The flexible-budget variance for variable costs is: A) $21,000 favorable B) $13,583 unfavorable C) $35,583 unfavorable D) $35,583 favorable ```
D) [(13,000 × $175,000/12,000)] - $154,000 = $35,583 F
61
``` The primary reason for high actual operating profits was: A) the variable-cost variance B) increased fixed costs C) higher sales volume than planned D) lower sales volume than planned ```
A) the variable-cost variance
62
Act. Results Flex. Bud. Variances Flex Bud. Units Sold 450k -------- 450k Revenues 168,320 4k F (A) Variable Costs (C) 800 U 63,440 Fixed Costs 33120 3440 F 36560 Op. Inc. 70960 (D) 64320 Sales-Vol. Vari. Static Budget Units Sold -------- 412,500 Revenues 5600 U (B) Vari. Costs 9,360 F 72,800 Fixed Costs 0 36560 Op. Inc. (E) 60560 ``` What amounts are reported for revenues in the flexible-budget (A) and the static-budget (B), respectively? A) $164,320; $158,720 B) $164,320; $169,920 C) $169,920; $177,920 D) $169,920; $166,720 ```
B) $164,320; $169,920
63
Act. Results Flex. Bud. Variances Flex Bud. Units Sold 450k -------- 450k Revenues 168,320 4k F (A) Variable Costs (C) 800 U 63,440 Fixed Costs 33120 3440 F 36560 Op. Inc. 70960 (D) 64320 Sales-Vol. Vari. Static Budget Units Sold -------- 412,500 Revenues 5600 U (B) Vari. Costs 9,360 F 72,800 Fixed Costs 0 36560 Op. Inc. (E) 60560 ``` What are the actual variable costs (C)? A) $72,800 B) $64,240 C) $62,640 D) $54,080 ```
B) $64,240
64
Act. Results Flex. Bud. Variances Flex Bud. Units Sold 450k -------- 450k Revenues 168,320 4k F (A) Variable Costs (C) 800 U 63,440 Fixed Costs 33120 3440 F 36560 Op. Inc. 70960 (D) 64320 Sales-Vol. Vari. Static Budget Units Sold -------- 412,500 Revenues 5600 U (B) Vari. Costs 9,360 F 72,800 Fixed Costs 0 36560 Op. Inc. (E) 60560 ``` What is the total flexible-budget variance (D)? A) $240 unfavorable B) $0 C) $1,360 favorable D) $6,640 favorable ```
D) $6,640 favorable
65
Act. Results Flex. Bud. Variances Flex Bud. Units Sold 450k -------- 450k Revenues 168,320 4k F (A) Variable Costs (C) 800 U 63,440 Fixed Costs 33120 3440 F 36560 Op. Inc. 70960 (D) 64320 Sales-Vol. Vari. Static Budget Units Sold -------- 412,500 Revenues 5600 U (B) Vari. Costs 9,360 F 72,800 Fixed Costs 0 36560 Op. Inc. (E) 60560 ``` What is the total sales-volume variance (E)? A) $14,960 unfavorable B) $5,600 unfavorable C) $3,760 favorable D) $14,960 favorable ```
C) $3,760 favorable
66
Act. Results Flex. Bud. Variances Flex Bud. Units Sold 450k -------- 450k Revenues 168,320 4k F (A) Variable Costs (C) 800 U 63,440 Fixed Costs 33120 3440 F 36560 Op. Inc. 70960 (D) 64320 Sales-Vol. Vari. Static Budget Units Sold -------- 412,500 Revenues 5600 U (B) Vari. Costs 9,360 F 72,800 Fixed Costs 0 36560 Op. Inc. (E) 60560 ``` What is the total static-budget variance? A) $10,400 favorable B) $6,640 favorable C) $3,760 unfavorable D) $3,760 favorable ```
A) $10,400 favorable
67
The flexible-budget variance pertaining to revenues is often called a selling-price variance.
TRUE
68
Cost control is the focus of the sales-volume variance.
FALSE
69
The flexible-budget variance for direct cost inputs can be further subdivided into a: A) static-budget variance and a sales-volume variance B) sales-volume variance and an efficiency variance C) price variance and an efficiency variance D) static-budget variance and a price variance
C) price variance and an efficiency variance
70
2) Budgeted input quantity information may be obtained from: A) actual input quantities used last period B) standards developed by your company C) data from other companies that have similar processes D) All of these answers are correct.
D) All of these answers are correct.
71
When actual input data from past periods is used to develop a budget: A) past inefficiencies are excluded B) expected future changes are incorporated C) information is available at a low cost D) audited financial information must be used
C) information is available at a low cost
72
When standards are used to develop a budget: A) past inefficiencies are excluded B) benchmarking must also be used C) information is available at a low cost D) flexible-budget amounts are difficult to determine
A) past inefficiencies are excluded
73
The term budget indicates: A) that standards have been used to develop the budget B) that actual input data from past periods have been used to develop the budget C) that engineering studies have been used to develop the budget D) planned amounts for a future accounting period
D) planned amounts for a future accounting period
74
A standard input: A) is a carefully determined price, cost, or quantity B) is usually expressed on a per unit basis C) may be developed using engineering studies D) All of these answers are correct.
D) All of these answers are correct.
75
``` Ideal standards: A) assume peak operating conditions B) allow for normal machine breakdowns C) greatly improve employee motivation and performance D) All of these answers are correct ```
A) assume peak operating conditions
76
Diana Industries, Inc. (DII), developed standard costs for direct material and direct labor. In 2010, DII estimated the following standard costs for one of their major products, the 10-gallon plastic container. Budgeted quantity Budgeted price Direct materials 0.10 pounds $30 per pound Direct labor 0.05 hours $15 per hour During June, DII produced and sold 10,000 containers using 980 pounds of direct materials at an average cost per pound of $32 and 500 direct manufacturing labor-hours at an average wage of $15.25 per hour. ``` June's direct material efficiency variance is: A) $1,860 unfavorable B) $600 favorable C) $1,360 favorable D) None of these answers are correct. ```
B) $30 × (980 - 1,000) = $600 F
77
Managers generally have more control over price variances than efficiency variances.
FALSE
78
To prepare budgets based on actual data from past periods is preferred since past inefficiencies are EXCLUDED.
FALSE
79
All budgets are based on standard costs.
FALSE
80
A standard is attainable through efficient operations but allows for normal disruptions such as machine breakdowns and defective production.
TRUE
81
One advantage of using standard times to develop a budget is they are simple to compile, are based solely on the past actual history, and do NOT require expected future changes to be taken into account.
FALSE
82
A favorable price variance for direct materials indicates that: A) a lower price than planned was paid for materials B) a higher price than planned was paid for materials C) less material was used during production than planned for actual output D) more material was used during production than planned for actual output
A) a lower price than planned was paid for materials
83
A favorable efficiency variance for direct manufacturing labor indicates that: A) a lower wage rate than planned was paid for direct labor B) a higher wage rate than planned was paid for direct labor C) less direct manufacturing labor-hours were used during production than planned for actual output D) more direct manufacturing labor-hours were used during production than planned for actual output
C) less direct manufacturing labor-hours were used during production than planned for actual output
84
An unfavorable price variance for direct materials might indicate: A) that the purchasing manager purchased in smaller quantities due to a change to just-in-time inventory methods B) congestion due to scheduling problems C) that the purchasing manager skillfully negotiated a better purchase price D) that the market had an unexpected oversupply of those materials
A) that the purchasing manager purchased in smaller quantities due to a change to just-in-time inventory methods
85
A favorable efficiency variance for direct materials might indicate: A) that lower-quality materials were purchased B) an overskilled workforce C) poor design of products or processes D) a lower-priced supplier was used
B) an overskilled workforce
86
A favorable price variance for direct manufacturing labor might indicate that: A) employees were paid more than planned B) budgeted price standards are too tight C) underskilled employees are being hired D) an efficient labor force
C) underskilled employees are being hired
87
An unfavorable efficiency variance for direct manufacturing labor might indicate that: A) work was efficiently scheduled B) machines were not properly maintained C) budgeted time standards are too lax D) more higher-skilled workers were scheduled than planned
B) machines were not properly maintained
88
Diana Industries, Inc. (DII), developed standard costs for direct material and direct labor. In 2010, DII estimated the following standard costs for one of their major products, the 10-gallon plastic container. Budgeted quantity Budgeted price Direct materials 0.10 pounds $30 per pound Direct labor 0.05 hours $15 per hour During June, DII produced and sold 10,000 containers using 980 pounds of direct materials at an average cost per pound of $32 and 500 direct manufacturing labor-hours at an average wage of $15.25 per hour. ``` June's direct material flexible-budget variance is: A) $1,860 unfavorable B) $600 favorable C) $1,360 unfavorable D) None of these answers are correct. ```
C) (980 × $32) - (10,000 × 0.10 × $30) = $1,360 U
89
Diana Industries, Inc. (DII), developed standard costs for direct material and direct labor. In 2010, DII estimated the following standard costs for one of their major products, the 10-gallon plastic container. Budgeted quantity Budgeted price Direct materials 0.10 pounds $30 per pound Direct labor 0.05 hours $15 per hour During June, DII produced and sold 10,000 containers using 980 pounds of direct materials at an average cost per pound of $32 and 500 direct manufacturing labor-hours at an average wage of $15.25 per hour. ``` June's direct material price variance is: A) $1,960 unfavorable B) $600 favorable C) $1,360 favorable D) None of these answers are correct. ```
A) 980 × ($32 - $30) = $1,960 U
90
Diana Industries, Inc. (DII), developed standard costs for direct material and direct labor. In 2010, DII estimated the following standard costs for one of their major products, the 10-gallon plastic container. Budgeted quantity Budgeted price Direct materials 0.10 pounds $30 per pound Direct labor 0.05 hours $15 per hour During June, DII produced and sold 10,000 containers using 980 pounds of direct materials at an average cost per pound of $32 and 500 direct manufacturing labor-hours at an average wage of $15.25 per hour. ``` June's direct manufacturing labor price variance is: A) $125 unfavorable B) $125 favorable C) $7,623.50 unfavorable D) None of these answers are correct. ```
A) 500 dlh × ($15.25 - $15.00) = $125 U
91
Diana Industries, Inc. (DII), developed standard costs for direct material and direct labor. In 2010, DII estimated the following standard costs for one of their major products, the 10-gallon plastic container. Budgeted quantity Budgeted price Direct materials 0.10 pounds $30 per pound Direct labor 0.05 hours $15 per hour During June, DII produced and sold 10,000 containers using 980 pounds of direct materials at an average cost per pound of $32 and 500 direct manufacturing labor-hours at an average wage of $15.25 per hour. ``` June's direct manufacturing labor efficiency variance is: A) $125 unfavorable B) $125 favorable C) $7,623.50 unfavorable D) None of these answers are correct. ```
D) 500 dlh - (10,000 × 0.05)] × $15 = Zero
92
Sawyer Industries, Inc. (SII), developed standard costs for direct material and direct labor. In 2011, SII estimated the following standard costs for one of their major products, the 30-gallon heavy-duty plastic container. Budgeted quantity Budgeted price Direct materials 0.20 pounds $25 per pound Direct labor 0.10 hours $15 per hour During July, SII produced and sold 5,000 containers using 1,100 pounds of direct materials at an average cost per pound of $24 and 525 direct manufacturing labor hours at an average wage of $14.75 per hour ``` July's direct material flexible-budget variance is: A) $1,400 unfavorable B) $21,100 favorable C) $2,500 unfavorable D) None of these answers are correct ```
A) (1,100 × $24) - (5,000 × 0.20 × $25) = $1,400 U
93
Sawyer Industries, Inc. (SII), developed standard costs for direct material and direct labor. In 2011, SII estimated the following standard costs for one of their major products, the 30-gallon heavy-duty plastic container. Budgeted quantity Budgeted price Direct materials 0.20 pounds $25 per pound Direct labor 0.10 hours $15 per hour During July, SII produced and sold 5,000 containers using 1,100 pounds of direct materials at an average cost per pound of $24 and 525 direct manufacturing labor hours at an average wage of $14.75 per hour ``` July's direct material price variance is: A) $1,400 favorable B) $1,100 favorable C) $2,500 unfavorable D) None of these answers are correct. ```
B) 1,100 × ($24 - $25) = $1,100 F
94
Sawyer Industries, Inc. (SII), developed standard costs for direct material and direct labor. In 2011, SII estimated the following standard costs for one of their major products, the 30-gallon heavy-duty plastic container. Budgeted quantity Budgeted price Direct materials 0.20 pounds $25 per pound Direct labor 0.10 hours $15 per hour During July, SII produced and sold 5,000 containers using 1,100 pounds of direct materials at an average cost per pound of $24 and 525 direct manufacturing labor hours at an average wage of $14.75 per hour
C) $25 × [1,100 - (5,000 × 0.20)] = $2,500 U
95
Sawyer Industries, Inc. (SII), developed standard costs for direct material and direct labor. In 2011, SII estimated the following standard costs for one of their major products, the 30-gallon heavy-duty plastic container. Budgeted quantity Budgeted price Direct materials 0.20 pounds $25 per pound Direct labor 0.10 hours $15 per hour During July, SII produced and sold 5,000 containers using 1,100 pounds of direct materials at an average cost per pound of $24 and 525 direct manufacturing labor hours at an average wage of $14.75 per hour ``` July's direct manufacturing labor flexible-budget variance is: A) $375.00 unfavorable B) $131.25 favorable C) $243.75 unfavorable D) None of these answers are correct. ```
C) (525 × $14.75) - (5,000 × 0.10 × $15) = $243.75 U
96
Sawyer Industries, Inc. (SII), developed standard costs for direct material and direct labor. In 2011, SII estimated the following standard costs for one of their major products, the 30-gallon heavy-duty plastic container. Budgeted quantity Budgeted price Direct materials 0.20 pounds $25 per pound Direct labor 0.10 hours $15 per hour During July, SII produced and sold 5,000 containers using 1,100 pounds of direct materials at an average cost per pound of $24 and 525 direct manufacturing labor hours at an average wage of $14.75 per hour ``` July's direct manufacturing labor price variance is: A) $375.00 unfavorable B) $131.25 favorable C) $243.75 favorable D) None of these answers are correct. ```
B) 525 dlh × ($14.75 - $15.00) = $131.25 F
97
Sawyer Industries, Inc. (SII), developed standard costs for direct material and direct labor. In 2011, SII estimated the following standard costs for one of their major products, the 30-gallon heavy-duty plastic container. Budgeted quantity Budgeted price Direct materials 0.20 pounds $25 per pound Direct labor 0.10 hours $15 per hour During July, SII produced and sold 5,000 containers using 1,100 pounds of direct materials at an average cost per pound of $24 and 525 direct manufacturing labor hours at an average wage of $14.75 per hour ``` July's direct manufacturing labor efficiency variance is: A) $375.00 unfavorable B) $131.25 favorable C) $243.75 favorable D) None of these answers are correct. ```
A) [525 dlh - (5,000 × 0.10)] × $15 = $375 U
98
Apple Valley Orchards, Inc. (AVO), developed standard costs for direct material and direct labor. In 2011, AVO estimated the following standard costs for one of their most well loved products, the AVO classic Grandma's large apple pie which had a brown sugar coating on the top of the crust as well as including cranberry and mince ingredients in addition to the apples. Budgeted quantity Budgeted price Direct materials 1.5 pounds $7.25 per pound Direct labor 0.25 hours $14.00 per hour During September, AVO produced and sold 1,200 pies using 1,875 pounds of direct materials at an average cost per pound of $7.00 and 280 direct labor hours at an average wage of $14.25 per hour. ``` September's direct material flexible-budget variance is: A) $100.00 unfavorable B) $100.00 favorable C) $75.00 unfavorable D) None of these answers are correct. ```
C) (1,875 × $7.00) - (1,200 × 1.5 × $7.25) = $75.00 U
99
Apple Valley Orchards, Inc. (AVO), developed standard costs for direct material and direct labor. In 2011, AVO estimated the following standard costs for one of their most well loved products, the AVO classic Grandma's large apple pie which had a brown sugar coating on the top of the crust as well as including cranberry and mince ingredients in addition to the apples. Budgeted quantity Budgeted price Direct materials 1.5 pounds $7.25 per pound Direct labor 0.25 hours $14.00 per hour During September, AVO produced and sold 1,200 pies using 1,875 pounds of direct materials at an average cost per pound of $7.00 and 280 direct labor hours at an average wage of $14.25 per hour. ``` September's direct material price variance is: A) $468.75 favorable B) $468.75 unfavorable C) $75.00 unfavorable D) None of these answers are correct. ```
A) 1,875 × ($7.00 - $7.25) = $468.75 F
100
Apple Valley Orchards, Inc. (AVO), developed standard costs for direct material and direct labor. In 2011, AVO estimated the following standard costs for one of their most well loved products, the AVO classic Grandma's large apple pie which had a brown sugar coating on the top of the crust as well as including cranberry and mince ingredients in addition to the apples. Budgeted quantity Budgeted price Direct materials 1.5 pounds $7.25 per pound Direct labor 0.25 hours $14.00 per hour During September, AVO produced and sold 1,200 pies using 1,875 pounds of direct materials at an average cost per pound of $7.00 and 280 direct labor hours at an average wage of $14.25 per hour. ``` September's direct material efficiency variance is: A) $468.75 favorable B) $468.75 unfavorable C) $543.75 favorable D) $543.75 unfavorable ```
D) $7.25 × [1,875 - (1,200 × 1.5)] = $543.75 U
101
Apple Valley Orchards, Inc. (AVO), developed standard costs for direct material and direct labor. In 2011, AVO estimated the following standard costs for one of their most well loved products, the AVO classic Grandma's large apple pie which had a brown sugar coating on the top of the crust as well as including cranberry and mince ingredients in addition to the apples. Budgeted quantity Budgeted price Direct materials 1.5 pounds $7.25 per pound Direct labor 0.25 hours $14.00 per hour During September, AVO produced and sold 1,200 pies using 1,875 pounds of direct materials at an average cost per pound of $7.00 and 280 direct labor hours at an average wage of $14.25 per hour. ``` September's direct labor flexible-budget variance is: A) $210.00 favorable B) $210.00 unfavorable C) $280.00 favorable D) $280.00 unfavorable. ```
A) (280 × $14.25) - (1,200 × 0..25 × $14) = $210.00 F
102
Apple Valley Orchards, Inc. (AVO), developed standard costs for direct material and direct labor. In 2011, AVO estimated the following standard costs for one of their most well loved products, the AVO classic Grandma's large apple pie which had a brown sugar coating on the top of the crust as well as including cranberry and mince ingredients in addition to the apples. Budgeted quantity Budgeted price Direct materials 1.5 pounds $7.25 per pound Direct labor 0.25 hours $14.00 per hour During September, AVO produced and sold 1,200 pies using 1,875 pounds of direct materials at an average cost per pound of $7.00 and 280 direct labor hours at an average wage of $14.25 per hour. ``` September's direct labor price variance is: A) $210.00 unfavorable B) $210.00 favorable C) $70.00 unfavorable D) $70.00 favorable ```
C) 280 dlh × ($14.25 - $14.00) = $70 U
103
Apple Valley Orchards, Inc. (AVO), developed standard costs for direct material and direct labor. In 2011, AVO estimated the following standard costs for one of their most well loved products, the AVO classic Grandma's large apple pie which had a brown sugar coating on the top of the crust as well as including cranberry and mince ingredients in addition to the apples. Budgeted quantity Budgeted price Direct materials 1.5 pounds $7.25 per pound Direct labor 0.25 hours $14.00 per hour During September, AVO produced and sold 1,200 pies using 1,875 pounds of direct materials at an average cost per pound of $7.00 and 280 direct labor hours at an average wage of $14.25 per hour. ``` September's direct labor efficiency variance is: A) $280.00 favorable B) $280.00 unfavorable C) $210.00 favorable D) $210.00 unfavorable ```
[280 dlh - (1,200 × 0.25)] × $14 = $280 F
104
These questions refer to flexible-budget variance formulas with the following descriptions for the variables: A = Actual; B = Budgeted; P = Price; Q = Quantity. ``` The best label for the formula (AQ - BQ) BP is the: A) efficiency variance B) price variance C) total flexible-budget variance D) spending variance ```
A) efficiency variance
105
``` The best label for the formula (AP - BP) AQ is the: A) efficiency variance B) price variance C) total flexible-budget variance D) spending variance ```
B) price variance
106
``` The best label for the formula [(AP)(AQ) - (BP)(AQ)] is the: A) efficiency variance B) price variance C) total flexible-budget variance D) spending variance ```
B) price variance
107
``` The best label for the formula [(AP)(AQ) - (BP)(BQ)] is the: A) efficiency variance. B) price variance C) total flexible-budget variance D) spending variance ```
total flexible-budget variance
108
Berman's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Flexible Variances Budget Price Efficiency Material A $40,000 $1,000F $3,000U Material B 60,000 500U 1,500F Direct manufacturing 80,000 500U 2,500F labor The most likely explanation of the above variances for Material A is that: A) a lower price than expected was paid for Material A B) higher-quality raw materials were used than were planned C) the company used a higher-priced supplier D) Material A used during September was $2,000 less than expected
A) a lower price than expected was paid for Material A
109
Berman's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Flexible Variances Budget Price Efficiency Material A $40,000 $1,000F $3,000U Material B 60,000 500U 1,500F Direct manufacturing 80,000 500U 2,500F labor ``` The actual amount spent for Material B was: A) $58,000 B) $59,000 C) $60,000 D) $61,000 ```
B) $60,000 + $500 U - $1,500 F = $59,000
110
Berman's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Flexible Variances Budget Price Efficiency Material A $40,000 $1,000F $3,000U Material B 60,000 500U 1,500F Direct manufacturing 80,000 500U 2,500F labor ``` The actual amount spent for direct manufacturing labor was: A) $80,000 B) $83,000 C) $82,000 D) $78,000 ```
D) $80,000 + $500 U - $2,500 F = $78,000
111
Berman's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Flexible Variances Budget Price Efficiency Material A $40,000 $1,000F $3,000U Material B 60,000 500U 1,500F Direct manufacturing 80,000 500U 2,500F labor The most likely explanation of the above direct manufacturing labor variances is that: A) the average wage rate paid to employees was less than expected B) employees did not work as efficiently as expected to accomplish the job C) the company may have assigned more experienced employees this month than originally planned D) management may have a problem with budget slack and might be using lax standards for both labor wage rates and expected efficiency
C)
112
Hector's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Flexible Variances Budget Price - Efficiency Material A $20,000 $1,000U $1,200F Material B 30,000 500F 800U Material C 40,000 1,400U 1,000F ``` The actual amount spent for Material A was: A) $18,800 B) $20,200 C) $19,800 D) $21,000 ```
C) $20,000 + 1,000 U - $1,200 F = $19,800
113
Hector's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Flexible Variances Budget Price - Efficiency Material A $20,000 $1,000U $1,200F Material B 30,000 500F 800U Material C 40,000 1,400U 1,000F ``` The actual amount spent for Material B was: A) $29,700 B) $30,800 C) $30,500 D) $30,300 ```
D) $30,000 - $500 F + $800 U = $30,300
114
Hector's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Flexible Variances Budget Price - Efficiency Material A $20,000 $1,000U $1,200F Material B 30,000 500F 800U Material C 40,000 1,400U 1,000F ``` The explanation that lower-quality materials were purchased is most likely for: A) Material A B) Material B C) Material C D) both Material A and C ```
B) Material B
115
The presumed cause of a material price variance will determine how a company responds
TRUE
116
The price variance is the difference between the actual price and the budgeted price of the input, multiplied by the actual quantity of input.
TRUE
117
For any actual level of output, the efficiency variance is the difference between actual quantity of input used and the budgeted quantity of input allowed to produce actual output, multiplied by the budgeted price.
TRUE
118
The use of high-quality raw materials is likely to result in a favorable efficiency variance and an unfavorable price variance.
TRUE
119
The direct manufacturing labor price variance is likely to be unfavorable if lower-skilled workers are put on a job.
FALSE
120
Although computed separately, price variances and efficiency variances should NOT be analyzed separately from each other.
TRUE
121
A purchasing manager's performance is best evaluated using the: A) direct materials price variance B) direct materials flexible-budget variance C) direct manufacturing labor flexible-budget variance D) affect the manager's action has on total costs for the entire company
D) affect the manager's action has on total costs for the entire company
122
One of the primary reasons for using cost variances is: A) they diagnose the cause of a problem and what should be done to correct it B) for superiors to communicate expectations to lower-level employees C) to administer appropriate disciplinary action D) for financial control of operating activities and understanding why variances arise
D) for financial control of operating activities and understanding why variances arise
123
A favorable cost variance of significant magnitude: A) is the result of good planning B) if investigated, may lead to improved production methods C) indicates management does not need to be concerned about lax standards D) does not need to be investigated
B) if investigated, may lead to improved production methods
124
The variances that should be investigated by management include: A) only unfavorable variances B) only favorable variances C) all variances, both favorable and unfavorable D) both favorable and unfavorable variances considered significant in amount for the company
D) both favorable and unfavorable variances considered significant in amount for the company
125
Typically, managers have the LEAST control over: A) the direct material price variance B) the direct material efficiency variance C) machine maintenance D) the scheduling of production
A) the direct material price variance
126
If manufacturing machines are breaking down more than expected, this will contribute to a(n): A) favorable direct manufacturing labor price variance B) unfavorable direct manufacturing labor price variance C) favorable direct manufacturing labor efficiency variance D) unfavorable direct manufacturing labor efficiency variance
D) unfavorable direct manufacturing labor efficiency variance
127
A single variance: A) signals the cause of a problem B) should be evaluated in isolation from other variances C) may be the result of many different problems D) should be used for performance evaluation
C) may be the result of many different problems
128
Variance analysis should be used: A) to understand why variances arise B) as the sole source of information for performance evaluation C) to punish employees that do not meet standards D) to encourage employees to focus on meeting standards
A) to understand why variances arise
129
Variances should be investigated: A) when they are kept below a certain amount B) when there is a small variance for critical items such as product defects C) even though the cost of investigation exceeds the benefit D) when there is an in-control occurrence
B) when there is a small variance for critical items such as product defects
130
When continuous improvement budgeted costing is implemented, cost reductions can result from: A) price reductions B) reducing materials waste C) producing products faster and more efficiently D) All of these answers are correct.
D) All of these answers are correct.
131
Nonfinancial performance measures: A) are usually used in combination with financial measures for control purposes B) are used to evaluate overall cost efficiency C) allow managers to make informed tradeoffs D) are often the sole basis of a manager's performance evaluations
A) are usually used in combination with financial measures for control purposes
132
Unfavorable direct material price variances are: A) always credits B) always debits C) credited to the Materials Control account D) credited to the Accounts Payable Control account
B) always debits
133
Favorable direct manufacturing labor efficiency variances are: A) always credits B) always debits C) debited to the Work-in-Process Control account D) debited to the Wages Payable Control account
A) Always credits
134
``` From the perspective of control, the direct materials efficiency variance should be isolated at the time of: A) purchase B) use C) completion of the entire product D) sale of the product ```
B) use
135
Standard costing systems are a useful tool when using: A) just-in-time systems B) total quality management C) computer-integrated manufacturing systems D) All of these answers are correct.
D) All of these answers are correct.
136
``` Repeatedly identifying causes of variances, initiating corrective actions, and evaluating results of actions is an example of A) efficiency. B) effectiveness. C) continuous improvement. D) All of these answers are correct. ```
B) effectiveness.
137
``` The relative amount of inputs used to achieve a given output level is known as A) efficiency. B) effectiveness. C) continuous improvement. D) All of these answers are correct. ```
A) efficiency.
138
A favorable variance can be automatically interpreted as "good news."
FALSE
139
Variances often affect each other.
TRUE
140
If variance analysis is used for performance evaluation, managers are encouraged to meet targets using creativity and resourcefulness.
FALSE
141
When using variance for performance evaluation, managers often focus on effectiveness and efficiency as two of the common attributes used in comparing expected results with actual results.
TRUE
142
For critical items such as product defects, a small variance may prompt investigation.
TRUE
143
A particular variance generally signals one particular problem
FALSE
144
If budgets contain slack, cost variances will tend to be favorable.
TRUE
145
Continuous improvement budgeted costs target price reductions and efficiency improvements.
TRUE
146
Improvement opportunities are easier to identify when products have been on the market for a considerable period of time.
FALSE
147
It is best to rely totally on financial performance measures rather than using a combination of financial and nonfinancial performance measures.
FALSE
148
From the perspective of control, the direct materials price variance should be isolated at the time of purchase.
TRUE
149
The goal of variance analysis is for managers to understand why variances arise, to learn, and to improve future performance.
TRUE
150
Employees logging in to production floor terminals and other modern technologies greatly facilitate the use of a standard costing system.
TRUE
151
Possible operational causes of an unfavorable direct materials efficiency variance include poor design of products or processes.
TRUE
152
Effectiveness is the relative amount of inputs used to achieve a given output level.
FALSE
153
``` The process by which a company's products or services are measured relative to the best possible levels of performance is known as: A) efficiency B) benchmarking C) a standard costing system D) variance analysis ```
B) benchmarking
154
When benchmarking: A) the best levels of performance are usually found in companies that are within different industries B) finding appropriate benchmarks is a minor issue C) comparisons can highlight areas for better future cost management D) Both A and C are correct.
C) comparisons can highlight areas for better future cost management
155
``` Ensuring benchmark numbers are comparable can be difficult because differences can exist across companies with: A) overall company strategy B) depreciation methods C) inventory methods D) All of these answers are correct. ```
D) All of these answers are correct.
156
When benchmarking, management accountants are MOST valuable when they: A) present differences in the benchmarking data to management B) highlight differences in the benchmarking data to management C) provide insight into why costs or revenues differ across companies D) provide complex mathematical analysis
C) provide insight into why costs or revenues differ across companies
157
Benchmarking is the continuous process of measuring products, services, and activities against the best possible levels of performance, either inside or outside the organization.
TRUE
158
When benchmarking, the best levels of performance are typically found in companies that are totally different.
FALSE
159
One problem with benchmarking is ensuring that numbers are comparable.
TRUE
160
When benchmarking it is best when management accountants simply analyze the costs and allow management to provide the insight as to why the revenues and costs differ between companies.
FALSE