chapter 6 exam Flashcards

1
Q

project network?

A

tool used for planning, scheduling, and monitoring project progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what are four things the project network depicts?

A

project activities, logical sequences, interdependencies of activities, and times for activities to start/finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what is a framework for project information system used by project managers to make decisions concerning time, cost, and performance?

A

project networks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what are project networks developed from?

A

the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

activity?

A

element in project that consumes time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what is used to build the activities found in the project network?

A

work packages from the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

can an activity have one or more work packages?

A

yes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

two primary explanations for failure of integrating work packages and network?

A

diff groups used to define work packages and activities. the WBS is poorly constructed and not deliverable/output oriented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

how can managers guarantee continuity?

A

by having same people that defined the WBS and work packages define the network activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what are the primary inputs for developing project network plan?

A

work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

4 things about activities?

A

element of project that takes time. may or may not require resources. work or wait. represent one or more tasks from a work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

merge activity?

A

has more than one activity immediately preceding it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

parallel activities?

A

activities that can take place at the same time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

path?

A

sequence of connected, dependent activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

critical path?

A

paths with longest duration through the network, if an activity on this path is delayed the project is delayed!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

burst activity?

A

has more than one activity immediately following it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

3 things about activity-on-node?

A

one of two methods used to develop project networks. dominates all project plans. activities represented by nodes (boxes).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

3 relationships that must be established for activities included in project network?

A

predecessor, successor, concurrent/parallel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

what questions do completion of forward and backward processes answer? (2)

A

forward pass - earliest times, backward pass - latest times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

what does a forward pass - earliest times do?

A

starts with first project activity and traces each path through the network to last project activity, adding activity times while tracing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

what is the longest path that denotes project completion time for plan?

A

critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

equation of forward pass?

A

early start + duration = early finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

what does backward pass - latest times do?

A

starts with last project activity on network and traces backward subtracting activity times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

what does the late finish usually equal? (2 things)

A

early finish or existing project duration deadline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
equation of backward pass?
late finish - duration = late start
26
total slack?
tells the amount of time an activity can be delayed and not delay the entire project
27
what tells the amount of time an activity can exceed its early finish date without affecting the project end date or imposed completion date?
total slack
28
sensitivity?
likelihood the original critical path will change once project is initiated
29
characteristics of an INSENSITIVE network schedule?
has one critical path and noncritical activities that enjoy significant slack
30
characteristics of a SENSITIVE network schedule?
has more than one critical path and/or noncritical activities with very little slack
31
free slack (float)?
amount of time an activity can be delayed without delaying any immediately following (successor) activity
32
what is the amount of time an activity can exceed its early finish date without affecting early start date of any successor?
free slack (float)
33
2 things about free slack?
never negative, only activities that occur at the end of a chain of activities where there is a merge activity can have free slack
34
what does the early start and late finish tell project managers?
the time interval in which the activity should be completed
35
should project managers select the activities or combination of them that will cost least to shorten a project when it must be expedited to meet an earlier date??
yes
36
what sets the level of detail for activities?
how many tasks are used in each one
37
what does having too much info to manage result in?
increased overhead costs
38
how do managers of small projects minimize level of detail?
eliminate some preliminary steps for drawing networks
39
do we assume the network will materialize? does it usually?
yes, no
40
looping?
attempt by planner to return to an earlier activity
41
activity ID numbers should always be higher for activities following an activity in question... what does this do?
avoids illogical precedence relationships among activities
42
can an activity occur more than once? if so what should it have?
it should only occur once, if occurs again should have new name and ID number
43
how do most schemes number activities?
in ascending order, each succeeding activity has larger number so flow of project activities is toward project completion
44
what type of charts are most popular during planning, resource scheduling, and status reporting?
bar charts
45
what does requiring common start and finish events in form of nodes avoid?
dangler paths - gives impression that project doesn't have clear beginning or ending
46
is a project with more than one activity beginning when project is to start a dangler path?
yes
47
if project network ends with more than one activity, what are those unconnected paths?
dangler paths
48
what is the method for showing relationships among activities?
finish-to-start relationship
49
laddering?
when an activity has a long duration and will delay the start of an immediately following activity, it can be broken into segments
50
benefit of drawing network with laddering approach?
so following activity can begin sooner or not delay the work
51
lag?
minimum amount go time a dependent activity must be delayed to begin or end
52
benefit of using lags? (3)
greater flexibility in network construction, avoid delays of large activities broken down and reduce network detail, used to constrain start and finish of an activity
53
what are the most commonly used relationship extensions?
start to finish, finish to finish, and combinations of the two
54
finish to start relationship?
typical, generic network style used
55
start to start relationship?
alternative to segmenting activities
56
can start to start relationships be used with or without lags?
yes, with or without lags
57
what can changing finish to start relations to start to start relationship do?
find compression opportunities
58
concurrent engineering?
breaks activities into smaller segments so work can be done in parallel and project expedited
59
finish to finish relationship?
the finish of one activity depends on the finish of another
60
start to finish relationship?
situations in which the finish of an activity depends on the start of another
61
can more than one lag relationship be attached to an activity?
yes
62
hammock activities? (2)
span over a segment of a project, also used to aggregate sections of a project
63
what determines duration of hammock activities?
the time span between other activities