True or False. Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
True.
Which of the following is NOT an emerging practice for project scheduling?
A) On-demand scheduling
B) Iterative scheduling with a backlog
C) Agile-method scheduling
C) Agile-method scheduling
Which of the following is NOT considered as scale factors?
A) general population B) team size C) organizational complexity D) geographic distribution E) regulatory compliance
A) general population
Which of the following dependencies involve a precedence relationship between project activities and are generally inside the project team’s control?
A) External
B) Internal
C) Discretionary
D) Mandatory
B) Internal
Which of the following is NOT a consideration when estimating duration?
A) Number of resources B) Advances in technology C) Law of diminishing returns D) Agile method E) Motivation of staff
D) Agile method
Which definition best describes analogous estimating?
A) a technique for estimating duration or cost of an activity or a project using predictive modeling
B) a technique for estimating duration or cost of an activity or a project using historical data
C) a technique for estimating duration or cost of an activity or a project using iterative methods
D) a technique for estimating duration or cost of an activity or a project using project management methods
B) a technique for estimating duration or cost of an activity or a project using historical data
What is the formula for triangular distribution?
tE=(tO + tM + tP) / 3
When is triangular distribution used?
A) there is insufficient historical data
B) when information is available
C) when expert judgement is needed
A) there is insufficient historical data
Developing an acceptable project schedule is a/an ____ process.
A) strenuous
B) adaptive
C) common
D) iterative
D) iterative
Which best describes the definition of crashing?
A) used to shorten the schedule duration for the least incremental cost by adding resources
B) technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration
A) used to shorten the schedule duration for the least incremental cost by adding resources