Chapter 4 - Quiz Flashcards

1
Q

For materials procured externally, the MRP

controller has the choice between creating a planned order or a purchase requisition

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

MRP quantities are grouped together

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Process steps

A

Routing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Materials can be produced or procured

A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Produced internal, planned order never created

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

With MRP at
plant level, the system adds together stocks from all of the individual storage locations,
with the exception of individual customer stock, to determine total plant stock.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

a request or instruction from a purchasing organization to a
vendor or a plant to supply or provide a certain quantity of goods or services at or by a
certain point in time.

A

Purchase order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

MRP controlller is _______

A

Person

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Difference Between independent requirements and dependent requirements

A

Independent requirements are used for FInal assembly, Dependent requirements are used for BOM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

a complete, formally structured list of the components that make up a
product or assembly

A

BOM (Bill of Materials)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

in house production (planned orders) are converted to _________

A

production orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Central Role of MRP is to balance stocks

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

sales are planned in advance via a sales forecast. The
result is the independent requirement, that is, the requirement for the finished
product, tradable assemblies, trading goods and replacement parts. This result
triggers material requirements planning.

A

Demand Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

availability check for a material is

carried out by the system. This indicator also controls:

A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Planning for materials that greatly influence profits

A

Master Production BOM Scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Time required to obtain trading goods

A

Planned delivery time

17
Q

Time needed for complete production and procurement of a finish product

A

Total replenishment lead time

18
Q

Explosion of BOM creates

A

Planned orders for customer requirement only

19
Q

Planned orders for customer requirement only

A

Reorder point planning