Chapter 3 - Value-Driven Delivery Flashcards

1
Q

Which technique is used to calculate process cycle efficiency?

A

Value Stream Mapping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What’s the formula for calculating process cycle efficiency?

A

Total value-add time / Total cycle time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What’s the “Monopoly Money”?

A

A prioritization scheme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What’s the name of the prioritization scheme that classifies in “Must Have”, “Should Have”, “Could Have”, “Would like to have”?

A

MoSCoW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 4 priority categories of the Kano Analysis?

A

Exciters, Satisfiers, Dissatisfiers, Indifferent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the available prioritization schemes?

A

Simple schemes, MoSCoW, Monopoly Money, 100-Point Method, Kano Analysis, Requirements Prioritization Model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which factors are taken into account in the Requirements Prioritization Model?

A

Benefit, Penalty, Cost and risk of proposed feature

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which prioritization method doesn’t use ANY categories?

A

Relative Prioritization / Ranking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which technique is used to depict Product Roadmaps?

A

Story Maps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How to construct a Risk-Adjusted Backlog?

A

Assign business value to each feature and rate the Expected Monetary Value of each risk. Then, add risks to the Product Backlog

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Expected Monetary Value?

A

Risk Impact ($) x Probability (%)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the 2 principles of a “money for nothing and change for free” type contract?

A
  1. Customer can change as long as overall costs same

2. Early termination at a cost of % remaining contract value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the principles of a “Graduated Fixed Price Contract”?

A

Variable rate depending on finish time (early, on time, late)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the 4 types of Agile contracts?

A

DSDSM contract, Money for Nothing and Change for Free, Graduated Fixed Price Contract, Fixed Price Work Packages, Customized Contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Kanban board?

A

A board with 3 task columns: To Do, In Progress and Done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is WIP Limits?

A

A technique for reducing the WIP e.g. by limiting the space for WIP items on a Kanban board

17
Q

What is the aim of WIP Limits?

A

To optimize throughput of work (not resource utilization).

18
Q

What are the key benefits of Incremental Delivery?

A

Early ROI + identify defects early

19
Q

What is the objective of “Customer-Valued Prioritization”?

A

To ensure we’re working on the items that yield the highest value to the customer

20
Q

What does IKIWISI mean?

A

I’ll Know It When I See It. Meaning that requirements are often identified during demos

21
Q

Formula of SPI?

A

Completed Features / Planned Features

22
Q

Formula of CPI?

A

Earned Value (value of completed features to date) / Actual Costs

23
Q

What metrics are shown in Cumulative Flow Diagrams (CFD)?

A

Total work, in progress work, Completed Work

24
Q

What does Little’s Law say?

A

Cycle times (time to complete work) is proportional to the size of the WIP queue

25
Q

NEED TO REVIEW CONCEPT OF CFDs

A

NEED TO REVIEW CONCEPT OF CFDs

26
Q

What are Risk Burn Down Graphs?

A

stacked area graphs of cumulative project risk severity

27
Q

What are the main areas of PMI Code of Ethics?

A

Responsibility, Respect, Fairness, Honesty