Chapter 3 Calculating unit costs Flashcards

1
Q

1.1 Standard costing

A

A standard cost is the expected, or budgeted, cost per unit of output. A standard cost card is drawn up in advance of a period and shows the expected usage of resources and price of resources for each cost unit.
Standard costing aids more accurate budgeting and timetabling of production in advance of the period. At the end of the period, it is then useful to compare standard and actual costs incurred. This allows control actions to be taken by management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2.1 Inventory valuation

A

There are two methods for determining the value of inventory:
- Absorption costing: inventory is valued at full production cost (including both variable and fixed elements of production cost)
- Marginal costing: inventory is valued at variable production cost only
Neither method includes non-production costs in the inventory value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

3.1 Marginal costing

A

Marginal costing values a cost unit at prime cost-plus variable production overhead.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4.1 Absorption costing

A

Absorption costing values a cost unit at prime cost-plus variable production overheads plus an estimate of the fair share of fixed production overheads. This is the same as marginal cost plus an estimate of the fair share of fixed production overheads. Absorption costing is also called full costing.
There are 3 stages to assigning fixed production overheads to a cost unit under absorption costing:
- Allocate and apportion
- Reapportion
- Absorb

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

4.2 Allocate and apportion

A

There are two types of fixed production overhead: overheads that arise in a department and overheads that are factory wide. Allocation is the process of charging whole cost items directly to a cost centre (only appropriate when costs arise solely in one cost centre).
Apportionment is the process of sharing cost items between cost centres. Overheads are apportioned on a fair basis so that the charge to a specific centre will reflect, with reasonable accuracy, the benefit obtained by that centre from the cost incurred. Usually, a different fair basis is applicable for each overhead.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

4.3 Reapportion

A

Costs allocated and apportioned to service cost centres must be reapportioned to production cost centres on a fair basis. Production cost centres physically work on the cost unit. Service cost centres support the production activities but do not physically work on the cost unit. If there is more than one service centre for which costs need to be reapportioned, either:
- Firstly, reapportion service cost centre with the biggest costs, or
- Firstly, reapportion the service cost centre which gives the biggest proportion of its services to other service cost centres

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

4.4 Absorb

A

All production overheads, now only included in production cost centres, are then absorbed into cost units using a predetermined overhead absorption rate (OAR). OAR is budgeted overhead cost divided by budgeted level of activity.
Predetermined, or budgeted figures are used so that cost can be determined at the start of the period, so businesses can set sales prices. The level of activity chosen should reflect the characteristics of that cost centre and thereby provide a reasonably accurate estimate of overhead costs for cost units. This is a matter of judgement. Possible measures of activity are:
- Number of cost units
- Prime cost
- Direct labour cost
- Direct materials cost
- Labour hours
- Machine hours
Absorption based on number of cost units – this is effective if all cost units are identical in resources utilised in each cost centre.
Absorption based on prime cost –
Absorption based on direct labour cost –
Absorption based on an hourly rate – this can refer to machine hours or labour hours. A direct labour hour basis is most appropriate in a labour-intensive environment. A machine hour rate is most appropriate in cost centres where production is controlled or heavily dictated by machines.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

4.5 Blanket absorption rate

A

A blanket absorption rate uses the same rate for all cost units irrespective of the department in which they were produced. A blanket absorption rate is only appropriate if individual departmental OARs would be like an overall company OAR.
This method is not appropriate if there are a number of departments and different cost units do not spend an equal amount of time in each department. Blanket absorption rates are also called a single factory absorption rate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

5.1 Over and under absorption of overheads

A

The OAR is calculated at the start of the period based on budgeted figures. It is likely that actual overheads and actual levels of activity are different to what was budgeted. Therefore, overheads absorbed will be different to total actual overheads.
- Over absorption occurs if absorbed > actual
- Under absorption occurs if absorbed < actual
To calculate over or under absorption use the following steps:
- OAR = budgeted overhead cost / budgeted level of activity
- Actual overhead incurred
- Overhead absorbed = actual activity x OAR
- Actual overhead incurred less overhead absorbed = under/(over) absorbed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

6.1 Activity based costing – calculating product costs

A
  • identity a business’ major activities
  • identify the cost drivers – these are the factors causing activity costs to be incurred. These can be volume related or transaction related
  • collect the costs associated with each activity into cost pools
  • calculate an activity absorption rate and absorb overheads into cost units
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

7.1 Costing methods

A

Job costing is appropriate for specific one-off jobs of relatively short duration. Job cost includes prime cost and absorbed overheads.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

7.2 Contract costing

A

Contract costing is appropriate for specific one-off jobs of relatively long duration. Contract cost includes prime cost, allocated overheads, and absorbed overheads.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

7.3 Batch costing

A

Batch costing is appropriate for a group of identical cost units. Total batch cost includes prime costs and absorbed overheads. Unit cost is the total batch cost / number of units

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

7.4 Process costing

A

Process costing is appropriate if there is a continuous flow of operation which produces identical products. Each cost centre is usually one stage in a bigger production process. Total process cost includes prime costs and absorbed overheads. Unit cost is total process cost divided by number of units.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

7.5 Life cycle costing

A

Life cycle costing tracks and accumulates actual costs and revenues attributable to each product over its entire life cycle. The life cycle runs from research and development through to withdrawal from the market. Analysing the life cycle costs avoids decisions being made solely on initial costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

7.6 Target costing

A

Market research is conducted to estimate the price consumers would be willing to pay to allow the business to achieve the required market share. The required profit is deducted from this price to generate the target cost. The business determines if it can achieve this target price. If not, profit margins will be eroded, or the product will not be produced.

17
Q

8.1 Just in time

A

Just in time (JIT) is an approach to operations planning which aims for goods and services to be produced exactly when they are needed. Therefore, zero inventory is held, but the customer does not have to wait. This is desirable because holding inventory is expense (storage costs, insurance, risk of obsolescence). Operational requirements for the JIT system include high quality, speed, reliability, efficient production planning and reliable sales forecasting.