Chapter 2 - System Life Cycle Concepts, Models and Processes Flashcards
An IPO Diagram includes the following:
A) all inputs, process activities, and possible outputs
B) key inputs, process activities and resulting outputs
C) all inputs, predictable activities and required outputs
D) key inputs, process activities and possible outputs
B) key inputs, process activities and resulting outputs
The number of process groups identified by 15288 is (choose 1):
A) 3
B) 4
C) 5
D) 6
B) 4
Project direction, as found in the Controls box of the input-process-output (IPO) diagram, is defined as (choose 1):
A) a vector defining the success criteria for a project.
B) the organisation’s direction to a project to continue, redirect, or terminate.
C) a measurement against assessment criteria that determines if a project is moving forward or stalled.
D) permission to continue forward at the conclusion of a phase-gate or stage-gate review.
B)
The 5 Organisational Project-Enabling Processes identified by ISO/IEC 15288 include (choose 3):
A) Technical Processes
B) Infrastructure Management
C) Agreement Processes
D) Human Resource Management
E) Quality Management
B, D, E
How many items are called out in the Controls box (choose 1):
A) 5
B) 4
C) 7
D) 6
C - 7
The 5 Organizational Project-Enabling Processes identified by ISO/IEC 15288 include (choose 2):
A) Portfolio Management
B) Agreement Processes
C) Life Cycle Model Management
D) Technical Processes
A, C
Select the Controls from the list below (choose 7):
A) Applicable laws and regulations
B) Organisation policies
C) Project controls
D) Organisation infrastructure
E) Project constraints
F) Standards
G) Agreements
H) Project infrastructure
I) Project direction
J) Knowledge management
K) Project control requests
A, F, G, B, I, E, K
The 4 process groups from ISO/IEC 15288 that support systems engineering include (choose 2):
A) Organisational project-enabling Processes
B) Work breakdown processes
C) Technical Processes
D) Project Initiation
A C
The input-process-output diagrams represent (choose 1):
A) the best way to perform systems engineering processes.
B) the fact that systems engineering must produce the documents listed in the output
C) one way the systems engineering processes can be performed
C
The 8 Technical Management Processes include (choose 4):
A) Project Planning
B) Project Assessment and Control
C) Requirements Analysis
D) Configuration Management
E) Implementation
F) Stakeholder Requirements Definition
G) Information Management
A B D G
What are the typical life cycle stages?
A) Concept, Development, Production, Utilisation, Support, Retirement
B) Concept, Development, Production, Operation, Support, Retirement
C) Concept, Development, Constuction, Operation, Support, Retirement
D) Development, Prodcution, Operation, Support, Renewal
A
INCOSE handbook pg27
What are the typical goals of decision gates? (Choose three)
A) The project deliverables satisfy the business case.
B) Decide what needs to be done in the next stage.
C) Unresolved issues that need to be addressed in that state are addressed.
D) The project deliverbales satisfy the client requirements.
E) Increase in systems maturity is within the defined threshold.
F) Identify risks through review of the design.
A, C, E
INCOSE handbook pg29
What is a technical review in accordance with ISO/IEC 24758 / IEEE 15288.2?
A) A review of notes, documents, and other data that forms the basis for a scientific conclusion.
B) Activities to assess the quality of the documentation produced compared to the client ask.
C) A detailed review of processes, product definition information, documented verification of compliance with requirements, and an inspection of products to confirm that products have achieved their required attributes or conform to released product configuration definition information.
D) A series of systems engineering activities conducted at logical transition points in a system life cycle, by which the progress of a project is assessed relative to its technical requirements using a mutually agreed upon set of criteria.
D
INCOSE handbook pg31
What is an audit in accordance with ISO/IEC 24758 / IEEE 15288.2?
A) A detailed review of processes, product definition information, documented verification of compliance with requirements, and an inspection of products to confirm that products have achieved their required attributes or conform to released product configuration definition information.
B) A series of systems engineering activities conducted at logical transition points in a system life cycle, by which the progress of a project is assessed relative to its technical requirements using a mutually agreed upon set of criteria.
C) Essential activities to ensure that the system meets the requirements, standards, and expectations of the stakeholders throughout its lifecycle.
D) Verificaiton that the requirements have been meet at each stage.
A
INCOSE handbook pg31
What are the 3 baselines? (Choose 3)
A) Functional
B) Allocated
C) Standards
D) Product
E) Requirements
A, B, D
INCOSE handbook pg32