Chapter 2 Management Flashcards

1
Q

This financial statement documents what a company owns and owes at a specific point in time by providing detailed information about assets, liabilities, and Shareholder’s Equity:

A

Balance Sheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A schedule that outlines what tasks will take place, when they are scheduled to begin and end, and what resources are needed to accomplish them is typically created during the Project Planning Phase and is called a ___________.

A

Resource-Loaded Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Asking the question “What can we learn and immediately apply?” is an example of which knowledge management tool applied to risk management?

A

Learning During

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The underlying foundation of the Earned Value Management System is:

A

The relationship between work completed, and the cost of doing the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The following is NOT true regarding a “Funds Thru” date:

A

The Antideficiency Act allows the contracting officer to instruct contractors to work when funds are no longer available

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Risk management is:

A

The ability to efficiently and cost-effectively mitigate problems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Categorizing purchases according to dollar value is done in:

A

Pareto Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Incremental funding requires all of the following EXCEPT:

A

Instructions from the contracting officer to work when funds are not available

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When tracking costs following the award of a contract, what is latency?

A

The delay between when a cost is incurred and when it appears in the accounting system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

An Estimate at Completion may be obtained by:

A

Adding the cost of work remaining to the cost of work accomplished to date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following best describes the project manager’s role in financial management?

A

Verifying the work completed that needs to be invoiced for.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The ORM 6-step model includes:

A

Identifying, analyzing, and prioritizing risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

__________is usually responsible for monitoring project performance.

A

Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

FedBizOpps is:

A

A web portal that allows vendors to review Federal business opportunities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which best describes the relationship between the project scope and the contract scope?

A

There is often direct correlation between the two, but the project scope may also be broader

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which of the following best describes project management?

A

The planning, organizing, directing and controlling of all aspects of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which of the following four levels of planning is defined as a focus on short-term (e.g., one- to two-year) goals that involves evaluating economic and environmental issues such as competition (for sellers), and requirements planning (for buyers)?

A

Tactical Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Portfolio Management is most focused on which of the following?

A

Business goal alignment, value alignment and program selection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A firm fixed-price contract results in __________ buyer risk and __________seller risk.

A

Low; High

20
Q

As the first step in the financial management process, this individual is responsible for estimating how much funding the contract will require over time, and for marrying those costs with the schedule to identify when expenses will occur:

A

The program manager or contract manager.

21
Q

This costing method uses a two-step process: 1 - assign the resource costs of each activity, and 2 - assign activity costs to the output:

A

Activity-Based Costing System.

22
Q

The process for creating the Resource-Loaded Schedule begins with:

A

…extracting a Work Breakdown Structure from the Statement of Work.

23
Q

Analysis to measure the company’s ability to meet current and long-term obligations would use the following ratio:

A

Solvency Ratio

24
Q

Categorizing suppliers into Transactional, Collaborative, and Strategic Alliance categories represents

A

Supplier Relationship Model

25
Q

What is the most likely direct cause of a project dispute related to failed delivery?

A

Quality issues with deliverables and performance due to vague definitions and lack of acceptance criteria.

26
Q

Which of the following focuses on multiple projects?

A

Program

27
Q

The following are intangible assets because their value comes from a legal claim or additional earning power:

A

Patents, Trademarks.

28
Q

When suppliers are being certified or pre-qualified they have been:

A

Screened

29
Q

Which of the following is not a responsibility of Supply Chain Management?

A

Achieve low cost contracts

30
Q

Supply Chain Management:

A

Involves managing the activities to produce and deliver a product or service from suppliers to the end user customer.

31
Q

A Basis of Estimate is prepared for each work package (the lowest level of the Work Breakdown Structure). It is:

A

…a description of how the work will be done, by whom, and the effort or materials required.

32
Q

To obtain Federal Government information formerly located in the Central Contractor Registration, Online Representations and Certifications, and the Excluded Parties List System, you would navigate to the following website:

A

System for Award Management.

33
Q

A purchase order has the following two step process that sometimes causes accounting data entry delays:

A

1- A commitment is made when the order is approved and funds are deducted, similar to an accrued expense.
2 - The value of the commitment is reduced as the supplier invoices for goods/services.

34
Q

An RFQ placed in a competitive environment described as a “Monopsony” will result in what type of pricing outcome?

A

Quotes from many sellers at low prices.

35
Q

Which is NOT true of the accounting codes that are created following the award of a contract?

A

They are standardized for all Work Breakdown Structures to allow project comparisons.

36
Q

Put the following in order from broadest to narrowest.

A

Portfolio, Program, Project

37
Q

A contracting officer is preparing to award a contract for Advisory & Assistance Services to a small business. The contracting officer wants to make sure the small business is financially capable of performing and managing the contract. The Contracting Officer requests the contractors Balance Sheet from the most recently completed fiscal year. What is an example of another item the Contracting Officer might consider requesting to make a more informed decision?

A

Cash flow statement

38
Q

When a party to a contract fails to enforce a term of the contract, we may have an example of:

A

Behavior of the Parties

39
Q

What actions would an operations manager take to improve administrative lead time (also known as procurement lead time)?

A

Measure how long it takes to award contracts, and determine whether the requesting department has provided full and accurate information to the acquisition office.

40
Q

Which of the following could mitigate a performance risk?

A

Create an effective ethics and compliance internal control system

41
Q

The act of moving goods out of one’s internal organization to another organization due to loss of value is:

A

Disposition

42
Q

Regardless of an organization’s contracting activity size and purpose, the following four key functions of management are essential:

A

Planning, Organizing, Directing, Controlling

43
Q

The statement “The probability of a delivery failure is only 10%, but the impact on our mission would be catastrophic” is an example of _________________.

A

Components of risk

44
Q

Providing information to satisfy Federal contract reporting requires the comparison of current accounting data and a time-phased program budget. One standard approach is the use of:

A

An “S” Curve that represents how activities ramp up and tail off during a project.

45
Q

The four essential elements of any marketing program consist of:

A

Products/Services, Price, Promotion, Place

46
Q

The SCOR model:

A

Reflects the basic functions of a supply chain operation

47
Q

Burn Rate funding analysis “spreads” the contract value over time in a level-loading scheme. This technique:

A

….fails to consider project phases, or the potential for programs to “ramp-up” activity at the beginning, and “tail off” at the end of a project.