Chapter 15: Steel Erection Flashcards
On multi-story structures, perimeter safety cables shall be installed at the final interior and exterior perimeters of the floors as soon as the ______ has/have been installed.
A. Concrete
B. Metal decking
C. Planking
D. Stairways
B. Metal decking
In this OSHA 1926 Subpart, the general contractor is referred to as the ______ contractor.
A. Controlling
B. Coordination
C. Prime
D. Sub-
A. Controlling
In addition to other terms, each connector shall have completed steel erection ______ training.
A. Climber
B. Connector
C. Hoisting
D. Welding
B. Connector
What is the OSHA abbreviation for a steel erection area where certain work may take place without the use of a guardrail system?
A. ADL
B. BDX
C. CDZ
D. DCD
C. CDZ
Covers for roof and floor openings must support without failing ______ times the weight of the employees, equipment, and materials that may be imposed on the cover at any one time.
A. One and a half
B. Two
C. Three
D. Four or More
B. Two
______ are preplanned to ensure that no employee is generally required to work directly below a suspended load.
A. Christmas treeing loads
B. Location of slings
C. Quantity of tie-offs
D. Routes
D. Routes
Cranes used in steel erection shall be inspected at least ______
A. Before each work day
B. Before each work shift
C. Daily
D. Weekly
B. Before each work shift
In addition to other items, each connector shall be protected from fall hazards of more than two stories or ______ above a lower level, whichever is less.
A. 15’
B. 20’
C. 25’
D. 30’
D. 30’