Chapter 15 Flashcards
The purpose of a review of a plan is to:
A) Improve work efficiency
B) Reduce project time and costs
C) Improve work quality
D) Improve safety
E) All of these are correct
E
Required records are kept to comply with the:
- Provincial Boilers and Pressure Vessels Act and Regulations
- Provincial Workers Compensation Board
- ASME codes
- Insurance companies
A) 1, 2
B) 2, 4
C) 1, 2, 3
D) 2, 3, 4
E) 1, 2, 4
E
Operations records are kept to a minimum and are not a legal requirement.
A) True
B) False
B
In a preventive maintenance system, mechanical work means:
- Inspecting
- Adjusting
- Preparing work orders
- Parts inventory control
- Lubricating
A) 2, 4, 5
B) 1, 2, 3
C) 2, 3, 4
D) 3, 4, 5
E) 1, 2, 5
E
Requirements for the Provincial Boiler and Pressure Vessels Act and Regulations as far as record keeping goes, the following must be adhered to:
A) A logbook is to be kept in all plants
B) The logbook must be available to the inspector and is a legal document
C) Logbook must include testing of safety valves
D) Logbook must be signed and dated by operators
E) All of these are correct
E
Preventive maintenance is the systematic inspection, cleaning, lubrication, and servicing of equipment.
A) True
B) False
A
The logbook is:
A) Used to record absenteeism
B) A legal document
C) Not to be used for recording operating temperatures and pressures
D) Not to be used as evidence in inquiries
E) Not required by the Boiler Inspector
B
The objective of the critical path is to identify:
A) The activities with the most milestones
B) The longest activity
C) Which set of activities results in the longest duration
D) The most expensive repairs
E) The most dangerous maintenance activities
C
The actual work phase of a plan is to make sure that the work is done, as per schedule.
A) True
B) False
A
Preventative maintenance can be separated into two classifications:
- Actual work
- Paper work
- Mechanical work
- Maintenance work
A) 1, 2
B) 3, 4
C) 2, 3
D) 1, 4
E) 2, 4
C