Chapter 14 – ‘The Production Cycle’ Flashcards

1
Q
  1. Most costs are locked in at which stage in the production cycle? 
    a. product design
    b. production planning  
    c. production operations  
    d. cost accounting
A

a.
product design (Correct. Decisions made during product design determine
the majority of costs.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. Which of the following is an advantage of bar-coding over RFID?
    a. speed  
    b. accuracy
    c. Cost
    d. safety
A

c. Cost (Correct. Bar-coding is currently less expensive than RFID)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
3. Which document lists the components needed to manufacture a specific
product?
A. operations list   
b. master production schedule 
c. bill of materials 
d. production order
A

c. bill of materials (Correct. The bill of materials lists the components of a
finished product.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. Which document captures information about labor used in production? 
    a. move ticket
    b. job-time ticket
    c. operations list  
    d. bill of materials
A

b. job-time ticket (Correct. The job-time ticket records time spent on each
activity. ) 

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. An increase in which component of quality costs is most likely to result
    in a decrease in the other three components?
    a. prevention costs
    b. inspection costs
    c. internal failure costs
    d. external failure costs
A

a. prevention costs (Correct. Increases in prevention costs often reduce the
time and cost of inspecting products, as well as the proportion of defective
products.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. Activity-based costing can be used to refine which of the following?
    a. job-order costing
    b. process costing
    c. both job-order and process costing
    d. neither job-order nor process costing
A

c. both job-order and process costing (Correct. Activity-based costing can be
used with either job-order or process costing.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Which system is most likely to be used by a company that massproduces
    large batches of standard items in anticipation of customer
    demand?
    a. MRP-II
    b. lean manufacturing
    c. activity-based costing
    d. throughput
A

a. MRP-II (Correct. MRP-II is a push form of manufacturing that is
appropriate for mass production of standardized items for which demand is
predictable.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
8. The development of an MPS would be most effective in preventing
which of the following threats?
a. recording and posting errors 
b. loss of inventory
c. production of poor-quality goods 
d. excess production
A

d. excess production (Correct. An MPS schedules production to satisfy demand
and, therefore, reduces the chance of overproduction.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Which control procedure is probably least effective in reducing the
    threat of inventory loss?
    a. limiting physical access to inventory
    b. documenting all transfers of inventory within the company
    c. regular materials usage reports that highlight variances from standards
    d. periodically counting inventory and investigating any discrepancies between
    those counts and recorded amounts
A

c. regular materials usage reports that highlight variances from standards
(Correct. Although variances could indicate theft, they are more likely to
reflect changes in efficiency.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
10. What is the number of good units produced in a given period of time
called?
a. productive capacity 
b. productive processing time 
c. yield 
d. throughput
A

d. throughput (Correct. Throughput is the measure of the number of good units
produced per unit of time.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly