Chapter 13 Flashcards

1
Q

Material Requirements Planning (MRP)

A

activity that determines the ordering of dependent-demand items (components of assembled products).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

MRP II

A

second generation MRP, adds broader scope by linking sales and operations planning, MPS, MRP, CRP, and detailed scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Capacity Requirements Planning (CRP)

A

uses the MRP shop order releases and operations times and routings to determine the capacity requirements from each work centre.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Dependent Demand

A

D that depends on the production schedule for the finished goods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 3 MRP Inputs

A
  • Master Production Schedule
  • BOM
  • Inventory Records
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Low-Level Coding

A

restructuring the BOM so that multiple occurrences of the same component all coincide with lowest level at which said component occurs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

MRP Processing

A

“explodes” end item requirements specified by the master schedule into time-phased requirements for assemblies, parts, and raw materials using the BOM offset by lead times. Figure 13-8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Gross Requirement

A

Total expected demand for an item or raw material in a time period (w/o regard to amount on hand).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Scheduled Receipt

A

open order scheduled to arrive from a vendor or shop floor in the beginning of a period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Projected on-hand

A

amount of inventory that us expected to be on hand at beginning of time period. scheduled receipt + any ending inventory expected from last period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Net requirement

A

actual amount needed in a time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Planned-order receipt

A

quantity planned to be received in the beginning of a period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Planned-order release

A

Quantity planned to be released in the beginning of a period (planned-order receipt offset by lead time).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Pegging

A

MRP processing in reverse - identifying immediate parent items that have generated a given set of requirements for an item such as D

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

2 systems used to update MRP records

A
  • Regenerative
  • Net-change
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Regenerative System

A

compiles all changes that occur within the time interval and periodically updates the system.

14
Q

Net-Change System

A

production plan is modified to reflect changes as they occur

if some defective purchased parts had to be returned to a vendor, manager can enter this info into the system right when it becomes known.

only changes are exploded through the system, the entire plan is not regenerated.

15
Q

Regenerative vs Net-Change

A

Regenerative is better for stable situations. It is disadvantageous, especially in situations where changes are frequent, because there is a time lag between receiving info and updating the system.

16
Q

MRP System Nervousness

A

a small change in requirement of an item at the top of the product structure tree can have large effects on items down the tree.

17
Q

Back-flushing

A

exploding an end item’s BOM periodically to determine the quantities of the components that must have been used to make the quantity of the item

18
Q

Primary Reports

A
  1. Planned-order schedules
  2. Order releases
  3. Changes to scheduled receipts
19
Q

Secondary Reports

A
  1. Performance-control reports
  2. Planning reports
  3. Exceptions reports
20
Q

Planning Bill

A

when end products only have minor differences (such as colour), they can be combined into an artificial product to simplify planning process

21
Q

Modular Bill

A

used to reduce the # of BOMs when a product consists many modules, each with a few options.

22
Q

Phantom Bill

A

for items that are usually not kept in inventory.

E.g., suppose that pedals of a specific bike are assembled outside the bike assembly line. A phantom bill is created for the components needed to assemble a pedal.

23
Q

Distribution Resource Planning (DRP)

A

planning method that determines time-phased replenishment schedules between a manufacturer’s facility and distribution centres (DCs), or between a DC and retail stores.

24
Q

Capacity Requirements Planning (CRP)

A

process of determining detailed capacity requirements of MRP

calculation on page 511

25
Q

Manufacturing Resource Planning (MRP II)

A

MRP expanded into broader system for planning and scheduling.
sales and operations planning - MPS - MRP - CRP

26
Q

Load Reports

A

Department or work centre reports that compare known and expected future capacity requirements with capacity availability.