Chapter 12 Project Administration Vocab Quiz Flashcards

1
Q

Change Order

A

Used when there is agreement among owner, architect, and contractor about the amount of the cost adjustment and the contract time associated with a change to job.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

RFI

A

Formal request for information to clarify details or correct errors or omissions on drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Notice to Proceed

A

Letter that is a legal document that (a) accepts the bid proposal and (b) establishes start/completion dates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Application and Certificate for Payment

A

Formal document used by the contractor to get paid for work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Progress Photographs

A

Visual recording including pictures that show specific events at the job site or work progress over time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Meeting Minutes

A

Notes from weekly meetings. Includes issues discussed, action dates, and persons responsible.
Diaries

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Daily Report

A

Document kept by the superintendent that records the day-to-day activities and conditions on the job site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Shop Drawings

A

Detailed and precise drawings that translate the intent of the design documents into a buildable system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Monthly Report

A

Reports sent monthly to the owner’s organization and the project team that shows job progress to date, cash flow actuals and projected, an updated schedule with critical path, change requests, and so on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly