Chapter 11 MC Flashcards
Generally speaking, the lowest level in the WBS is referred to as:
The work package
Scope creep is generally the result of:
A poorly defined SOW
Which of the following is not a benefit of having a highly detailed WBS?
- Lower status reporting costs
- Less likely that anything will be omitted
- Better estimating
- better activity planning
Lower status reporting costs
All work packages in a project must be at the same level of the WBS.
FALSE
Generally Speaking, Work packages are assigned to one functional unit.
TRUE
Which of the following documents is not defined in the text as one of the four critical documents for preliminary planning?
- SOW
- WBS
- Specifications
- Network Diagrams
Network Diagrams
If the customer’s SOW contains words such as nearly or approximately, then:
The customer uses his discretion in determining the meaning.
Project Managers often rewrite the customer’s SOW into a document that the project team can easily understand. The document is called?
The scope statement.
Which of the following would be the first item to be discussed in the initial kickoff meeting for a project? Understanding of the: -Requirements - Plan - Schedule - Budget
Understanding of the requirements
Which of the following is often overlooked when planning and budgeting a project?
- Customer’s Milestones
- Cost and size of contractual documentation
- Number of meetings with the customer
- Timing of the deliverables
Cost and size of contractual documentation
Which of the following is normally not addressed in a change control board meeting to approve a scope change?
- Cost of the change
- Which functional unit will perform the change
- impact on the schedule
- Value-added opportunity for the client
Which functional unit will perform the change
Which of the following is usually not validated by using the WBS?
- schedule
- risks
- quality of the deliverable
- budget
The quality of the deliverables
A PM desires a WBS that goes through six levels of detail. Level 3 through level 6 would most likely be prepared by the:
subject matter experts
Plans such as the cost plan, schedule plan and quality plan are referred to as:
Subsidiary Plans
Which of the following is usually preferred for the placement of the project manager with regard to the WBS? The PM’s salary should be:
There should be only one WBS element covering the PM’s salary