Chapter 10/11 Direct material/labour variances and overhead variances Flashcards
Direct material price variance formula
Purchased QTY X (Actual price - Standard price)
Direct material price variance formula
PQ x (AP - SP)
Direct material Quantity variance formula
Standard price x (Actual Qty - standard Qty)
Direct material Quantity variance formula
SP x (AQ - SQ)
Direct Labour (DL) Rate Variance
Actual hours x (actual rate - standard rate)
Direct Labour (DL) Rate Variance
AH x (AR - SR
Direct Labour (DL) Efficiency variance
standard rate x (Actual hours - Standard hours)
Direct Labour (DL) Efficiency variance
SR x (AH - SH)
CHAPTER 11
CHAPTER 11
Variable overhead spending variance
actual variable overhead - (AH x SVR)
Variable overhead efficiency variance
SVR x (AH - SH)
Fixed overhead budget variance
Actual fixed overhead - Budget fixed overhead
Fixed overhead volume variance
Budgeted fixed overhead - Applied fixed overhead
APPLIED FIXED OVERHEAD
actual units produced x fixed hours x fixed price