Name all quantity of si system with their unit
length- m
mass- kg
time-s
temperature- k
electric current- ampere
amount of substance- mole
luminous intensity- ((CANDELA)))))
Shallow, thin and surface work like plastering are expressed in
m2
mass, voluminous and thick work like earthwork, cement concrete, masonry are expressed in
m3
all earthwork E/W are expressed in
m3
surface dekhni bittikai
m2
sand filling
m3
brickwork b/w in foundation, superstrucuture
m3
plastering
m2
pcc in foundation
plum concrete pcc
lime concrete pcc
m3
50 mm thick pcc
m2( dimension deyxa so m2)
rcc work (beam, slab, lintel )
m3
dpc
m2
expansion and contraction joint
running metre (rm)
wood work for door and window
m3
partition dekhni bittikai
m2
form work
m2
steel reincforcement for rcc work
kg or MT (METRIC TON)
WIRE fencing
running metre (rm)
GI sheet
AC sheet
m2
since they are thin so m2
painting
m2
since they are thin so m2
white washing
cement washing
varnishing
m2
french polishing
varnish polishing
m2
flooring
,2
plaster of paris pop
m2