Change Management Flashcards
As covered in RICS Black Book 'Change control and management'
What is change management?
Management of skills, tools and techniques that enable change to be carried out effectively at both pre- and post-contract stages
What is change control?
The process or processes that can lead to the alteration of the timescale, the cost or scope of the project
Do all changes require instruction?
Some require instructions, but not all.
PS: Not all instructions are variations, as they may not affect cost or duration
What constitutes a change? (JCT D&B)
Under Clause 5.1:
A change is any alteration to the works, materials and goods, removal of works executed, or a change to the obligations and restrictions imposed in the Employer’s Requirements
What is the RICS process for managing change?
- Identify the reason(s) for change
- Investigate the impact of items such as costs, timescales and locations
- Strive to mitigate risks and maximise opportunities in relation to the overall objectives of the project
- Review and accept or reject the change.
Who can initiate a change?
- Employer - altering the scope, or increasing the volume of an item
- Contractor - if changes to contractual requirements are necessary, or if a submission could benefit parties through reduced timescale, durable product, or lower cost
Who is authorised to make changes to the contract? (JCT D&B)
Employer’s Agent
Under Article 3:
‘the Employer’s Agent shall have full authority to receive and issue applications, consents, INSTRUCTIONS, notices, requests or statements and otherwise to act for the Employer under any of the conditions’
What are the types of and reasons for a change?
- Requests - made by an employer or contractor.
- Value Engineering
- A Relevant Event - JCT
- Revisions to statutory requirements and regulations
- Agreed tender assumptions prove to be incorrect
- Unforeseen ground conditions are encountered
- Specified items are unavailable in the programmed timescale
- Additional works are required
- Discrepancies in or between contract documents
- Non projects factors:
○ Change in employer’s business needs
○ Changing market conditions
○ Changes in planning regulation or law
○ Changes in technology
When can the change control procedure be initiated in the pre-contract phase?
- towards the end of concept design, if the project is tendered at this stage as design and build contracts are
- at the end of the concept design stage, when the project brief might be frozen; that is, when the design is fixed
- when the detailed design, technical design and specification are finalised
- during the tender stage, when documentation needs amending or additional material needs to be added to reflect changes identified by the tendering process.
When can the change control procedure be initiated in the post-contract phase?
- when the contractor has been appointed and any further changes may qualify as a change or variation
- when the employer instructs the expenditure of a prime cost or provisional sum
- under JCT Design and Build contracts, when the contractor proposes and makes an agreed change that is within its scope.
What is the definition for change under each form of contract suite?
JCT - Variations
FIDIC - Variations
NEC - Compensation Events
What is a key difference between change under JCT and NEC forms of contract?
- JCT split time and cost into separate elements
- NEC deals with time and cost together
Who carries the risk for change?
Employer - under JCT Standard Form Contract - Example: Requested change from stainless steel to brass ironmongery.
Contractor - under JCT D&B or contract with Contractor Design Portion (CDP) - Example: Rectification of poor quality work
How do you manage risk?
Risk Register - Risks ranked according to priority, which is discussed at regular intervals.
This should contain:
- the name of the risk and associated probabilities
- a planned response for managing each risk
- provision for monitoring and controlling the risk so that it is reassessed and re-evaluated
- provision for additional identification of risks throughout the project.
What is risk allowance?
NRM 1 defines risk allowance as an amount set aside as a precaution against uncertain outcomes