Ch 9 - Cost Control Flashcards
What are the three variables in Earned Value Measurement (EVM)?
- PV: planned value
- AC: actual cost
- EV: estimated value
What is planned value (PV)?
the approved budget assigned to the work to be completed during a given time period
What is actual cost (AC)?
money that’s actually been expended during the given time period for completed work
What is estimated value (EV)?
value of work completed to date compared to the budget
How is EV (estimated value) figured?
The percentage of work completed x the budget amount for that item
Ex: 25% completed and budget is $1000 = $250
What is the most common EVM used?
cost variance
What is the formula for cost variance?
CV = EV - AC
What does cost variance (CV) analyze?
How actual costs compare to the budgeted amount. Positive number = below budget, negative number = over budget
What does schedule variance (SV) analyze?
compares an activity’s progress to date to the estimated progress, displayed in cost..
Is project ahead, on time or behind schedule for the planned period
What is the formula for SV (schedule variance)
SV = EV - PV
*Negative number = behind schedule
Positive number = ahead of schedule
CV (cost variance) and SV (schedule variance) are what type of indicators?
efficiency indicators used to predict future project performance
What is the cost performance index (CPI)?
measure value of work completed at the measurement date against the actual cost
What is CPI (cost performance index) the most critical of all EVM according to PMBOK guide?
tells you the cost efficiency for the work completed to date or at the completion of the project .
CPI less than 1 = spending more than anticipated for work completed at measurement date
CPI greater than 1 = spending less than anticipated
Formula for Cost performance index (CPI)
CPI = EV / AC
What does the schedule performance index (SPI) measure?
measures the progress to date against the progress that was planned