Ch 9 - Cost Control Flashcards

1
Q

What are the three variables in Earned Value Measurement (EVM)?

A
  1. PV: planned value
  2. AC: actual cost
  3. EV: estimated value
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is planned value (PV)?

A

the approved budget assigned to the work to be completed during a given time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is actual cost (AC)?

A

money that’s actually been expended during the given time period for completed work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is estimated value (EV)?

A

value of work completed to date compared to the budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How is EV (estimated value) figured?

A

The percentage of work completed x the budget amount for that item
Ex: 25% completed and budget is $1000 = $250

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the most common EVM used?

A

cost variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the formula for cost variance?

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What does cost variance (CV) analyze?

A

How actual costs compare to the budgeted amount. Positive number = below budget, negative number = over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does schedule variance (SV) analyze?

A

compares an activity’s progress to date to the estimated progress, displayed in cost..
Is project ahead, on time or behind schedule for the planned period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the formula for SV (schedule variance)

A

SV = EV - PV
*Negative number = behind schedule
Positive number = ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

CV (cost variance) and SV (schedule variance) are what type of indicators?

A

efficiency indicators used to predict future project performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the cost performance index (CPI)?

A

measure value of work completed at the measurement date against the actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is CPI (cost performance index) the most critical of all EVM according to PMBOK guide?

A

tells you the cost efficiency for the work completed to date or at the completion of the project .
CPI less than 1 = spending more than anticipated for work completed at measurement date
CPI greater than 1 = spending less than anticipated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Formula for Cost performance index (CPI)

A

CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does the schedule performance index (SPI) measure?

A

measures the progress to date against the progress that was planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How should the SPI (schedule performance index) formula be used

A

in conjunction with an analysis of the critical path to determine if the project will finish ahead of time or behind schedule

17
Q

How are results for SPI (schedule performance index) interpreted?

A

result greater than one means project is progressing ahead of schedule.
result less than one means project is behind schedule

18
Q

What is the formula for SPI (schedule performance index)

A

SPI = EV/PV

19
Q

What does the Estimate at Completion (EAC) analysis indicate?

A

forecast of the total cost of the project based on both current project performance and remaining work

20
Q

What is budget at completion (BAC)?

A

total amount of budget for a work package, control account, schedule activity, or the project

21
Q

What is estimate to complete (ETC)?

A

cost estimate for remaining project work. Typically provided by team members actually working on project activities

22
Q

What is the EAC formula?

A

EAC = AC + ETC

23
Q

What would a comparison of BAC (budget at completion) and ETC (estimate to complete) tell you?

A

current estimate of any deviation from budgeted amount

24
Q

What is To-Complete Performance Index (TCPI)?

A

the project performance level remaining work must achieve in order to meet the stated financial or scheduled goals.

25
Q

What is the formula for TCPI (To-Complete Performance Index)?

A

TCPI = (BAC - EV) / (BAC - AC)

26
Q

How are TCPI results be interpreted

A

result of 1.0 = keep doing what you’re doing, On schedule/budget
>1 = ahead of schedule/budget, do not need to perform as efficiently
<1 = behind schedule/budget, need to perform more efficiently to meet BAC goal

27
Q

What is variance analysis?

A

comparison of planned project results to actual project results

28
Q

What does variance analysis look at when used in the cost control process?

A

looks at difference between cost control baseline and actual performance, with VAC (variance at completion) frequently being used

29
Q

What does the variance at completion (VAC) measure?

A

the difference between budget at completion and estimate at completion

30
Q

What is the formula for VAC (variance at completion)

A

VAC = BAC - EAC

31
Q

In an EVM chart, if earned value is above planned value, what does this mean?

A

means you’ve completed more work than you’ve planned by that date (ahead of schedule)

32
Q

In an EVM chart which info is on the horizontal axis, and which is on the vertical axis?

A

Time is horizontal, cost is vertical

33
Q

In an EVM chart, if the actual cost is below the earned value, what does this mean?

A

You’re spent less for the work you’ve completed than planned (below budget)

34
Q

In an EVM chart, if the earned value is below the planned value, what does this mean?

A

behind schedule (completed less work than you’ve planned

35
Q

In an EVM chart, if actual cost is above earned value, what does this mean?

A

You’ve spent more for work than you’ve completed than planned (over budget)