How to calculate backfill?
Subtract volume of concrete from excavation volume then multiply by swell factor to determine volume in loose CY.
excavation backfill (LCY) equation
Excavation (BCY) - concrete volume (cy) x swell factor (1.35)/compaction factor (.95)
excavation disposal (lcy) equation
Excavation (bcy) x swell factor (1.35) - backfill (lcy)
How to quantify structural steel?
Number of pieces for install labor, and weight for OM estimate. include rolled steel. Include additional 15% for connections
Quantify bolts?
Bolts are quantified by number for labor productivity
Quantify joist?
By length for each type. material and labor may be determined by linear foot.
Quantify decking?
By square feet. include additional 10% for lapping.
Quantify stairs?
By number of flights, number of landings or length.
Quantify dimensional lumber?
by linear foot for listed type then converted to board feet. (BF = (W” x Thick” x length’) / 12”/foot))