Cement Head Flashcards

1
Q

On a standard primary cement job, if the top plug fails to bump, what would you recommend to the customer (choose 2 answers below)?

A
  1. After agreement with the customer, pump an additional volume equal to half the shoe track volume, and then stop pumping.
  2. If the plug still does not bump, stop pumping and check returns.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What should you do if the plug you are installing is too large for the cement head you are using?

A
  1. Notify the Job Supervisor (SS/FE) and let him find a correct alternate plug or decide not to drop the plug.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why are wells cemented?

A
  1. Provide complete isolation of zones (Hydraulic Bond)
  2. To support the casing (Shear Bond)
  3. Protect casing string.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When you get the cement head to location you find that the O ring is damaged on the top cap, what should you do?

A
  1. Replace the O-ring with the correct O-ring.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

After dropping the bottom plug, you begin to pump the slurry but at the same time the area around the lower pin puller begins to leak, how would fix the leak without causing significant amounts of lost time?

A
  1. Screw the pin back in. Making sure the plug was dropped (indicated by the tattle tale) first.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Both you and the customer notice a pressure spike upon releasing the bottom plug, what might this be attributed to (please choose 2 answers)?

A
  1. Possible small amount of dried cement in the valve you just opened.
  2. The pin did not retract all the way - you just burst the bottom plug diaphragm.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If the tattle tail does not indicate that the plug has departed from the head, what is the first action you should take?

A
  1. Inform the client of the problem.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If either of the pin pullers are too stiff to move when you try to launch the wiper plugs, what would be your first action to solve the problem?

A
  1. Remove the head and place the plugs in the casing (as needed), either replace the head or circulating swedge and finish displacing.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Identify the features of a bottom cement (wiper) plug. Select the right answer.

A
  1. Constructed with a hollow core covered with a thin membrane.
  2. Cleans casing wall.
  3. Seat for landing top plugs.
  4. Pressure is used to rupture the diaphragm.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

After the top plug is in the wellbore, which valves are opened to allow the displacement fluid to clear the cement residue from all internal lines in the cement head? Select all the correct answers.

A
  1. Bottom plug valve and middle plug valve.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Select the sentence that best describes the cementing process:

A
  1. When casing is run, cement is used to fill the space between the casing and OH/previous casing.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Fabricated cement heads can withstand up to _______ depending on the size of the head, and the integral heads can be used up to _________ depending on the size of the head respectively.

A
  1. 5000 psi, 10000 psi
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Why does the single-plug cement head represent a higher risk to the operator than the double-plug cement head? Select all the correct answers.

A
  1. Because the top cap has to be removed to load the top plug.
  2. Because the loading of the top plug may occur high above the rig floor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The larger the internal diameter of the cement head, the ___________ the approved pressure rating.

A
  1. Lower
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The customer makes a change to the drilling program, the pressure test after the job now goes beyond the pressure rating of the head, the best plan of action would be what?

A
  1. Remove the cement head, install the circulating swedge, continue with the pressure test.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The pressure rating of a cement head should always be checked after pressuring up the system.

A

b. False must be before