CDT Exam Prep Flashcards 2018
CDT Exam Prep Flashcards 2018
CDT Exam Prep Flashcards 2018
Question #1
Which of these documents, might we find in the Project Manual but they are not contract documents?
A. The Agreement
B. Procurement Requirements
C. Addendum
D. Supplemental Conditions
Question #1
Answer: B
Reference: PDPG 11.1
Explanation: Procurement requirements are addressed to prospective bidders or proposers interested in the project. Although not necessarily part of a contract, the procurement requirements are usually bound with other written construction documents into a project manual.
Question #2
Before a model building code can become the building code for a jurisdiction, it has to be adopted by?
A. Authority Having Jurisdiction
B. State Government
C. Building Inspector
D. International Organization for Standardization
Question #2
Answer: A
Reference: PDPG 6.3
Explanation: Before a model building code can become the building code for a jurisdiction, it has to be adopted by that AHJ. Once adopted, they then are responsible for enforcing that building code within their jurisdiction.
Question #3
The Construction Manager is hired by this entity?
A. General Contractor
B. Owner
C. A/E
D. Contract Administrator
Question #3
Answer: B
Reference: PDPG 4.5
Explanation: The Owner usually engages the services of a Construction Manager, an entity that typically contracts with the Owner to provide construction management services.
Question #4
The parties to the Construction Agreement are?
A. General Contractor, Subcontractor, and Construction Manager
B. A/E, General Contractor, and Contract Administrator
C. Building Official and General Contractor
D. Owner, Contractor, and A/E
Question #4
Answer: D
Reference: PDPG 7.10
Explanation: (PDPG Figure 7.1) The tripartite relationship among the Owner, Contractor, and A/E is created by obligations to third-parties to the contract. For example, the Owner-A/E agreement may require certain duties of the A/E acting on behalf of the Owner during construction. The Contractor has a right to rely on the proper performance of these duties. The A/E, similarly, relies on the Contractor to perform certain duties identified in the Owner-Contractor agreement, even though the A/E is not a party to that contract. The A/E relationship to the contractor in the Owner-Contractor agreement is a third-party relationship. These third-party relationships create the third side of the triangle in the construction process. (PDPG 7.10) The Owner contracts first with the A/E to design the project and to prepare bidding documents. The Owner then obtains bids through the competitive bidding process from bidding contractors. When one of the bidders is selected by the Owner, the Owner will either directly enter into the contract (such as for a project to be constructed with public funds), or negotiate the final cost and then enter into the contract (such as for a privately funded project).
Question #5
The organization responsible for the General Conditions known as 201 are?
A. DBIA
B. AGC
C. AIA
D. CSI
Question #5
Answer: C
Reference: PDPG 12.3.3.2
Explanation: Each document deals with project conditions and issues in a similar manner but with language determined to be in accord with the needs of each organization.
Question #6
When there is a dispute between the specifications and the drawings, what is the proper way to settle the dispute?
A. The drawings have priority
B. The A/E should interpret
C. The specifications
D. Arbitration
Question #6
Answer: B
Reference: PDPG 11.2.10, 11.2.10.4, AIA A201 1.2.1
Explanation: The drawings and specification are complementary documents in the AIA and EJCDC general conditions. (PDPG 11.2.10) Precedence: Questions of precedence often arise among large scale drawings, small-scale drawings, and specifications. However, the use of statements in the project manual to establish the precedence of the various contract documents is not recommended because the documents are complementary. The general conditions of the contract should indicate only that in a case of conflict between drawings and specifications, the A/E will make a documented interpretation. (PDPG 11.2.10.4) When the contract documents are being interpreted, the contents of the drawings and the specifications must be considered together. If an item is not addressed in both the drawings and the specifications, it does not mean that it is not required for the project. (AIA A201 1.2.1) The Contract Documents are complementary, and what is required by one shall be as binding as if required by all.
Question #7
A subcontractor is obligated to the prime contractor in the same manner as the prime contractor is obligated to the:
A. Architect
B. Owner
C. Material Supplier
D. Principal in Charge
Question #7
Answer: B
Reference: PDPG 15.4.4
Explanation: A subcontractor generally provides labor at the site. A material supplier furnishes the materials for others to install. (PDPG 15.4.4) Subcontractor: An entity that has a direct contract with the contractor to perform a portion of the work of the project at the site. (PDPG 15.4.4) Supplier: Furnishes or supplies products or services for the project, but does not perform labor at the site.
Question #8
The requirements of the General Conditions can be modified or expanded to accommodate specific project conditions, owner’s requirements, or unusual aspects relating to the roles, rights, duties, and responsibilities of the parties to the contract for construction, in this document:
A. Contract Modifications
B. Supplemental Conditions
C. Addendum
D. Consensus Documents
Question #8
Answer: B
Reference: PDPG 12.3.3.3
Explanation: The requirements of the General Conditions can be modified or expanded in the Supplementary Conditions to accommodate specific project conditions, owner’s requirements, or unusual aspects relating to the roles, rights, duties, and responsibilities of the parties to the contract for construction. Supplementary Conditions are not standard for every project and must be prepared based on requirements of the specific project.
Question #9
Which of the following are not legal binding construction documents?
A. General Conditions
B. Specifications
C. Preliminary Project Description
D. Addendum
Question #9
Answer: C
Reference: PDPG 11.3.11.2
Explanation: Preliminary Project Descriptions are associated with the Schematic Design Phase and are informational documents that are not used for construction.
Question #10
This document states that the Contractor shall review, approve, and submit to the Architect, shop drawings, product data, samples, and similar submittals required by the contract documents. It also states that the Architect will review and approve or take other appropriate action upon the Contractor’s submittals:
A. Construction Agreement
B. Field Order
C. General Requirements
D. AIA A201
Question #10
Answer: D
Reference: PDPG 15.8.3
Explanation: AIA Document A201 states that the Contractor shall review, approve, and submit to the Architect, shop drawings, product data, samples, and similar submittals required by the contract documents. It also states that the Architect will review and approve or take other appropriate action upon the Contractor’s submittals.
Question #11
Division 01 sections apply broadly to the execution of the work of all the other sections of the specifications. In addition, they expand on certain administrative and procedural provisions of the:
A. Drawings
B. Construction Agreement
C. Conditions of the Contract
D. Procurement Documents
Question #11
Answer: C
Reference: PDPG 11.3.16
Explanation: Division 01 sections expand on certain administrative and procedural provisions in the conditions of the contract and apply broadly to the execution of the work of all the other sections of the specifications.
Question #12
Defined as the written and graphic documents prepared or assembled by the A/E for communicating the project design for construction and administering the construction contract:
A. Construction Documents
B. Plans
C. Procurement Documents
D. Conditions of the Contract
Question #12
Answer: A
Reference: PDPG 15.2.2
Explanation: An important principle governing the production of construction documents is that each document, written or graphic, has a specific purpose and should be used forthat purpose. Each requirement should be stated only once and in the correct location.
Question #13
Typically, Procurement Requirements should not include which of the following documents?
A. Instructions for Procurement
B. Available Information, including Resource Drawings
C. Procurement Forms and Supplements
D. Performance Bonds
Question #13
Answer: D
Reference: PDPG 12.1, 12.2
Explanation: Typically, Procurement Requirements include the following documents: solicitation; Instructions for Procurement; Available Information, including Resource Drawings; Procurement Forms and Supplements; Addenda (as applicable to procurement). Thus, Performance Bonds are not included in the procurement documents. Thus, Performance Bonds are not included in the procurement document.
Question #14
The Invitation to Bid is designed to attract:
A. Architects
B. Designers
C. Qualified Bidders
D. Subcontractors
Question #14
Answer: C
Reference: PDPG 12.2.1
Explanation: The Invitation to Bid is intended to attract qualified bidders and to help prospective bidders decide whether to obtain the procurement documents.
Question #15
The volume containing the specifications, Conditions of the Contract, Information to Bidders, Instructions to Bidders, and the bid form is called:
A. Spec book.
B. Preliminary Project Descriptions.
C. Project Manual.
D. Submittals.
E. None of the above.
F. All of the above.
Question #15
Answer: C
Reference: PDPG Figure 11.1
Explanation: See PDPG figure 11.1
Question #16
The documents developed to attract and assist qualified bidders in properly submitting bids are called?
A. Contract Documents
B. Procurement Requirements
C. Conditions of the Contract
D. Bidders Agreement
Question #16
Answer: B
Reference: PDPG 11.1
Explanation: Procurement Requirements instruct the bidders or proposers about the established procedures or preparing and submitting their bids or proposals.
Question #17
Signed by each party the Agreement can be best explained as:
A. Defines the relationship of the Owner, A/E, and Contractor
B. Is the one instrument of the contract documents that binds the signing parties to the work
C. Constitutes the legal portion of the specifications
D. Binds the Architect to the General Contractor
Question #17
Answer: B
Reference: PDPG 7.10.3
Explanation: The Agreement is the written document signed by each party, and it is the legal instrument binding the parties to the contract.
Question #18
An Alternate:
A. Is the same as an option in the specifications.
B. Is used for the same purpose as unit prices.
C. Should be described in Division 01 and specified in the appropriate specification sections.
D. Should be described in detail on the bid form.
Question #18
Answer: C
Reference: PDPG 13.8.2, 12.2.4, 13.8.2
Explanation: (PDPG 13.8.2) Alternates should be carefully expressed in the procurement documents, including the criteria by which alternates will or will not be awarded. Alternates should be clearly delineated on the drawings as well as addressed appropriately in the specifications. If this is not done carefully, misunderstandings and misinterpretations can occur regarding the scope of an Alternate. (PDPG 12.2.4) Alternates may be either additive or deductive to the base bid, the stipulated sum bid, or the total unit price bid. Appropriate blanks should be provided on the bid form. They must be clearly described in Division 01, Section 01 23 00 Alternates. The Instructions to Bidders should contain guidance for preparing alternate bids. (PDPG 13.8.2) Division 01 sections on Allowances and Alternates require particular coordination with the sections in other divisions that specify the affected products.
Question #19
Contract Documents consist of:
A. Agreement between Owner and Contractor, Conditions of the Contract, Drawings, and Specifications, Addenda and Modifications, other Documents listed in the Agreement.
B. Agreement between Owner and Contractor, Conditions of the Contract, Drawings and Specifications, Project Manual, Shop Drawings.
C. Agreement between Owner and Contractor, Conditions of the Contract, Drawings and Specifications, Instructions to Bidders, Bid Form, Addenda, Modifications, other documents listed in the Agreement.
Question #19
Answer: A
Reference: PDPG Figure 11.1
Explanation: The Contract Documents include Contracting Forms, Project Forms, Conditions of the Contract, Specifications, Contract Drawings, Revisions, Clarifications, and Modifications.
Question #20
Contract documents include:
A. Written portions of the contract only.
B. Graphic portions of the contract only.
C. Both written and graphic portions of the contract.
D. Invitation to Bid.
Question #20
Answer: C
Reference: PDPG 11.1
Explanation: Contract Documents consist of both written and graphic elements and typically include the following: contracting requirements, specifications, contract drawings, pre-contract revisions, clarifications and proposals, and contract modifications.
Question #21
Addenda are used to:
A. Modify the procurement documents before award of the contract.
B. Modify the contract documents after award of the contract.
C. Modify drawings and specifications only.
D. Formalize verbal instructions given during bidding.
Question #21
Answer: A
Reference: PDPG 11.1
Explanation: Addenda are written or graphic documents issued to clarify, revise, add to, or delete information in the procurement documents or in previous addenda. Typically, an addendum is issued prior to the receipt of bids or proposals.
Question #22
The Agreement is part of the:
A. Bidding Requirements.
B. General Conditions.
C. Specifications.
D. Contract Forms.
Question #22
Answer: D
Reference: PDPG 12.3.1
Explanation: The form of agreement to be used for a project is identified in the contracting requirement portion of the procurement documents. It is good practice for procurement documents to contain the form of agreement for the prospective contractor’s reference.
Question #23
Division 01 should be used to:
A. Provide a location for General and Supplementary Conditions.
B. Provide a means to modify standard sections of the specifications.
C. Provide a logical arrangement for specifying administrative, procedural, and temporary facilities.
D. Provide a location for specifying special construction and materials the bidders might overlook.
Question #23
Answer: C
Reference: PDPG 11.3.16
Explanation: See PDPG 11.3.16 for a complete discussion.
Question #24
Division 01 sections relate to:
A. Procurement requirements, the agreement, general and supplementary conditions, and specifications.
B. Procurement requirements, the agreement, general and supplementary conditions, the specifications, and the drawings.
C. The agreement, general and supplementary conditions, and specification only.
D. The agreement, general conditions, specifications, and drawings.
Question #24
Answer: B
Reference: PDPG 11.3.16.2
Explanation: See PDPG 11.3.16.2 for a complete discussion.
Question #25
Division 01 sections should coordinate with:
A. Procurement requirements and the agreement
B. General and supplementary conditions
C. Specifications and Drawings
D. All of the above
Question #25
Answer: D
Reference: PDPG 11.2.10.4, 11.3.16.2
Explanation: (PDPG 11.2.10.4) Particular attention should be given to coordinating Division 01 sections with the conditions of the contract. The level of specification detail should complement the level of drawing detail. Early coordination with sufficient time devoted to the task will help achieve design intent and promote elimination of problems during the construction stage. (PDPG 11.3.16.2) Specification sections are subject to the administrative and procedural requirements of the conditions of the contract and of Division 01.
Question #26
Administrative and procedural requirements are specified in:
A. General Conditions.
B. Supplementary Conditions.
C. Division 01 General Requirements.
D. Bidding requirements.
E. Instructions to Bidders.
Question #26
Answer: C
Reference: PDPG 11.3.16
Explanation: The sections in Division 01, which are collectively referred to as the General Requirements, specify administrative requirements, procedural requirements, temporary facilities and controls, performance requirements, and life cycle activities.
Question #27
The agreement form, before modification, should be reviewed carefully by the:
A. Owner’s legal counsel.
B. Owner.
C. Architect and Owner.
D. Contractor.
Question #27
Answer: A
Reference: PDPG 7.10.2
Explanation: The agreements and forms to be used on a project should be reviewed carefully by the party’s legal counsel before modification and execution.
Question #28
If a contractor recognizes or has knowledge of errors, inconsistencies, or omissions in the contract documents, the contractor is responsible for reporting those errors, omissions, or inconsistencies to:
A. Owner.
B. Authority Having Jurisdiction (AHJ).
C. A/E.
D. His/her Surety Company.
Question #28
Answer: C
Reference: AIA A201 3.2.2
Explanation: Typically, the conditions of the contract require the contractor to report errors, inconsistencies, or omissions to the A/E. The contractor could be held liable for not repeating errors, inconsistencies, oromissions if the contractor knew there were errors, inconsistencies, or omissions.
Question #29
Shop drawings, product data, and samples are:
A. Considered part of the contract documents.
B. Not contract documents.
C. Prepared by the Architect.
D. Prepared during construction document stage.
Question #29
Answer: B
Reference: AIA A201 3.12.4
Explanation: (AIA A201 3.12.4) Shop Drawings, Product Data, Samples and similar submittals are not Contract Documents. Their purpose is to demonstrate how the Contractor proposes to conform to the information given and the design concept expressed in the Contract Documents for those portions of the Work for which the Contract Documents require submittals