CD Terms Flashcards

1
Q

fiduciary

A

is a party that has been entrusted with the property of another for safekeeping.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

pro forma

A

A pro forma is assumed, forecasted, or informal information presented in advance of the actual or formal information. The common objective of a pro forma document is to give a fair idea of the cash outlay for a shipment or an anticipated occurrence. Pro forma financial statements give an idea of how the actual statement will look if the underlying assumptions hold true. Latin for, according to form or for form’s sake.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A tort claim is a claim made against another party due to ____________.

A

Torts are civil wrongs recognized by law as grounds for a lawsuit. These wrongs result in an injury or harm constituting the basis for a claim by the injured party.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

common law

A

the law developed by the common law courts as being common to all the Crown’s subjects, as distinct from equity.
a general name for Anglo-American case-based systems, as opposed to civilian code-based systems.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

date of substantial completion

A

The date, certified by the architect, when the construction is sufficiently completed, in accordance with the contract documents, so that the owner can occupy the project for the intended use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

application for payment

A

a contractor’s written request for payment of the amount due on account of work completed and or materials suitably stored on site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

final completion

A

The completion of all work in accordance with the terms and conditions of the contract documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

subcontractor

A

one who has a contract with a prime contractor to perform a portion of the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

means of egress

A

The elements which comprise an exit to the outside, including aisles, corridors, doors, and stairways

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

general contract

A

The contract between the owner and the contractor for the construction of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

single prime contract

A

A contract for building construction under which one prime contractor is responsible for the entire project, in contrast to having separate contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

record drawings

A

A term sometimes erroneously used to describe a drawings revised to show changes made during construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

unit price

A

An amount, stated in dollars per unit, provided by the contractor with his or her bid for adding or deleting specific portions of the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

lump sum contract

A

An agreement under which the architect or contractor is paid a specific amount as the total fee for services performed. Also called stipulated sum contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

consultant

A

An engineer or other specialist retained by the architect to provide specified professional services to the architect which the architect is required to provide to the owner under the owner-architect agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

letter of intent

A

A letter signifying intention to enter into a formal agreement and setting forth the general terms thereof

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

performance specification

A

A specification which defines products or systems by describing end results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

substantial completion

A

As defined in the AIA General Conditions, completion of a project to the point where the owner can occupy all or designated portions of the work for the purpose for which it is intended

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

mechanic lien

A

A claim on property by those who furnish material or labor for the construction of a building. Clear title to the property cannot be obtained until the claim is settled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

waiver of lien

A

A document by which one relinquishes the right of a mechanic’s lien against the property of another

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

standard of care

A

The requirement that a professional exercise reasonable ability and judgement in a specific circumstance, the absence of which constitutes negligence. Also called due care

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

guaranteed maximum cost

A

An amount established in a arrangement between an owner and a contractor as the maximum cost of performing specified work. Also called upset price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

sample

A

A material or assembly submitted for the architect’s approval prior to the manufacturer or delivery to the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

warranty

A

A legally enforceable assurance of the quality of materials and labor furnished for a project, or of the length of time that a project or a part thereof will perform satisfactorily. Also called a guarantee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

fast-track

A

Describing a construction procedure in which construction on each phase of a project is begun when its design is completed, without waiting for overall project design completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Americans with Disabilities Act (ADA)

A

Federal civil rights legislation which establishes the right of persons with disabilities to equal access to sites and buildings and set design guidelines for its implementation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

certificate of substantial completion

A

A document prepared by the architect stating that the work is substantially complete, thereby establishing the date of substantial completion. It generally fixes the time within which the contractor must complete the unfinished work listed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

bid

A

A proposal by a contractor to do the work required by the contract documents for a stipulated sum of money

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

critical path method (CPM)

A

A system of planning and scheduling construction operations which analyzes sequences and durations of time using network diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

cost-plus fee contract

A

An agreement under which the contractor, or the architect is reimbursed for his or her costs and in addition is paid a fee for his or her services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

contract time

A

The period of time within which the work must be completed, as established in the contract documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

progress payments

A

Payments made to the contractor during progress of the work on account of work completed and/or materials suitably stored

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

liquidated damages

A

a sum chargeable against the contractor as reimbursement for damages suffered by the owner because of the contractor’s failure to complete the work within a specified time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

construction management (CM)

A

Management services performed by the architect or others, over and above normal architectural services that contribute to the control of time and cost in the construction project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

change order

A

A written order to the contractor, prepared by the architect and signed by the owner, contractor, and architect, which authorizes a change in the work, the contract sum, or the contract time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

professional liability insurance

A

Insurance which financially protects an architect against claims for damages resulting from professional negligence. Also called errors and omissions insurance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

construction documents

A

Working drawings and specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

bidding documents

A

The invitation to bid, instructions to bidders, bid form, and the contract documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

submittal

A

A shop drawing, project data, or sample submitted by the contractor to the architect for review prior to incorporation in the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

base bid

A

The sum of money stated in the bid for which the bidder offers to do the work, not including any alternate bids.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

insurance

A

coverage by contract, whereby one party agrees to indemnify or reimburse another against the loss from a specified hazard

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

statue of limitations

A

An ordinance which specifies the period of time within which legal action must be brought to obtain legal relief for damage or injury.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

certificate of occupancy

A

A document issued by the governing authority stating that a building complies with application laws and permitting occupancy for its designated use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

negligence

A

Failure to meet the ordinary standard of care expected of an architect or other professional in a specific circumstance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

surety bond

A

An agreement under which one party (the surety) guarantees to make good to another party (the obligee) the debt, default, or failure to perform of a third party (the contractor). also called a bond.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

performance bond

A

a bond which guarantees to the owner that the contractor will perform the work in accordance with the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

release of lien

A

A legal document signed by the supplier of material or labor for a project, which releases his or her mechanic’s lien against the property

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

advertisement for bids

A

Published public notice soliciting proposals for a construction project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

certificate for payment

A

A statement by the architect informing the owner of the amount due to the contractor on account of work completed and or materials suitably stored

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

supplementary conditions

A

Part of the contract documents prepared by the architect, which may modify provisions of the general conditions of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

payment request

A

A contractor’s written request for payment of the amount due on account of the work completed and or materials suitably stored on site. Also called application for payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

project representative

A

The architect’s representative at the site, who assists in the general administration of the construction contract for a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

labor and material payment bond

A

A bond guaranteeing to the owner that the contractor will pay for all the labor and materials used for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

due care

A

The requirement that a professional exercise reasonable ability and judgement in a specific circumstance the absence of which constitutes negligence. Also called standard of care.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

upset price

A

An amount established in an agreement between the owner and a contractor as the maximum cost of performing specified work. Also called guaranteed maximum cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

deposit for bidding documents

A

a deposit of money required for each bidder as security for the bidding documents to sure the return of the documents by unsuccessful bidders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

property insurance

A

Fire and property damage insurance for a project during construction usually purchased by the owner, Also called builder’s risk insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

construction change directive

A

A document signed by the owner and the architect which authorizes a change in the work, the contract sum, or the contract time. It is used when there is not complete agreement on the terms of a change order.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

XCU

A

The exclusion from insurance coverage for liability arising out of X explosion or blasting, Collapse of a structural damage to a building and Underground damage caused by mechanical equipment

60
Q

Observation

A

On-site examination of the contractor’s work by the architect to determine in general if it is proceeding in accordance with the contract documents

61
Q

Worker’s compensation insurance

A

Insurance which covers workers job related injuries usually required by law

62
Q

sick building syndrome

A

A term used to describe poor air quality, which can lead o discomfort and possibly disease

63
Q

shop drawings

A

drawings prepared by the contractor, subcontractor, manufacturer, or supplier, showing how specific portions of the work shall be fabricated and or installed

64
Q

contract sum

A

The total payable amount by the owner to the contractor, as stated in the owner-contractor agreement for performing the work under the contract documents

65
Q

specifications

A

Part of the contract documents comprising written descriptions of materials, construction systems and workmanship

66
Q

surety

A

An individual or company that guarantees to make good to another party the debt, default, or failure to perform of a third party

67
Q

basic services

A

The architectural services normally required for a building project, usually consisting of schematic design , DD, CD, bidding or negotiation and construction contract documents

68
Q

addition to the contract sum

A

An amount added to the contract sum wither by an accepted additive alternate or by change order

69
Q

schedule of values

A

A statement furnished to the architect by the contractor reflecting the amounts to be allotted for the principal divisions of the work. It serves as a guide for reviewing the contractor’s periodic application for payment

70
Q

fixed limit of construction cost

A

the maximum allowable cost of the construction work, as established in the owner-architect agreement.

71
Q

option

A

a choice given to the contractor to provide specified alternates without prior approval of the architect

72
Q

superintendent

A

the contractor’s representative at the site

73
Q

gurantee

A

A legally enforceable assurance of the quality of materials and labor furnished for a porject, or of the length of time that a project or a part thereof will perform satisfactorily. Also called a warranty

74
Q

retainage

A

An amount withheld from each payment to the contractor in accordance with the terms of the owner-contractor agreement

75
Q

as-built drawings

A

drawings showing existing conditions

76
Q

barrier-free provisions

A

Regulations which provide for accessibility to buildings and sites for persons with disabilities

77
Q

bond

A

An agreement under which one party (the surety) guarantees to make good to another party the debt, default, or failure to perform of a third party (the principle). Also called a surety bond

78
Q

punch list

A

A list of items to be corrected or completed, which is provided by the contractor and usually expanded by the architect based on a detailed inspection of the work prior to substantial completion.

79
Q

agent

A

One who acts on behalf of another

80
Q

working drawings

A

the part of the contract documents prepared by the architect which graphically illustrates the construction required for the project

81
Q

float

A

The extra time available for a construction activity above its estimated time duration without causing any delay of project completion

82
Q

additive alternate

A

A proposal by a bidder for an amount to be added to the base bid if the corresponding change in the work is accepted.

83
Q

program

A

A written statement of the owner’s conditions and requirements for the project

84
Q

indirect expense

A

Overhead expense, that is expenses indirectly incurred and not chargeable to a specific project. Also called overhead expense

85
Q

bid bond

A

a surety bond guaranteeing that the bidder will sign a contract if offered in accordance with his or her proposal.

86
Q

reference specification

A

A specification which refers to quality standards established by recognized testing authorities or by the federal government.

87
Q

substitution

A

A material system or product proposed y a contractor as being equivalent to that required by the contract documents

88
Q

liability insurance

A

insurance which financially protects the insured against liability on account of bodily injury or property damage sustained by another

89
Q

post completion services

A

additional services rendered to the owner by the architect following actual completion of the project

90
Q

certificate of insurance

A

A memorandum which outlines the types and limits of the insurance coverages carries by the contractor for a project

91
Q

instructions to bidders

A

Instructions in the bidding documents for preparing and submitting bids for a project. Also called notice to bidders

92
Q

contract documents

A

working drawings, specifications, addenda, general conditions of the contract, supplementary conditions, and the owner-contractor agreement

93
Q

direct personnel expense (DPE)

A

Salaries and wages attributable to a specific project, plus benefits such as employment taxes, insurance, sick leave, holidays, vacations, pensions and similar benefits

94
Q

project budget

A

The sum established by the owner as available for the entire project, including the construction budget, land cost, equipment cost, financing cost, cost of professional services, and contingency allowances

95
Q

lowest acceptable bonna fide bid

A

the lowest bid which complies with all the stipulated requirements

96
Q

CSI MasterFormat

A

A systematic listing of construction trades, materials, systems, and administrative requirements published y the Construction Specifications Institute for the purpose of organizing construction specifications.

97
Q

prime contractor

A

any contractor on a project who has a contract directly with the owner

98
Q

project manual

A

The manual prepared by the architect for a project including the technical specifications bidding instructions and forms, general conditions, supplementary conditions, special conditions and other legal admin documents

99
Q

hold harmless clause

A

a contractual obligation whereby one party agrees to guarantee another party against loss or damage from specified liabilities Also called indemnification

100
Q

comprehensive services

A

The architects basic services expanded to include certain additional services such as programming, land use studies and so on.

101
Q

Division One

A

The general requirements division of the specifications which establishes the administrative and procedural duties of the contractor, architect, and owner during construction

102
Q

addenda

A

statements or drawings which modify the basic contract documents after the latter have been issues to the bidders, but prior to closing the bids

103
Q

arbitration

A

An alternative to litigating a dispute in which one or more arbitrators hears the evidence and renders a decision

104
Q

direct expense

A

expense items directly incurred by or attributable to a specific project

105
Q

supervision

A

Direction of the work by the contractor’s personnel. Supervision is not the responsibility of the architect

106
Q

cash allowance

A

an amount not included in the contract sum to cover the cost of certain items not specified in detail. Hardware and other finish items are often handled in this manner.

107
Q

closed proprietary specification

A

A proprietary specification which requires a particular brand or trade name and does not permit any substitutions

108
Q

overhead expense

A

Indirect expense, that is expenses indirectly incurred and not chargeable to a specific project. Also called indirect expense

109
Q

special conditions

A

Part of the contract documents, other than the general and supplementary conditions describing unique conditions of a project

110
Q

express warranty

A

a legally enforceable promise made by the warrantor

111
Q

subrogration

A

The substitution of one entity for another with regard to legal rights

112
Q

indemnification

A

a contractual obligation whereby one party agrees to guarantee another party against loss or damage from specified liabilities. Also called the hold harmless clause.

113
Q

descriptive specification

A

A specification which describes all product components, arrangements, assembly methods, properties and other details and requirements.

114
Q

builder’s risk insurance

A

Fire and property damage insurance for a project during construction usually purchased by the owner. Also called property insurance

115
Q

notice to bidders

A

Instructions in the bidding documents for preparing and submitting bids for a project. Also called instructions to bidders

116
Q

total quality management

A

an approach to the delivery of goods or services in which quality is determined by customer satisfaction and conformance to requirements

117
Q

approved equal

A

A material or method that is approved by the architect as being equivalent to what was originally specified

118
Q

errors and omissions insurance

A

Insurance which financially protects an architect against claims for damages resulting from professional negligence. Also called professional liability insurance

119
Q

percentage agreement

A

An owner-architect agreement under which the professional fee is based upon a percentage of the construction cost of the project

120
Q

Davis-Bacon Act

A

Federal legislation that requires the Department of Labor to set prevailing wages for government-financed construction projects

121
Q

multiple of direct personnel expense agreement

A

An agreement providing for payment for professional services based upon the direct personnel expense multiplied by an agreed factor.

122
Q

trade discount

A

The difference between the list price and the actual price paid

123
Q

penalty

A

A charge against the contractor for failing to complete the project by a specific date

124
Q

separate prime contract

A

One of several owner-contractor agreements for a project, each of which provides for constructing a major portion of the work (general construction, electrical, mechanical, etc.) by a different contract

125
Q

Pert

A

Acronym for a project evaluation review technique. A form of network analysis developed for military work and similar to the critical path method.

126
Q

Proprietary specification

A

A specification which calls for desired materials products, systems, and equipment by their trade names and model numbers

127
Q

clerk of the works

A

The owner’s job site representative

128
Q

contingency allowance

A

An amount included in a construction budget normally 5 to 10 percent, to provide for unforeseen or unpredictable costs

129
Q

bonus and penalty clause

A

A provision in the construction contract for payment of a bonus to the contractor for completing the project prior to a specific date, and for a charge (penalty) against the contractor for failing to complete the project by that date.

130
Q

alternate bid

A

A proposal by a bidder for an amount to be subtracted from or added to the base bid if the corresponding change in the work is accepted. This may be either a deductive or additive alternate.

131
Q

completion bond

A

A bond obtained by the contractor or owner which guarantees that the project will be completed free of liens

132
Q

stipulated sum contract

A

An agreement under which the architect or contractor is paid a specific amount as the total fee for services performed. Also known as lump sum contract

133
Q

open proprietary specification

A

A proprietary specification which names several acceptable materials, products, or systems any of which may be used by the contractor.

134
Q

incentive clause

A

A clause in a cost plus fee contract between the owner and the contractor in which the savings between the guaranteed maximum cost and the actual project costs are proportionally shared.

135
Q

deductive alternate

A

A proposal by a bidder for an amount to be subtracted from the base bid if the corresponding change in work is accepted.

135
Q

Base bid with alternates

A

A type of specification that calls out a proprietary product but allows the substitution of other products that the contractor thinks are equal to the one stated.

136
Q

ASTM

A

American Society for Testing Materials

137
Q

ANSI

A

American National Standard Institute

138
Q

MSDS

A

Is a listing of product safety information prepared by manufacturers and marketers of products containing toxic chemicals

139
Q

Construction procurement services

A

During this phase the architect must assist the owner in obtaining competitive bids or negotiated proposals and must assist in awarding the contract and preparing contracts for construction.

140
Q

Privity

A

One party to a contract is protected from claims from other parties with whom there is no direct contractual relationship.

141
Q

Pre-bid conference

A

A meeting with the architect, owner, and bidders during which the bidders can ask questions and the architect and owner can emphasize particularly important conditions of the project

142
Q

Sole proprietorship

A

The company is owned by an individual and operates under the individuals name or a company name.

143
Q

Corporation

A

An association of individuals created by statutory requirements and having an existence independent from its members. Usually taxed at a lower rate than individuals.

144
Q

field sketch

A

is used to revise contract documents based on conditions found in the field