Case Study Questions Flashcards
The property was in a conservation area – what implications did this have?
As part of this project, we also planned to replace the existing shop front window. Therefore this element of the works would require planning approval. However, as the property is located within a conservation area, we were restricted on what materials we could use. the original proposal allowed for replacing the exiting timber frame, with a aluminum frame. However, this option was not favorable with the local planners, therefore the compromise was to replace the shop front frame with hardwood, but to include a double glazing unit to improve energy efficiency.
What information did you supply to building control?
Plans and specification, which includes; Details and spec of floor upgrades heating system design and spec FA system upgrades Information of the replacement shop front window. Partitions systems and Fire doors. Lighting/emergency lighting and ventilation. Information on M doc accessible w/c
What negotiations were required with the planning officer? How did you carry these out?
Due to the limited timescale and a oversight by myself, the planning application was submitted to the local authority, with out obtaining per-planning advice on the best suitable option for the replacement shop front window. However, I did contract the planning department to find out what there thoughts were, and it was at this point that it was established that the original proposal would not be approved. Therefore, I planning to meet the Planners on site to discus the option available, and it was advised that the frame would need to be Timber, and I was able to negotiate that the glazing to be double glazed, as I was able to point out some of the surround shopfront windows had been replaced with a double glazing unit.
The project was based in Wales. Were there any additional considerations to make when compared to it being based in England?
In Wales, Building Regulations that previously applied to England and Wales continue to apply, but from 01 January 2012, any revisions to the English regulations apply to England only. New regulations and guidance are the responsibility of the Welsh government (ref Welsh Government: Building Regulations). Approvals are granted by the local authorities.
What do you understand by stakeholder management? Did you utilise any stakeholder management on your project?
There is no single answer or approach for Stakeholder Management, however below are a good recommendation; Communication Consult early and often Remember they're only human Plan it Relationship are key Simple, but not easy Just part of managing risk Compromise Understand what success is Take responsibility
Why did you use JCT MW with Contractors design? What elements did the contractor design? Were there any warranties in place for these works?
We used JCT MW with CD as we required the contractors were required the design the replacement heating system, as per my clients requirements.
How did you arrive at the figure of £600 LADs?
Professional/management fees
Loss of meeting room hire
General inconvenience for the client.
You have said that you would require a contractor to open up the floor to allow to undertake the intrusive survey, what other methods are there?
I could have looked at using a borascope, however, i felt that in order to get a real feel of what is going on, opening up the floor voids would be the best option.
my opinion may have been different, if the floor was occupied at the time of inspection, as i would not want to course unnecessary disruption to the staff, however, as the floor was vacant, and we have approval from the LL, this was not a problem.
At what point are alterations required to meet the guidance contained within approved document L2B.
Under Part L2B consequential improvement is required in buildings with a total useful floor area greater than 100m2, and greater that 25% of the total useful floor area of the existing building.
Replacement shop front window = 1.8 W/m2.K for the whole unit.
Rear roof = 0.18 (W/m2.K)
Floor = 0.25 (W/m2.K)
How would the provisional sums in key issue 2 option 2 be expended? What would be the implication on programme?
The PC Sums were defined, therefore the contractor would have allowed for these works in his programme.
if they had been undefined PC Sums, then the contractor would have been allowed to claim for additional costs suffered and a extension of time.
You have said you used a framework contractor. How is this process managed?
Sorry, this was a mistake, the contractors were not on a framework, but were selected from a pre approved list of contractor on my employers approved contractor list.
How much additional time did you allow the contractor for the additional works? How was this figure arrived at?
we allowed 2 additional weeks, for the structural works. this was calculated from discussions with the structural engineer, the contractor and previous experience from other similar projects.
What information is contained within a license to alter? Who agrees the license?
???
Did the removal of the asbestos roof require any party wall notices? Which one (s)?
Yes, was it bridge both my client property and the adjacency owner property.
Part structure notice was required.
Was the removal of the asbestos roof notifiable? Why?
No, as this was identified as non notifiable works in the R&D survey and the HSE also have a useful guide on what is and what is-not notifiable.