Case Study Q&A Flashcards
Why was D&B selected?
The client wanted to prioritise transferring risk over to the contractor over ensuring quality.
Risk was a higher priority than quality.
What design stage was the project tendered at?
RIBA Stage 3
The design could of been developed to RIBA stage 4, to help retain quality and mitigate further risk for the client, but this would negate the programme savings.
Given that a two-stage traditional tender was appraised, why wasn’t a two-stage D&B route appraised?
In heindsight, it would of been a good option to consider.
Advantages
- Increased contractor involvement in design
– Ability to overlap design and tendering
Disadvantages
- Lack of competitiveness during second stage
– Programme implication to include a tender period (although this can be overlapped with design)
Which takes precedence the ERs or CPs under a D&B route?
Unamended, CP takes precedence if conflict with ERs
- CPs are prepared by the contractor which responds to the employer’s requirements.
- In this document(s), the contractor will set out a more detailed design (based on the employer’s requirements), which will require further development throughout the course of the project.
If amended, ERs take precedence.
On St John Wood House, how was quality maintained and risk of derogation from the clients expectation of this quality maintained?
The design team were involved in inspecting and testing the completed design and construction work, and identifying and documenting any quality issues and defects.
In Key Issue 2, you mention that due to limited time for cost planning and design development you recommend proceeding with the current specification – could you explain this a bit more?
Given that programme was also a key driver for the client, and given the point at which the overspend was identified, this left little time to engage in a detailed VE exercise. As such, it was decided to proceed with the the current specification.
What is the difference between scope reduction and VE?
Scope reduction is the process of cutting activities associated with a project, while value engineering (VE) is a process that involves finding ways to reduce costs while maintaining the value of a project
Is VE purely about reducing cost?
No, value engineering is about a creative problem-solving process that aims to optimize value while minimizing costs.
Could you tell me the difference between Value Management and Value Engineering?
Value management (VM) and value engineering (VE) are both used to improve the value of a project, but they differ in their scope, approach, and when they are best applied:
Approach
VM is a positive process that seeks to balance time, cost, and quality, while VE can be seen as a negative process that focuses on eliminating costs.
Audience
VM reports are often strategic documents for a broad range of stakeholders, while VE reports are more technical and written for engineers or project managers.
Timing
VM should be carried out early in a project, while VE is more systematic and can be used to address specific functions.
Could you suggest and example where VE may increase in cost?
- Choosing cheaper materials to reduce upfront costs might lead to increased maintenance or replacement costs in the future.
- Investing in a energy efficient material / plant in the short term, to reduce cost in the long term.
You refer to comparing against benchmark data – what do you need to consider when comparing against benchmark data?
Location
Time
Abnormals
Using indices such as those in BCIS
Did you come up with the value engineering options yourself?
No, I discussed these with the wider design team, to try and establish, given the programme constraints, what we could VE.
Did you explain to the client that all four objectives (Time, Risk, Quality & Cost), may not be achieved?
Yes, typically 2 or 3 of these priorities take precedence and are achieved at the sacrifice of the other(s)
If design lacked the detail, which I assume at RIBA stage 3 on a high end house it would, that there would be financial risk. Even if you developed design to RIBA stage 4, would there still not be a premium?
There would yes, but it would be likely that the premium included by the contractor may be lower due to less risk.
How would you make sure the contractor does not cut costs on a D&B?
- Robust ERs
- Regular Monitoring - Ensuring the design team were involved in inspecting and testing the completed design and construction work, and identifying and documenting any quality issues and defects.
- Transparent Communication
Could you start on site earlier with a singe stage competitive tender and how?
Going out to tender with a less developed design including CDP and PSums
Is there a way you could appoint a contractor without a PCSA?
A letter of intent (LOI) is a possible alternative to a pre-construction service agreement (PCSA):
PCSA: A comprehensive, stand-alone agreement for a specific scope of work.
LOI: A temporary placeholder for a building contract that’s used when a preferred contractor has been identified but some details are still being worked out. LOIs are often used to give parties time to finish negotiations and start work while the final details are agreed. However, not all LOIs are legally binding.
Traditional two-stage tender - How did you ensure competitiveness throughout the second stage?
You could ask for 3 quotes for certain / large package.
How did the client set their budget?
Did you complete previous estimates?
Did you have sufficient contingency’s?
The client wanted to target a budget of approx £1000/ft2
Yes, the PTE did represent a significant uplift however, the client did not request any VE up until that point.
We had a contingency but the overspend ultimately used it all up.
How far off was the PTE to the tender return?
The PTE was £65K higher.
£6.3m & £6.235m