Case Study Flashcards
Listen building grades
Grade 1 - exceptional interest
Grade 2 - more than special
3 - special
What were some implications of listed?
Grade 1 - more stringent no alterations to external facade
Grade 2 - change the glazing but keep horizontal stone
Cost implications of listed building?
Comes with cost premiums bc need specialist contractors such as heritage stone
Problems with overlapping design and construction?
Interface problems
Seen on projects where design later down the line hasn’t aligned with where MEP was being installed
Why can design be incorporated at later date in CM?
Employer has greater control of design
Risk with client under D&B
- performance of contractor
- changes come with premiums
FA on intermediate
Contractor has 6 months to agree and then Employer 3 months
FA with intermediate?
Contractor has 6 months and then employer has 3 months
Privity of contract
Obligations of contract can’t be put on anyone not party to the contract
RICS annual return
Company details
PII
CHP
Client money handling procedure
Levitt review
New obligations for organizations
Cooperate with RICS
Have a CHP
Have appropriate PI