Case Study Flashcards

1
Q

How did you deal with correction of errors in priced tender documents?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why did you choose the JCT intermediate building contract over the minor works building contract and what are the key differences?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Tell me about the contents of the pre construction pack?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you evaluate tenders and select a contractor?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you ensure that the tendering process was fair?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What advice did you give the client about Insurance under the JCT Intermediate Building Contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the purpose of the Joint Names Insurance Policy under the JCT Intermediate Building Contract?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How did you document or record the client’s brief?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What were some of your duties as principal designer?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What documentation would you produce as a principal designer under CDM 2015?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What steps did you take to identify, eliminate or mitigate any health and safety risks associated with the design?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How did you ensure that the design complied with any relevant industry standards or best practices?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How did you manage the design process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Why did you undertake bi-weekly inspections?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you ensure compliance with health and safety regulations during a site inspection?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What should be included in a site inspection report?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How did you provide accurate weekly reports to stakeholders if you only attended site on a bi-weekly basis?

A
18
Q

Why would an asbestos consultant be required for removal of windows?

A
19
Q

Other than fire rated plasterboard, what other alternative method could you have adopted to infill the window opening?

A
20
Q

How do you determine the appropriate materials for infilling windows?

A
21
Q

What are the key considerations when infilling windows?

A
22
Q

What are the potential issues with infilling windows in the mannerrecommended?

A
23
Q

What is the difference between a Relevant Event and a Relevant Matter in a building contract?

A
24
Q

Had the client appointed a new contractor and run the new works concurrently, could this have lead to frustration of the original building contract?

A
25
Q

Would the first contractor be entitled to a EoT/loss and expense claim?

A
26
Q

What are the potential remedies available to the contractor who has suffered loss due to frustration of a building contract?

A
27
Q

How would you have dealt with the instruction/variation if the contractor quoted vastly inflated sum for the new works?

A
28
Q

Within the context of CDM2015, what would the implications have been with two principle contractors working on site together?

A
29
Q

How did you assess if the reinforcing bars were of a sufficient depth?

A
30
Q

How did you advise on the cost Impact of new concrete piers built off pad foundations?

A
31
Q

How did you ensure that contract terms and conditions were being met by both parties?

A
32
Q

How do you ensure that contractors are fulfilling their obligations under the contract?

A
33
Q

How did you evaluate contractor performance?

A
34
Q

Tell me about a issue you observed in one of your inspections and how you addressed it?

A
35
Q

How would early engagement with specialists have helped with Key Issue 1?

A
36
Q

What issues did you encounter with the light levels in this project and how did you address it?

A
37
Q

What were some of the successes of this project?

A
38
Q

How did you act professionally during this project?

A
39
Q

What would you do differently in future projects based on the lessons learned from this project?

A
40
Q

What would you do differently next time?

A
41
Q

How did you act ethically?

A
42
Q

What were your key achievements?

A