Case Study Flashcards
Please explain what you mean by the ‘Lump Sum’ contract form.
What standard form of contract is this?
What Is a Lump Sum Contract? Under a lump sum contract, also known as a stipulated sum contract, the project owner provides explicit specifications for the work, and the contractor provides a fixed price for the project
What standard form of contract is this?
A lump sum contract or “fixed fee contract” is a traditional means of procurement in which a single “lump sum” price for all of the works is agreed upon before the works starts
Please explain your role on the project of ‘Commercial and Contract
Administration’.
I was involved in reviewing IPA from the Contractor and providing recommendation to the Client.
Also, Valuing Variation & Claim and providing recommendation.
What did ‘tracking and reporting the status of the change accurately’
require?
Any Change from the Contractor , Client had to be initiated through the Oracle system( APMS) and responded …………………………………………………………………………………………………………………………………………………………………..
Give an example of how you were ‘providing adequate control
over the usage of budget contingencies’.
………………………………………………………………………………………………………………………………………………………………….
What handover and closure process did you apply on this project
Not involved in the closing period………………………………………………………………………………………………
How did you respond to the contractors financial issues, to
complete the project and achieve the key objective (time of
completion)
……………………………………………………………………………………………………………………………………………………………………………..
How could you have avoided this financial issue?
financial checks to be completed as part of the
procurement process?
How can a cashflow support management of contractor financial
stability?
Businesses need cash to fund new projects, keep current projects moving forward, pay for materials and labor and cover other costs…….
How was the key issue related to the contractors financial issues
Stoppage of work at Site was due to the contractor not paying the sub contractor & outsourced labour at site.
What substantiation was the contractor contractually bound to provide in
order to receive payment?
CC to provide IR with Code A & B
On what basis did you withhold payment?
Payment for IR with Code C & D was withheld.
Were there any signs on the project that could have highlighted resource
allocation issues earlier?
No
How were you able to assess the impact of covid in this issue, compared
to misallocation of resources and/or issues due to contractor financial
issues?
The period of the key issue was during the ease of Covid situation. Moreover, ……………………………………………….
Page 2
Option 1: On-Account Payment for Variation under process
Which issue was this option aimed to solve (covid, misallocation of
resources, contractor financial issues)?
Contractor financial issues
How would this option have resolved the identified key issue of
resource management?
By improving the cashflow, & subsequently payment to the subcontractor & resumption of work at Site.