Case Study Flashcards

1
Q

Please explain what you mean by the ‘Lump Sum’ contract form.

What standard form of contract is this?

A

What Is a Lump Sum Contract? Under a lump sum contract, also known as a stipulated sum contract, the project owner provides explicit specifications for the work, and the contractor provides a fixed price for the project

What standard form of contract is this?

A lump sum contract or “fixed fee contract” is a traditional means of procurement in which a single “lump sum” price for all of the works is agreed upon before the works starts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Please explain your role on the project of ‘Commercial and Contract
Administration’.

A

I was involved in reviewing IPA from the Contractor and providing recommendation to the Client.
Also, Valuing Variation & Claim and providing recommendation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What did ‘tracking and reporting the status of the change accurately’
require?

A

Any Change from the Contractor , Client had to be initiated through the Oracle system( APMS) and responded …………………………………………………………………………………………………………………………………………………………………..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Give an example of how you were ‘providing adequate control
over the usage of budget contingencies’.

A

………………………………………………………………………………………………………………………………………………………………….

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What handover and closure process did you apply on this project

A

Not involved in the closing period………………………………………………………………………………………………

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How did you respond to the contractors financial issues, to
complete the project and achieve the key objective (time of
completion)

A

……………………………………………………………………………………………………………………………………………………………………………..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How could you have avoided this financial issue?

A

financial checks to be completed as part of the
procurement process?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How can a cashflow support management of contractor financial
stability?

A

Businesses need cash to fund new projects, keep current projects moving forward, pay for materials and labor and cover other costs…….

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How was the key issue related to the contractors financial issues

A

Stoppage of work at Site was due to the contractor not paying the sub contractor & outsourced labour at site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What substantiation was the contractor contractually bound to provide in
order to receive payment?

A

CC to provide IR with Code A & B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

On what basis did you withhold payment?

A

Payment for IR with Code C & D was withheld.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Were there any signs on the project that could have highlighted resource
allocation issues earlier?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How were you able to assess the impact of covid in this issue, compared
to misallocation of resources and/or issues due to contractor financial
issues?

A

The period of the key issue was during the ease of Covid situation. Moreover, ……………………………………………….

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Page 2

Option 1: On-Account Payment for Variation under process

Which issue was this option aimed to solve (covid, misallocation of
resources, contractor financial issues)?

A

Contractor financial issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How would this option have resolved the identified key issue of
resource management?

A

By improving the cashflow, & subsequently payment to the subcontractor & resumption of work at Site.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How did this help you achieve your key objective of delivering on
time?

A

By improving the cashflow, & subsequently payment to the subcontractor & resumption of work at Site.

17
Q

How did this impact cost, quality and risk of the project?

A

This helped to mitigate any delay to the project & subsequent cost overrun & to finish the work as per the required specs.

Imp:
Option 1: On-Account Payment for Variation under process
Risk-……………………….

Option 2: Providing an Advance Payment for the Remaining Work
Risk-……………………….

Option 2: Full Payment for the completed works with Code B IR’
Risk-……………………….

18
Q

What is required contractually to make a payment for a variation?
( Clarify Jibr, Sal)

A

Work to be completed at Site & the CC to submit the IRs with Code A

19
Q

What is required contractually to make an advance payment

A

This should be incorporated as an addendum to the Contract.

20
Q

Full Payment for the completed works with Code B IR’
How would this option have been managed contractually?
( Clarify Ifha)

A

By approval from the Client; & CC to provide an undertaking letter to convert the IRs to Code A (for which have been paid 100%) within the stipulated date. Failure to do so, payment to be withheld.

21
Q

How did your options manage risk on your project?

  • What risks did your options add to the project?
  • Did your option analysis and advice achieve the key objective of
    the project – delivery on time
A

How did your options manage risk on your project?

Mitigated delay and subsequent cost over run.

Complete the work as per the specs.

What risks did your options add to the project?

Option 3 Risk- Challenge to get the cc to convert the IRS into Code A ( by addressing & resolving the minor & major comments in the IR’s)

Did your option analysis and advice achieve the key objective of
the project – delivery on time?

Yes

22
Q

What would you do differently next time

A

Although this is a financial issue. however this could be expediated by the timely resolution of technical issues both both the Teams. Involving technical Team heads early on.

(If involved early on in a project, check the Financial Status of the CC.

Experienced & reputed Contactor.

23
Q

How did you act ethically?

A

I have ensured the CC meet the Contractual obligation under the Contract & provide proper substantiation & records required as per the Contract. I took a collaborative approach in the resolution of Key issue by involving the different Team members based on mutual respect & responsibility & ownership of Task.

(The Rules of Conduct are based on ethical principles of honesty, integrity, competence,
service, respect, and responsibility.)

24
Q

What were your key achievements?

A

Facilitate better Communication with CC commercial Team.

Coordinate meeting , workshops in the resolution of the key issue.

Involve the discipline Heads & Senior Management in the resolution of Technical issues.

Proactive &robust approach to ensure the conversion of Code B IR’s.