Case Law Flashcards
Week 1 - Obligations - 4 cases
1) Wells v Army & Navy Co-operative Society (1902)
2) Glenlion Construction Ltd v The Guinness Trust (1987)
3) Greater Glasgow Health Board v Keppie Henderson Partners (1989)
4) Independent Broadcasting Authority v EMI Electronics Ltd & BICC Construction Ltd (1980)
Week 2 - Time - 6 cases
1) Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970)
2) Hadley v Baxendale (1854)
3) Clydebank Engineering & Shipbuilding Co Ltd v Don Jose Rame Yzqierdo y Castenada (1905)
4) Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd (1915)
5) Parking Eye v Beavis (2015)
6) City Inn Ltd v Shepherd Construction Ltd (2010)
Week 3 - Certification - 4 cases
1) Northern Regional Health Authority v Derek Crouch Construction Co Ltd (1984)
2) Beaufort Developments (NI) Ltd v Gilbert Ash (NI) Ltd (1998))
3) Crown Estates Commissioners v John Mowlem & Co Ltd (1994)
4) Firholm Builders Ltd v McAuley (1982)
Week 4 - Instructions & Variations - 1 case
1) Williams v Fitzmaurice (1858)
Week 5 - Payment - 4 cases
1) Charles Gray & Son Ltd v Stern (1953)
2) Ramsay & Son v Brand (1898)
3) Stirling County Council v Official Liquidator of John Frame Ltd (1951)
4) S&T (UK) Ltd v Grove Developments Ltd (2018)
Week 6 - Subs & Suppliers - 3 cases
1) Scott Lithgow v GEC Electrical Projects Ltd (1992)
2) Archivent Sales and Developments Ltd v Strathclyde Regional Council (1985)
3) Blyth & Blyth Ltd v Carillion Construction (2002)
Week 7 - Suspension & Termination - 2 cases
1) White & Carter (Councils) Ltd v McGregor (1962)
2) Melville Dundas (in receivership) Ltd v George Whimpey Ltd (2007))
Week 8 - Remedies - 5 cases
1) Balfour Beatty Construction (Scotland) Ltd v Scottish Power PLC (1994)
2) Ruxley Electronics and Construction Ltd v Forsyth (1995)
3) FG Minter Ltd v Welsh Health Technical Services Organisation (1980)
4) Ogilvie Builders Ltd v City of Glasgow District Council (1995)
5) Redpath Dorman Long Ltd v Tarmac Construction Ltd (1982)
Week 9 - Insurances - 3 cases
1) Scottish Special Housing Association v Wimpey Construction UK Ltd (1986)
2) British Telecommunications PLC v James Thomson & Sons (Engineers) Ltd (1999)
3) Aberdeen Harbour Board v Heating Enterprises (Aberdeen) Ltd (1990)
Week 10 - Rights for third parties - no cases
None
Week 11 - Liability in delict - 12 cases
1) Donoghue v Stevenson (1932)
2) Spartan Steel & Alloys Ltd v Martin & Co (Contractors) Ltd (1972)
3) Dutton v Bognor Regis (1972)
4) Anns v Merton LBC (1977)
5) Junior Books v The Veitchi Co Ltd (1982)
6) Peabody Donation Fund (Governors of) v Sir Lindsay Parkinson & Co (1985)
7) Simaan General Contracting Co v Pilkington Glass Ltd (1988)
8) D&F Estates Ltd v Church Commissioners (1989)
9) Parkhead Housing Association v Phoenix Preservation Ltd (1990)
10) Murphy v Brentwood DC (1991)
11) Dynamco v Holland Hannen & Cubitts Ltd (1971)
12) Stevenson v A&J Stephen (Builders) Ltd (1996)
Wells v ? (1902)
Army ‘&’ Navy Co-operative Society
? v Army ‘&’ Navy Co-operative Society (1902)
Wells
Wells v Army ‘&’ Navy Co-operative Society (?)
1902
Wells v Army ‘&’ Navy Co-operative Society (1902)
Tag line - TIme at large
Key issue - Employer unable to hold contractor to LDs for being late
Particulars;
• Works to be completed within a year.
• Works completed 1 year late.
• Delays not contractors fault.
• Delays mainly due to late possession of site, late issue of architects info, other contractors.
• No mechanisms in contract to extend duration.
• Time at large
Glenlion Construction Ltd v ?
1987
The Guinness Trust
? v The Guinness Trust
1987
Glenlion Construction Ltd
Glenlion Construction Ltd v The Guinness Trust
?
1987
Glenlion Construction Ltd v The Guinness Trust
(1987) 39 BLR 89
Tag line - Contractor’s early finish
Key issue - Contract completion - architect under no obligation to assist contractor in early completion
Particulars;
• Contract called for contractor to complete “on or before” date for completion
• Programmed to finish early
• Contractor unable to finish early due to timing of issue of architects info
• Contractor claimed loss / expense
• Lost
• Architect under no obligation to issue information in time to allow early finish - only in time to allow completion by date of completion
Greater Glasgow Health Board v ? (1989)
Keppie Henderson Partners
? v Keppie Henderson Partners (1989)
Greater Glasgow Health Board
Greater Glasgow Health Board v Keppie Henderson Partners (?)
1989
Greater Glasgow Health Board v Keppie Henderson Partners (1989) SLT 387
Tag line - Defective heating design
Key issue - Contractor deemed not responsible for design defects
Particulars;
• Defective heating system due to spec’d mats not being of a reasonable quality and design / mats not being of reasonable suitably.
• Selection of mats / design not down to contractor.
• Contractor only responsible for quality of workmanship - “reasonable skill and care”.
• “Fit for purpose” (e.g. that system would work) would not apply as no design responsibility.
Independent Broadcasting Authority v ? (1980)
EMI Electronics Ltd and BICC Construction Ltd
? v EMI Electronics Ltd and BICC Construction Ltd (1980)
Independent Broadcasting Authority
Independent Broadcasting Authority v EMI Electronics
Ltd and BICC Construction Ltd (?)
1980
Independent Broadcasting Authority v EMI Electronics
Ltd and BICC Construction Ltd (1980) 14 BLR 1
Tag line - Unfit for purpose mast
Key issue - D&B contractor responsible for “fit for purpose”
Particulars;
• Contractor engaged to D&B aerial mast at Emory Moor.
• IBA had advised what they were looking for and use but no other info.
• IBA had another mast at Winter Hill violently oscillate and wrote to BICC to confirm this would not happen.
• BICC confirmed would be designed to avoid this (and implied it would be fit for purpose)
• Some time after completion mast fell down due to asymmetrical ice loading and vortex shedding
• BICC responsibility to re-build etc.
Peak Construction (Liverpool) Ltd v ? (1970)
McKinney Foundations Ltd
? v McKinney Foundations Ltd (1970)
Peak Construction (Liverpool) Ltd
Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (?)
1970
Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970)
Tag line - Defective pile & time at large
Key issue - No provision in contract for EOT due to employer delay
Particulars;
• Peak bespoke contract (weighted very much in their favour) used - not standard contract.
• McKinney D&B contractor for piling.
• McKinney complete and off site.
• Major defect found with 1 pile and a number of minor defects with other piles.
• Peak took 58 weeks to decide on solution to rectify.
• Actual remedial works took 6 weeks.
• Peak tried to apply damages.
• Found no mechanism in contract to grant EOT in contract due to delay caused by employer so LDs could not be applied - contractor given reasonable time to complete - time at large.
Hadley v ? (1854)
Baxendale
? v Baxendale (1854)
Hadley
Hadley v Baxendale (?)
1854
Hadley v Baxendale (1854)
Tag line - Crankshaft and remoteness of damages
Key issue - Remoteness of damages
Particulars;
• Hadley owned mill powered by steam engine which broke down due to broken crank shaft.
• Baxendale hired to take old crankshaft to manufacturer long distance away so that replacement could be made and deliver said replacement to Hadley.
• Agreed to deliver by 2nd day of receiving replacement.
• Took 7 days.
• Hadley’s mill at stand still the entire time - unbeknown to Baxendale.
• Hadley tried to sue for loss of earning etc.
• Baxendale argued he was unaware of this and would have delivered sooner had he known.
• Decision that Baxendale should be liable for the ordinary / generic damages i.e. those which would be normal for standard breach of contract.
• Decided as Baxendale was unaware that mill would be at a standstill not liable of special, consequential or collateral losses - should have been communicated at time of contracting.
Clydebank Engineering and Shipbuilding Co Ltd v ? (1905)
Don Jose Rame Yzquierdo y Castaneda
? v Don Jose Rame Yzquierdo y Castaneda (1905)
Clydebank Engineering and Shipbuilding Co Ltd
Clydebank Engineering and Shipbuilding Co Ltd v Don Jose Rame Yzquierdo y Castaneda (?)
1905
Clydebank Engineering and Shipbuilding Co Ltd v Don Jose Rame Yzquierdo y Castaneda (1905)
Tag line - The Castaneda & LDs
Key issue - Liquidated Damages
Particulars;
• Contract to build and deliver war ships with LDs of £500 per vessel per week.
• Contract complete, contract sum paid in full, boats delivered late.
• Spanish government submit claim for LDs
• Clyde make 3 arguments; (1) LDs could not be applied as warships do not generate profit therefore no loss (2) Had they been delivered on time they would have likely been sunk like the rest of the Spanish Navy during the Spanish-American War (3) Contract sum paid in full meant right to claim LDs had been waived.
• Decided (1) LDs did apply and were not a penalty (2) Irrelevant (3) Full payment of contract sum is not a waiver.
Dunlop Pneumatic Tyre Co Ltd v ? (1915)
New Garage & Motor Co Ltd
? v New Garage & Motor Co Ltd (1915)
Dunlop Pneumatic Tyre Co Ltd
Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd (?)
1915
Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd (1915)
Tag line - Sales agreement and LDs
Key issue - Liquidated damages - penalty or LDs?
Particulars;
• Dunlop manufactured and supplied various items to New Garage.
• Agreed in contract that New Garage would pay £5 in LDs for every item sold or offered in breach of their agreement.
• New Garage breached various times and Dunlop claimed LDs.
• New Garage argued these were penalties and not LDs.
• Found that Dunlop was correct.
• LDs were clarified as follows; LD should be genuine and fair pre-estimate of damage decided upon at the time of making the contract, not at time of breach.
Parking Eye v ? (2015)
Beavis
? v Beavis (2015)
Parking Eye
Parking Eye v Beavis (?)
2015
Parking Eye v Beavis (2015)
Tag line - Parking fine: penalty or damage
Key issue - Liquidated Damages - Penalty or LD?
Particulars;
• Parking eye managed car park.
• Beavis overstayed by 1 hour despite warning signage - received £85 charge.
• Beavis argued unenforceable as charge was a penalty under common law and / or unenforceable under the “Unfair Terms in Consumer Contracts Regulations 1999”.
• Parking Eye won.
• Found that Parking Eye and the landowners had a legitimate interest in charging overstaying motorists, which extended beyond the recovery of any loss. It was an economic entity which required to be protected (through charge). £85 charge neither extravagant nor unconscionable therefore was not a penalty.
City Inn Ltd v ? (2010)
Shepherd Construction Ltd
? v Shepherd Construction Ltd (2010)
City Inn Ltd
City Inn Ltd v Shepherd Construction Ltd (?)
2010
City Inn Ltd v Shepherd Construction Ltd (2010)
Tag line - Shared delays
Key issue - Concurrent delays / apportionment of delays
Particulars
• Contract to build new hotel in Bristol.
• Architect issued late instructions but failed to issue EOT on grounds that contractor already late.
• Found that delay could be shared.
• Where there are competing causes but a dominant cause can be established then that cause determines if an EOT can be granted.
• Where a dominant cause cannot be established then delay can be apportioned between them.
Northern Regional Health Authority v ? (1984)
Derek Crouch Construction Co Ltd
? v Derek Crouch Construction Co Ltd (1984)
Northern Regional Health Authority
Northern Regional Health Authority v Derek Crouch Construction Co Ltd (?)
1984
Northern Regional Health Authority v Derek Crouch Construction Co Ltd (1984)
Tag line - Power with arbitrator or court
Key Issue - Courts Powers
Particulars;
• Issues arose around lack of instructions for certain sections of the works and the values being certified.
• Contract allowed for issues to be taken to arbitrator only.
• Only able to go to arbitration after PC.
• Decided that contractor unable to take matters to court as the power had been conferred to the arbitrator and could not be held by both the arbitrator and the courts.
• This was the basis for the next 14 years until Beaufort Developments (NI Ltd) v Gilbert Ash (NI) Ltd (1998)
• Duncan Wallace argued re this for the entire 14 year process
Beaufort Developments (NI Ltd) v ? (1998)
Gilbert Ash (NI) Ltd
? v Gilbert Ash (NI) Ltd (1998)
Beaufort Developments (NI Ltd)
Beaufort Developments (NI Ltd) v Gilbert Ash (NI) Ltd (?)
1998
Beaufort Developments (NI Ltd) v Gilbert Ash (NI) Ltd (1998)
Tag line - Power with arbitrator and court
Key Issues - Courts Powers
Particulars;
• Overturned Norther Regional Health Authority v Derek Crouch Construction Co Ltd (1984)
• Practical completion on project was delayed.
• Contractor served notice of arbitration.
• Employer claimed damages against contractor and architect.
• Court could hold power same power as arbiter.
• Meant certificates could be challenged right away and did not have to wait for arbitration (starting after PC).
Crown Estates Commissioners v ? (1994)
John Mowlem & Co Ltd
? v John Mowlem & Co Ltd (1994)
Crown Estates Commissioners
Crown Estates Commissioners v John Mowlem & Co Ltd (?)
1994
Crown Estates Commissioners v John Mowlem & Co Ltd (1994)
Tag line - English broad view on conclusivity
Key Issues - Final Certificates (Conclusivity)
Particulars;
• Mowlem employed to construct development on site of former Chelsea Palace Barracks.
• Final cert isssued.
• 4 months later further defects issued to Mowlem who argued too late, not their problem as final cert issued.
• Decided final cert was conclusive evidence that all works fully complete
• Case in English law, takes broad view on Conclusivity of final cert
Firholm Builders Ltd v ? (1982)
McAuley
? v McAuley (1982)
Firholm Builders Ltd
Firholm Builders Ltd v McAuley (?)
1982
Firholm Builders Ltd v McAuley (1982)
Tag line - Scottish narrow view on conclusivity
Key Issues - Final Certificate (Conclusivity) & Set-Off
Particulars;
• Main contractor claimed balance of monies due under contract after issue of final certificate
• Employer tried to off-set cost of defective works.
• Found that unlike in Crown Estates v John Mowlem, final cert does not offer Conclusivity all works are defect free.
• Final cert is evidence that architect was reasonably satisfied works were complete however employer could still argue architect ought not to have been satisfied.
• Case in Scots law which demonstrates more narrow view on Conclusivity.
Williams v ? (1858)
Fitzmaurice
? v Fitzmaurice (1858)
Williams
Williams v Fitzmaurice (?)
1858
Williams v Fitzmaurice (1858)
Tag line - House with no floor boards
Key Issues - True lump sum contract
Particulars;
• Williams engaged to build a house for Fitzmaurice
• Carried out under true lump sum contract
• Spec / drawings didn’t detail any floorboards
• Bottom of spec Williams had signed memorandum agreeing that house would “be completed and fit for occupation” by a specified date
• Williams tried to claim extra for floorboards
• Deemed included as house unfit for occupation without floorboards
• Would have been a variation if under a SBC
Charles Gray & Son Ltd v ? (1953)
Stern
? v Stern (1953)
Charles Gray & Son Ltd
Charles Gray & Son Ltd v Stern (?)
1953
Charles Gray & Son Ltd v Stern (1953)
Tag line - Common law interim payment
Key Issues - Common law no implied right to interim payment
Particulars;
• Charles Gray house builders
• Contracted to sub divide house
• Ad hoc contract - not standard building contract
• No express terms agreed for interim payment
• At end of first month Charles Gray applied for money
• Mr Stern refused
• Charles Gray sued for payment
• Held Charles Gray had no right to interim payment and had failed to carry out material part of contract