Name the Process Groups
- Initiating
- Planning
- Executing
- Monitoring & Controlling
- Closing
Name the Knowledge Areas
- Integration Management
- Scope Management
- Time Management
- Cost Management
- Quality Management
- Human Resource Management
- Communications Management
- Risk Management
- Procurement Management
- Stakeholder Management
What are the Processes and Knowledge Areas involved with “Initiating”?
Process (Knowledge Area):
- Develop Project Charter (Integration)
- Identify Stakeholders (Stakeholder)
What are the Processes involved with “Planning” for the Integration and Scope Knowledge Areas?
Process (Knowledge Area):
- Develop Project Management Plan (Integration)
- Plan Scope Management (Scope)
- Collect Requirements (Scope)
- Define Scope (Scope)
- Create WBS
What are the Processes involved with “Planning” for the Time Knowledge Area?
Process (Knowledge Area):
- Plan Schedule Management (Time)
- Define Activities (Time)
- Sequence Activities (Time)
- Estimate Activity Resources (Time)
- Estimate Activity Durations (Time)
- Develop Schedule (Time)
What are the Processes involved with “Planning” for the Cost, Quality, HR, and Communications Knowledge Areas?
Process (Knowledge Area):
- Plan Cost management (Cost)
- Estimate Costs (Cost)
- Determine Budget (Cost)
- Plan Quality Management (Quality)
- Plan Human Resource Management (HR)
- Plan Communication Management (Communications)
What are the Processes involved with “Planning” for the Risk, Procurement, and Stakeholder Knowledge Areas?
Process (Knowledge Area):
- Plan Risk Management (Risk)
- Identify Risks (Risk)
- Perform Qualitative Risk Analysis (Risk)
- Perform Quantitative Risk Analysis (Risk)
- Plan Risk Responses (Risk)
- Plan Procurement Management (Procurement)
- Plan Stakeholder Management (Stakeholder)
What are the Processes involved with “Executing” for the Integration, Quality, and HR Knowledge Areas?
Process (Knowledge Area):
- Direct and Manage Project Work (Integration)
- Perform Quality Assurance (Quality)
- Acquire Project Team (HR)
- Develop Project Team (HR)
- Manage Project Team (HR)
What are the Processes involved with “Executing” for the Communications, Procurement, and Stakeholder Knowledge Areas?
Process (Knowledge Area):
- Manage Communications (Communications)
- Conduct Procurements (Procurement)
- Manage Stakeholder Engagement (Stakeholder)
What are the Processes involved with “Monitoring & Controlling” for the Integration, Scope, Time and Cost Knowledge Areas?
Process (Knowledge Area):
- Monitor & Control Project Work (Integration)
- Perform Integrated Change Control (Integration)
- Validate Scope (Scope)
2 Control Scope (Scope) - Control Schedule (Time)
- Control Costs (Cost)
What are the Processes involved with “Monitoring & Controlling” for the Quality, Communications, Risk, Procurement, and Stakeholder Knowledge Areas?
Process (Knowledge Area):
- Control Quality (Quality)
- Control Communications (Communications)
- Control Risks (Risk)
- Control Procurements (Procurement)
- Control Stakeholder Engagement (Stakeholder)
What is a Project Management Plan?
The single, approved document that will guide the project’s execution and control
What are the ITOs for “Develop Project Management Plan”?
Inputs:
None
Tools:
None
Outputs:
Project Management Plan
What is a “Project Charter”?
Creates the official project through the development of the project charter
What are the ITOs for “Develop Project Charter”?
Inputs:
Project Statement of Work (SOW)
Business Case
Tools:
None
Outputs:
Project Charter