CAPM Module 5, 6 & 7 Flashcards

CAPM Prep

1
Q

Which of the following best describes a project life cycle?

A

A series of phases that a project passes through from its initiation to its closure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the primary purpose of a project phase?

A

To divide the project into manageable sections.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which organizational structure is characterized by a strong project manager authority and a full-time project management administrative staff?

A

Projectized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In a functional organizational structure, who has the most authority?

A

Functional Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which development approach is best suited for projects with high uncertainty and frequent changes?

A

Agile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a key characteristic of the agile development approach?

A

Flexibility to changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which of the following is NOT a project performance domain?

A

Marketing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the main focus of the scope performance domain?

A

Defining and controlling what is included in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which document formally authorizes a project?

A

Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the purpose of a project management plan?

A

To guide project execution and control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following best describes a project environment?

A

The cultural, social, and political context within which the project operates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In a matrix organizational structure, who shares authority over the project team?

A

Project Manager and Functional Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which phase of the project life cycle typically involves the most resource allocation?

A

Execution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the primary output of the planning phase in a project?

A

Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which of the following is a key benefit of using a predictive development approach?

A

Detailed upfront planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the main objective of the execution phase in a project?

A

To complete the project work as defined in the project management plan

17
Q

Which organizational structure is most likely to have a project manager with limited authority?

A

Functional

18
Q

What is the primary focus of the delivery performance domain?

A

Ensuring the project delivers the intended value

19
Q

Which document outlines the project’s objectives, deliverables, and key milestones?

A

Project Charter

20
Q

What is the main purpose of the closing phase in a project?

A

To formally close the project and hand over deliverables

21
Q

You are managing a project in a matrix organizational structure where both you and the functional manager share authority over the project team. During a critical phase, you notice that team members are receiving conflicting instructions from the functional manager and yourself. What is the best course of action to resolve this issue?

A

Schedule a meeting with the functional manager to clarify roles and responsibilities.

22
Q

Your project involves developing a new software application, and the requirements are not fully defined. The client expects frequent changes and rapid delivery of functional components. Which development approach should you recommend to best meet the client’s needs?

A

Agile

23
Q

During the planning phase of your project, you are tasked with defining the project scope. The project sponsor insists on including several features that are not aligned with the project’s objectives. How should you handle this situation to ensure the project scope remains focused?

A

Explain the impact of the additional features on the project’s objectives and negotiate a focused scope.

24
Q

You are managing a project that is currently in the execution phase. The project sponsor requests a significant change that will impact the project scope and timeline. What is the best course of action to handle this request?

A

Evaluate the impact of the change and follow the change control process.

25
Q

During the initiation phase of a project, you are tasked with identifying key stakeholders. One of the stakeholders is resistant to the project and has a history of opposing similar initiatives. How should you manage this stakeholder?

A

Engage the stakeholder early and address their concerns.