CAPM MOD-7 Flashcards

1
Q

(5) Steps to Create Budget

A
  • Cost estimate
  • Add Up Activities (Cost Baseline)
  • Add Reserves
  • Liaison w/Senior Management
  • Present for Approval
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What Effect can multiple critical paths have?

A

Higher level of risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are critical activities?

A
  • Vital to project schedule success
  • May not be on critical path
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Ho do you find critical path?

A

Path w/most days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does not have any float?

A

Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Float

A

Time in activity can be delayed/extended without delaying finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Critical path

A
  • Longest Path
  • Shortest Duration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What effect does crashing usually have on project?

A

Increases project costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Fast Tracking

A

Overlapping Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Crashing

A

Adding People/Equipment to Critical Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does negative float mean?

A

Dates not feasible without changing plan?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you calculate float?

A

Early finish date - Late finish date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you perform backward pass?

A
  • Assign finish date to end milestone
    _ Each activity gets start/finish
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does backward pass represent?

A

Late start/finish dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How do you do a forward pass?

A
  • Assign start date to start milestone
  • Left to right
  • Assign start/finish dates to each activity/milestone
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does a forward pass represent?

A
  • Earliest possible finish date
  • Shortest duration
17
Q

(3) Steps to estimated durations

A
  1. Forward pass
  2. Backward pass
  3. Calculate float
18
Q

Except for first/last milestone, what must every milestone/activity be connected by?

A
  • Predecessor
  • One successor
19
Q

Does a milestone have durations/resources assigned?

A

No

20
Q

Steps to develop a project schedule? (1-3)

A
  1. Identify milestones
  2. Specify activities (WBS)
  3. Sequence (Put in order)
21
Q

Steps to develop a project schedule? (4-5)

A
  1. Estimate resources
  2. Determine Duration
22
Q

What does a schedule depend on?

A

Creating a WBS

23
Q

What is a Work Breakdown Structure?

A
  • Total Scope of work to be completed by team
  • Break down into individual tasks
24
Q

Scope creep

A

uncontrolled scope expansion w/out changes on schedule or budget

25
Q

What does scope define?

A

What is to be delievred

26
Q

(3) Types of baselines found in project management plan

A
  1. Scope baseline
  2. Schedule baseline
  3. Cost baseline
27
Q

What type of approach uses a project management plan?

A

Predictive

28
Q

Time Materials contract

A
  • Cost-Reimbursable
  • Fixed Price
29
Q

Cost-Plus Contact

A
  • Seller pays for actual costs
    AND
  • Fee for sellers profit
30
Q

(3) Types of procurement contracts

A
  • Fixed Price
  • Cost Plus
  • Time/Materials
31
Q

First step in planning for resources

A

Estimate activity resources

32
Q

What can PM tailor in predictive approach?

A
  1. Engagement
  2. Tools
  3. Methods
  4. Processes
33
Q

What approach for intangible products?

A

Agile

34
Q

What approach for physical products?

A

Predictive

35
Q

What factors should you consider when tailoring a predictive life cycle?

A
  1. Product/Deliverable
  2. Project Team
  3. Culture
36
Q

Importance of charter (1-3)

A
  1. Authorizes start
  2. High Level requirements
  3. Shared understanding
37
Q

Importance of charter (4-5)

A
  1. Identify stakeholders
  2. How project links to ongoing work