CAPM Keywords Flashcards
To memorize key terms from glossary in PMBOK 6th edition.
Within the quality management system, this is an assessment of correctness.
Accuracy
The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.
Acquire Resources
Obtaining human and material resources necessary to perform project activities. *It applies a cost of resources, and is not necessarily financial.
Acquisition
A distinct, scheduled portion of work performed during the course of a project.
Activity
AON
Activity-on-Node (AON)
The realized cost incurred for the work performed on an activity during a specific time period.
Actual Cost (AC)
The time in calendar units between the actual start date of the schedule activity and either the data date of the project schedule if the schedule activity is in progress or the actual finish data if the schedule activity is complete.
Actual Duration
A project life cycle that is iterative or incremental.
Adaptive Life Cycle
A technique that allows large numbers of ideas to be classified into groups for review and analysis.
Affinity Diagrams
Any document or communication that defines the initial intentions of a project.
Agreements
A technique used to evaluate identified options in order to select the options or approaches to use to execute and perform the work of the project.
Alternative Analysis
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
Analogous Estimating
Various techniques used to evaluate, analyze, or forecast potential outcomes based possible variations of project or environmental variables and their relationships with other variables.
Analytical techniques
A factor in the planning process that is considered to be true, real, or certain, without proof or demonstration.
Assumption
A project document used to record all assumptions and constraints throughout the project life cycle.
Assumption log
Method of measuring quality that consists of noting the presence (or absence) of some characteristic (attribute) in each of the units under consideration.
Attribute Sampling
A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date.
Backward Pass
A graphic display of schedule-related info.
Bar chart
The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.
Baseline
Supporting documentation outlining the details used in est. project estimates such as assumptions, constraints, level of detail, ranges, and confidence levels.
Basis of Estimates
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS).
Bottom-Up Estimating
The sum of all budgets established for the work to be performed.
Budget at Completion (BAC)