CAPM I phone APP Cost Managment Flashcards

Project Cost MGT

1
Q

Cost baseline

A

Answer: A time-lapse exposure of when the project monies are to be spent in relation cumulative values of the work completed in the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned value Rules

A

Answer: 1. Earned value Management Computation formulas or determining the estimate to complete are defined. 2. Earned value credit criteria are established.3. Define the WBS level at which earned value technique analysis will be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value Technique

A

Answer: Compares planned performance to actual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Scheduled Variance (SV)

A

Answer: The difference between the earned value and the planned value. The formula is SV = EV - PV.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the range for a rough order of magnitude estimate?

A

Answer: +/-50% from actual.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Bottom-Up Estimating

A

Answer: Start by estimating the work packages with the lowest level of detail and work your way up.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the formula for TCPI?

A

Answer: (BAC - EV)/(BAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost Change Control System:

A

Answer: A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In which process is the cost management plan created?

A

Answer: In integration management as part of the Develop Project Management Plan process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost Budgeting:

A

Answer: Aggregating the estimated costs of individual activities or work packages to establish a cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cost Aggregation:

A

Answer: Cost are parallel to each WBS work package. The cost of each work package are aggregated to their corresponding control accounts. Each control account then is aggregated to the sum of the project cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost baseline

A

Answer: Time-phased budget that is used in a basis against which to measure, monitor, and control overall performance on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Variance

A

Answer: The difference between what is expected and what was experience

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Direct Cost

A

Answer: Cost are attributed directly to the project work and cannot be shared among projects. (For example, airfare, hotels, long distance phone charges, and so on).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Variance =

A

Answer: Variance = BAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly